BLD-Final | 2/6/2018 | 2/6/2018 | 2/6/2018 | P | PASS |
Mike Jordan
|
|
|
Can this be done after 3pm? Phone #: ###-#### Inspection requested via web by Andrew Clark
|
DOC - Permit Finaled | 2/6/2018 | 2/6/2018 | 2/6/2018 | P | PASS |
Mike Jordan
|
|
|
|
BLD-Final | 2/5/2018 | 2/6/2018 | 2/6/2018 | A | FAIL |
Mike Jordan
|
|
|
Andrew Phone #: ###-####. Need CO detector and landings at man door and both sliders.
|
BLD-Final | 1/29/2018 | 1/29/2018 | 1/29/2018 | P | FAIL |
Brandon Shaw
|
|
|
Need trades final- Ele and Mech
|
BLD-Energy code compliance | 12/13/2017 | 12/14/2017 | 12/14/2017 | A | DEFR |
Mike Jordan
|
|
|
Andrew Phone #: ###-####. Walls have been sheet rocked. No energy inspection was called in. Noted to contractor to have ibsulation sub contractor provide letter noting that job was installed per current codes.
|
BLD-Framing/Rough-in | 10/5/2017 | 10/6/2017 | 10/6/2017 | A | PASS |
Mike Jordan
|
|
|
Andrew Phone #: ###-####. All framing issues have been resolved. Air seal pack completed. Ok to insulate.
|
BLD-Conference | 10/4/2017 | 10/5/2017 | 10/5/2017 | A | DONE |
Mike Jordan
|
|
|
Meet Glen ; Andrew Phone #: ###-#### Inspection requested via web by Andrew Clark
|
BLD-Framing/Rough-in | 10/4/2017 | 10/4/2017 | 10/4/2017 | P | NR |
Mike Jordan
|
|
|
Phone #: ###-#### Inspection requested via web by Andrew Clark.. Not all corrections are completed.
|
BLD-Framing/Rough-in | 10/2/2017 | 10/2/2017 | 10/2/2017 | P | FAIL |
Mike Jordan
|
|
|
Electrical Inspection is this afternoon as well.... we need okay to insulate tomorrow Phone #: ###-#### Inspection requested via web by Andrew Clark. Complete airseal after electrical rough in inspection. Nail off 3 ply truss per enginering.Lateral bracing on A2 truss placed at wrong location. Nail off all simpson hangars. Provide headers in doors @ existing exterior wall and install h2.5 on existing truss to wall. Strap top plates from addition to existing top plates. Strap top plates on interior wall at 3ply point load to adjacent wall. Provide continous bearing from 3ply point load to footing. Provide smoke detectors in exisitng bedrooms, hardwired and interconnected. Correction notice posted.
|
BLD-Wall Bracing | 8/23/2017 | 8/24/2017 | 8/24/2017 | A | PASS |
Mike Jordan
|
|
|
Shear // Andrew Phone #: ###-####
|
BLD-Foundation | 7/11/2017 | 7/11/2017 | 7/11/2017 | P | PASS |
Mike Jordan
|
|
|
Levi Phone #: ###-####
|
BLD-Footing | 6/30/2017 | 7/5/2017 | 7/5/2017 | P | PASS |
Mike Jordan
|
|
|
Levi Phone #: ###-####
|