BLD-Final | 4/11/2018 | 4/11/2018 | 4/11/2018 | P | PASS |
Mike Jordan
|
|
|
Phone #: ###-#### Inspection requested via web by David Scaggs
|
BLD-Aging Inspection | 2/13/2018 | 2/13/2018 | 2/13/2018 | | PASS |
Mike Jordan
|
|
|
|
BLD-Final | 12/14/2017 | 12/15/2017 | 12/15/2017 | A | PASS |
Mike Jordan
|
|
|
Phone #: ###-#### Inspection requested via web by David Scaggs. Ok for temp. occ. Will be ok for perm. occ. once zoning and public works signs perm.
|
FIRE-Final Inspection | 12/14/2017 | 12/15/2017 | 12/15/2017 | A | PASS |
Troy Cobbley
|
|
|
Life safety passed
Phone #: ###-#### Inspection requested via web by David Scaggs
|
FIRE-Final Inspection | 12/14/2017 | 12/14/2017 | 12/14/2017 | P | FAIL |
Troy Cobbley
|
|
|
No city approved plans or notes on site. Need the GRD permit inspected/finaled. I did test all of the smoke alarms and verified fire extinguishers. Per conversation with Ron Johnson an address monument will be needed at the entrance to show the interior building addresses for the responding personell.
Phone #: ###-#### Inspection requested via web by David Scaggs
|
BLD-Final | 12/12/2017 | 12/13/2017 | 12/13/2017 | A | NR |
Mike Jordan
|
|
|
Please call contact number when complete so we can obtain physical sign off. Phone #: ###-#### Inspection requested via web by David Scaggs. Needs fire/life/safety finals and zoning.
|
BLD-Energy code compliance | 10/3/2017 | 10/3/2017 | 10/3/2017 | P | PASS |
Mike Jordan
|
|
|
Dave Phone #: ###-####
|
BLD-Energy code compliance | 10/2/2017 | 10/2/2017 | 10/2/2017 | P | NR |
Mike Jordan
|
|
|
David Phone #: ###-####
|
BLD-Framing/Rough-in | 9/28/2017 | 9/29/2017 | 9/29/2017 | A | PASS |
Brandon Shaw
|
|
|
Phone #: ###-#### Inspection requested via web by david scaggs
|
FIRE-Sprinkler Rough-in | 9/28/2017 | 9/28/2017 | 9/28/2017 | P | PASS |
Troy Cobbley
|
|
|
Rough-in passed. Tenting passed. Piping can be covered except for tie in area
|
BLD-Wall Bracing | 7/10/2017 | 7/11/2017 | 7/11/2017 | A | PASS |
Mike Jordan
|
|
|
Exterior shear Inspection requested via web by Marty Short
|
BLD-Footing | 6/9/2017 | 6/9/2017 | 6/9/2017 | P | PASS |
Brandon Shaw
|
|
|
Marty Phone #: ###-####
|
BLD-Footing | 6/8/2017 | 6/8/2017 | 6/8/2017 | P | FAIL |
Dave Hannah
|
|
|
Marty Phone #: ###-####
|
BLD-Energy code compliance | 6/6/2017 | 6/6/2017 | 6/6/2017 | P | PASS |
Mike Jordan
|
|
|
Marty Phone #: ###-####. Rigid insulation on stemwalls interior side under slab on grade.
|
BLD-Concrete | 5/23/2017 | 5/24/2017 | 5/24/2017 | P | CANC |
Mike Jordan
|
|
|
Wall // Marty Phone #: ###-####
|
BLD-Foundation | 5/24/2017 | 5/24/2017 | 5/24/2017 | P | PASS |
Mike Jordan
|
|
|
Wall // Marty Phone #: ###-####
|
BLD-Footing | 5/19/2017 | 5/22/2017 | 5/22/2017 | A | PASS |
Mike Jordan
|
|
|
Marty Phone #: ###-####
|