Permit Information
Permit NumberBLD17-01173
StatusFinaled
Name VAN AUKER CONSTRUCTION
Site Address 12248 W EXECUTIVE DR
Project NameCloverdale #12
Customer Number 
ePlanReviewNo
Description
(CLOVERDALE #12 - SHELL & CORE WAREHOUSE)(ENERGY/ASHRAE 90.1) Permit for the construction of a new 26,000 sq. ft. warehouse building shell with work to include construction of the tilt up building and general site work per the approved plans and the attached engineering and plan review report. No occupancy is allowed under this permit. Separate building permits will be required for occupancy of the building or individual spaces. This building is fully fire sprinklered for area increase. CDM
Contact Information
See Activities list for contact information
Show All Activities
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
BLD-Final12/7/201712/8/201712/8/2017PPASS
DetailsJim Sly
Mark Phone #: ###-####
DOC - Permit Finaled12/8/201712/8/201712/8/2017PPASS
DetailsJim Sly
FIRE-Final Inspection12/1/201712/4/201712/4/2017APASS
DetailsTroy Cobbley
life safety passed

Mark Phone #: ###-####
FIRE-Final Inspection11/22/201711/27/201711/27/2017AFAIL
DetailsTroy Cobbley
Install Knox Box, finish installing the exit discharge lights, finish concrete infront of south exit door.

Mark Phone #: ###-####
BLD-Energy code compliance11/6/201711/8/201711/7/2017PNR
DetailsMike Jordan
Insulation // Mark Phone #: ###-####.
BLD-Framing/Rough-in10/18/201710/19/201710/19/2017APASS
DetailsMike Jordan
Mark Phone #: ###-####
BLD-Framing/Rough-in10/13/201710/16/201710/16/2017PPASS
DetailsMike Jordan
Mark-plywood on the roof awings Phone #: ###-####. Steel stud framing for awnings.
BLD-Foundation9/14/20179/14/20179/14/2017PPASS
DetailsJim Storey
Rebar // Mark Phone #: ###-####
BLD-Concrete9/8/20179/11/20179/11/2017PPART
DetailsMike Jordan
rebar- Mark Phone #: ###-####. Loading dock wall.
BLD-Footing8/21/20178/22/20178/22/2017PPART
DetailsMike Jordan
Mark Phone #: ###-####. Work in progress on remainder of loading dock footings. Will have special inspection.
BLD-Foundation8/18/20178/21/20178/21/2017APART
DetailsMike Jordan
Rebar // Mark Phone #: ###-####. remainder of exterior footings and work in progress on dock footings. Ok pending specail inspection.
BLD-Footing8/16/20178/16/20178/16/2017PPASS
DetailsMike Jordan
Mark Phone #: ###-####. east exterior footinf, north exterior footing to loading dock, south east portion of exterior footing.
BLD-Concrete8/8/20178/9/20178/9/2017APART
DetailsMike Jordan
Rebar - Mark Phone #: ###-####. Work in progress on reinforcement for concrete tilt panels. Inspected panels #6 and #16. ok. Will have special inspection. Ok to place concrete after special inspection is ok.
BLD-Concrete7/20/20177/21/20177/21/2017APASS
DetailsMike Jordan
rebar in piers - Mark Phone #: ###-####. Column pad footings 4 total ok..
BLD-Conference6/19/20176/21/20176/21/2017ADONE
DetailsMike Jordan
jake Phone #: ###-####. Precon meeting with contractor and sub contractors.