BLD-Final | 11/5/2018 | 11/8/2018 | 11/8/2018 | P | PASS |
Mike Jordan
|
|
|
Please call me when you''re expected to be on site and I will meet you there. Phone #: ###-#### Inspection requested via web by Stephen Lee
|
DOC - Permit Finaled | 11/8/2018 | 11/8/2018 | 11/8/2018 | P | PASS |
Mike Jordan
|
|
|
All issues have been resolved. ok for final.
|
BLD-Conference | 10/31/2018 | 10/31/2018 | 10/31/2018 | P | PASS |
Mike Jordan
|
|
|
Review of fire shaft and first layer of fire rated gypsum board. Work commences at 8:30, please call if you have time earlier to stop by. If first layer is installed, will call to have you come by an inspect. Phone #: ###-#### Inspection requested via web by Stephen Lee
|
BLD-Conference | 9/29/2018 | 10/1/2018 | 10/1/2018 | A | PASS |
Mike Jordan
|
|
|
Please call prior to arrival, I will meet you onsite. Earlier in the AM preferred. Phone #: ###-#### Inspection requested via web by Stephen Lee. Angle supports added per plan and noted special inspection reports. Ok to fire proof new supports.
|
BLD-Conference | 9/27/2018 | 9/28/2018 | 9/28/2018 | P | CANC |
Mike Jordan
|
|
|
Please call prior to arrival and I will meet you onsite. This conference is for you to inspect the structural bracing that was just installed on 09/26/2018. Phone #: ###-#### >> Inspection requested via web by Stephen Lee Inspection cancelled from web by: Stephen Lee
|
BLD-Conference | 7/11/2018 | 7/12/2018 | 7/12/2018 | P | DONE |
Mike Jordan
|
|
|
afternoon between 1:45 and 3:45 for review of fire shaft correction notice. Please call me before you plan on going out so I can meet you there. Phone #: ###-#### Inspection requested via web by Stephen Lee. Discussed repairs with contractor and their proposed solutions prior to moving foward.
|
BLD-Conference | 7/10/2018 | 7/11/2018 | 7/11/2018 | P | CANC |
Mike Jordan
|
|
|
Reschedule for tomorrow afternoon between 1:45 and 3:45 for review of fire shaft correction notice. Please call me before you plan on going out so I can meet you there. Phone #: ###-#### Inspection requested via web by Stephen Lee. rescheduled for tomorow afternoon.
|
BLD-Conference | 7/10/2018 | 7/11/2018 | 7/10/2018 | A | CANC |
Mike Jordan
|
|
|
Please call Stephen prior to heading over, I will meet you onsite. The site is available to meet between 8:45 am to 10:45 am. in the morning, if those times do not work for your schedule then we have another window between 1:45 to 3:45 in the afternoon. This is to review the fire shaft correction notice. Phone #: ###-#### >> Inspection requested via web by Stephen Lee Inspection cancelled from web by: Stephen Lee
|
BLD-Final | 5/6/2018 | 5/9/2018 | 5/9/2018 | A | FAIL |
Mike Jordan
|
|
|
Please contact Stephen Lee when on your way, I will meet you there. Phone #: ###-#### Inspection requested via web by Stephen Lee. Provide the UL for the double wall grease duct from captive air showing 1hr. assembly and fireblock detail at penetrations. Make up air duct needs to be wrapped or in 1hr shaft for entire length. Provide UL and method for wrapping make up air duct and firestop details at penetrationns. Install all structural components as shown on Sheet A1-1.. Provide special inspection for epoxt bolting. correction notice issued.
|
FIRE-Final Inspection | 5/2/2018 | 5/3/2018 | 5/3/2018 | P | PASS |
Troy Cobbley
|
|
|
Life safety passed.
call on your way- Steve Phone #: ###-####
|