Information based on query as of Monday, May 13, 2024.
Permit Information
Permit NumberBLD17-01583
StatusFinaled
Name PINNACLE BUILDERS INCORPORATED
Site Address 1713 W JEFFERSON ST
Project NameJefferson Flats
Customer NumberGRD17-00063
ePlanReviewYes
Description
(JEFFERSON FLATS) // PLAN MODIFICATION TO REVISE EXTERIOR 1-HOUR RATED WALL CONSTRUCTION DETAIL AT RIM JOIST, ELIMINATE EAST AWNING, REVISE STRUCTURAL FRAMING AND DETAILING. 12/27/18 JAR. //**Permit for the construction of a 6-unit, 3 story wood framed apartment building with work to include general site work and construction of the new building per the approved plans. This building fire sprinklered with a full NFPA-13 system. **JAR**
Contact Information
See Activities list for contact information
Show All Activities
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
BLD-Final4/23/20194/23/20194/23/2019PPASS
DetailsTony Young
BLD-Final4/14/20194/15/20194/15/2019PPART
DetailsTony Young
Need final life safety, landscaping, zoning, and building. Any questions please call Andy at ###-####. Phone #: ###-#### Inspection requested via web by Andy Eells,, ok pending others for a perm. c of o
FIRE-Final Inspection4/15/20194/15/20194/15/2019PPASS
DetailsJim Page
Fire sprinkler inspection complete, fire alarm inspection complete, fire extinguishers are placed with current inspection tags. Final life fire safety inspection complete.

Andy Phone #: ###-####
BLD-Energy code compliance1/17/20191/17/20191/17/2019PPASS
DetailsDave Hannah
Insulation inspection first floor approved plans are under stairs. If you have any questions please call Andy at ###-#### Phone #: ###-#### Inspection requested via web by Andy Eells
BLD-Energy code compliance1/16/20191/17/20191/17/2019APASS
DetailsDave Hannah
Insulation inspection first floor approved plans are under stairs. If you have any questions please call Andy at ###-#### Phone #: ###-#### Inspection requested via web by Andy Eells
BLD-Energy code compliance1/15/20191/15/20191/15/2019APASS
DetailsDave Hannah
3rd floor and 2nd floor ready possibly 1st depending on inspection time. Plans under stairs in mechanical room lock box code CORE. please call ahead so I can meet you there. Andy 2086317535 Phone #: ###-#### Inspection requested via web by Andy Eells
BLD-Framing/Rough-in1/8/20191/8/20191/9/2019PPASS
DetailsDave Hannah
Andy Phone #: ###-####
BLD-Wall cover11/26/201811/26/201811/26/2018PPASS
DetailsTony Young
Partial framing for soffit cover. Wanting to cover all exterior soffits and overhangs before full framing. Plans and engineering under stairs. Call Andy with any questions Phone #: ###-#### Inspection requested via web by Andy Eells
BLD-Wall cover11/9/201811/13/201811/13/2018APASS
DetailsTony Young
Remainder of exterior sheetrock. Jim looked at first level and second story walkway. Approved plans under stairs in garage. Phone #: ###-#### Inspection requested via web by Andy Eells
BLD-Wall cover11/8/201811/8/201811/8/2018PPART
DetailsTony Young
Need partial exterior drywall nailing inspection. Please call with questions ###-#### Phone #: ###-#### Inspection requested via web by Andy Eells,, lower sections on exterior ok
BLD-Wall Bracing11/2/201811/5/201811/5/2018PCANC
DetailsDave Hannah
MTI special inspection on shear scheduled at 2pm. the 5th. Phone #: ###-#### Inspection requested via web by Andy Eells hold downs and stapes ok
BLD-Conference9/5/20189/6/20189/6/2018APEND
DetailsDave Hannah
Give me a call to meet onsite to go over questions on fire rated wall detail. Thank You Andy Eells ###-#### Phone #: ###-#### Inspection requested via web by Andy Eells
BLD-Foundation8/1/20188/2/20188/2/2018APASS
DetailsDave Hannah
James Phone #: ###-####
BLD-Foundation7/24/20187/25/20187/25/2018APEND
DetailsDave Hannah
Ty Phone #: ###-#### this is a footing also mti will check rebar and test concrete setbacks and rebar ok
BLD-Foundation7/24/20187/24/20187/24/2018PCANC
DetailsTony Young
Please call ahead // Ty Phone #: ###-#### Inspection cancelled from web by: Keeley Wilson