BLD-Final | 7/25/2017 | 7/26/2017 | 7/26/2017 | P | PASS |
Mike Jordan
|
|
|
Cameran Phone #: ###-####
|
DOC - Permit Finaled | 7/26/2017 | 7/26/2017 | 7/26/2017 | P | PASS |
Mike Jordan
|
|
|
All issues resolved. Flush bolts approved by plsn review.
|
BLD-Final | 7/16/2017 | 7/17/2017 | 7/17/2017 | P | PEND |
Mike Jordan
|
|
|
Please call Nic a half-hour before inspection. Phone #: ###-#### Inspection requested via web by Nic van Diepen. Architect to provide letter to building official for possible alternate for flush mounted locks on B occ. with 68 occupant load. Everything else ok.
|
FIRE-Final Inspection | 7/16/2017 | 7/17/2017 | 7/17/2017 | A | PASS |
Jim Page
|
|
|
No fire sprinklers, no fire alarms, fire extinguishers are in place with current inspection tags. Final life fire safety inspection passed/complete.
|
BLD-Framing/Rough-in | 5/12/2017 | 5/12/2017 | 5/12/2017 | P | PASS |
Dave Hannah
|
|
|
Please call Nic a half hour before inspection. Thanks, Phone #: ###-#### Inspection requested via web by Nic van Diepen
|
FIRE-Conference | 5/5/2017 | 5/8/2017 | 5/8/2017 | P | DONE |
Troy Cobbley
|
|
|
Conference to discuss existing mag lock installation at door #17. Please call Nic a half-hour before arriving. Thanks, Phone #: ###-#### Inspection requested via web by Nic van Diepen
|
BLD-Footing | 5/1/2017 | 5/2/2017 | 5/2/2017 | A | PASS |
Mike Jordan
|
|
|
Please call Nic 1/2 hr before inspection. Thanks, Phone #: ###-#### Inspection requested via web by Nic van Diepen. Interior ncolumn pad footings ok.
|
BLD-Conference | 4/28/2017 | 5/1/2017 | 5/1/2017 | A | DONE |
Mike Jordan
|
|
|
Please call Nic 1/2hr before estimated arrival at site. Conference to discuss access for inspection of nailing. Thanks, Phone #: ###-#### Inspection requested via web by Nic van Diepen
|