Information based on query as of Friday, May 10, 2024.
Permit Information
Permit NumberBLD17-02757
StatusFinaled
Name ST LUKES HEALTH SYSTEM LTD
Site Address 305 E JEFFERSON ST
Project NameSt. Luke's Children's Pavilion
Customer Number 
ePlanReviewYes
Description
(St. Luke's Children's Pavilion) This permit if for the construction of the Sky Bridge and tenant building out for the 3 story below grade parking garage and 4 story medical office with an occupied roof. Scope of work includes tenant improvement build out, envelope, sky bridge, mechanical, electrical, plumbing and fire systems. This project consist of multiple permits including BLD17-00090 Structural Steel and Concrete, GRD16-00070 Shoring, Grading, Drainage and Site Utilities.
Contact Information
See Activities list for contact information
Show All Activities
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
BLD-Final7/31/20197/31/20197/31/2019PPASS
DetailsDave Hannah
Justin Phone #: ###-####
FIRE-Final Inspection7/30/20197/31/20197/31/2019APASS
DetailsJim Page
Fire sprinkler inspections are complete, fire alarm inspections are complete, fire extinguishers are placed with current inspection tags. Previously noted items have been corrected that were noted in last fire conference. Final life fire safety inspection complete.

Justin Phone #: ###-####
BLD-Conference7/19/20197/22/20197/22/2019ADONE
DetailsJim Page
Fire conference complete, fire alarm interface between main site fire alarm system and CP building complete.

fire life safety consult // Justin Phone #: ###-####
BLD-Final6/11/20196/12/20196/12/2019APART
DetailsDave Hannah
Justin Phone #: ###-#### ok for temp occ
FIRE-Final Inspection6/11/20196/11/20196/11/2019APART
DetailsJim Page
Partial final inspection complete for life fire safety. Per conversation with Ron Johnson a 45 day TCO is autorized for life fire safety. Remaining items to inspect before life fire safety can be finaled are: Sigange by the exterior of the building on least one stairwell stating roof top access, finish fire proof wrapping of non essential items for fire pump in fire pump room, closer springs on stairwell gates preventing people from going to the basement in an emergency need to be tensioned or replaced with no exit signage placed on mentioned gates, provide fire alarm notification in sound booth as discussed as well as network the fire alarm control panels together from main site to new building as discussed (network requirement verified with Lee Meridith, fire alarm plan reviewer).
FIRE-Conference6/10/20196/11/20196/11/2019ADONE
DetailsJim Page
Fire conference complete.

Justin Phone #: ###-####
FIRE-Conference5/29/20195/30/20195/30/2019ADONE
DetailsJim Page
Fire conference complete.

Justin Phone #: ###-####
BLD-Other5/21/20195/23/20195/23/2019ACANC
DetailsDave Hannah
Egress // Justin Phone #: ###-####
FIRE-Conference4/8/20194/9/20194/9/2019PCANC
DetailsJim Page
Fire conference will be rescheduled per conversation with the point of contact, this request is cancelled.

Requesting 1st life safety walk; pre-final conference in conjunction with scheduled fire sprinkler final testing being performed by TVFP on same date/time at location. Superintendent - Jamal Nelson Phone #: ###-#### Inspection requested via web by Jamal Nelson
BLD-Ceiling Grid Inspection3/28/20193/29/20193/29/2019PPASS
DetailsDave Hannah
Inspection of 4th floor shaft wall assemblies and ceiling grid; early afternoon preference; please call Superintendent-Jamal Nelson, 5min prior to arrival - thank you. Phone #: ###-#### Inspection requested via web by Jamal Nelson
BLD-Ceiling Grid Inspection3/25/20193/27/20193/28/2019PNR
DetailsDave Hannah
Shaft wall assemblies and ceiling grid on level 4; please call Superintendent 5min prior to arrival - thank you. Phone #: ###-#### Inspection requested via web by Jamal Nelson
BLD-Ceiling Grid Inspection3/6/20193/8/20193/8/2019APASS
DetailsDave Hannah
2nd floor in-fill ceiling; 3rd floor shaft wall assemblies and ceiling grid; 4th floor shaft wall assemblies. Please call Superintendent - Jamal Nelson, 5min prior to arrival - thank you. Phone #: ###-#### Inspection requested via web by Jamal Nelson
BLD-Ceiling Grid Inspection2/18/20192/20/20192/21/2019PPASS
DetailsDave Hannah
Ceiling grid inspection level 1-2; approval to place ceiling tile. Please call Jamal Nelson, 5min prior to arrival - thank you. Phone #: ###-#### Inspection requested via web by Jamal Nelson
BLD-Other2/13/20192/14/20192/15/2019PPART
DetailsDave Hannah
Shaft wall assemblies Levels 1-2; approval for ceiling cover. Call Jamal Nelson 5min prior to arrival if possible. Phone #: ###-#### Inspection requested via web by Jamal Nelson
BLD-Framing/Rough-in2/1/20192/4/20192/5/2019PPART
DetailsDave Hannah
Shaft wall assembly - level 2 exhaust; please call Jamal Nelson on arrival Phone #: ###-#### Inspection requested via web by Jamal Nelson
BLD-Framing/Rough-in1/31/20192/1/20192/1/2019PDEFR
DetailsBrandon Shaw
Shaft wall assembly - level 2 exhaust; please call Jamal Nelson on arrival Phone #: ###-#### Inspection requested via web by Jamal Nelson
BLD-Framing/Rough-in1/25/20191/25/20191/25/2019PPART
DetailsDave Hannah
Interior framing Level 4; shaft wall assemblies Levels 1-3 Phone #: ###-#### Inspection requested via web by Jamal Nelson
BLD-Framing/Rough-in1/14/20191/17/20191/17/2019PPASS
DetailsDave Hannah
Interior framing 4th floor Phone #: ###-#### Inspection requested via web by Jamal Nelson
BLD-Framing/Rough-in12/17/201812/18/201812/18/2018APART
DetailsDave Hannah
shaft wall assemblies on levels 2 and 3. Phone #: ###-#### Inspection requested via web by Jamal Nelson ok to cover outter layers two large mec shafts
BLD-Other12/10/201812/12/201812/12/2018ADONE
DetailsDave Hannah
Skybridge placement - review game plan for moving and setting bridge in place. Please call Jamal Nelson 20min prior to arrival. Phone #: ###-#### Inspection requested via web by Jamal Nelson
BLD-Framing/Rough-in11/27/201811/28/201811/29/2018PDONE
DetailsDave Hannah
Review of mechanical shafts and damper locations Phone #: ###-#### Inspection requested via web by Jamal Nelson
BLD-Framing/Rough-in11/15/201811/20/201811/28/2018PCANC
DetailsDave Hannah
Stephen Proctor - Summit Wall: Shaft wall assemblies Level 2; Interior framing on L4; drywall hanging on L3. Phone #: ###-#### Inspection requested via web by Jamal Nelson
BLD-Framing/Rough-in11/27/201811/27/201811/28/2018PPEND
DetailsDave Hannah
Stephen Proctor - Summit Wall: Shaft wall assemblies Level 2; Interior framing on L4; drywall hanging on L3. Phone #: ###-#### Inspection requested via web by Jamal Nelson
BLD-Framing/Rough-in11/26/201811/26/201811/27/2018PPEND
DetailsDave Hannah
Stephen Proctor - Summit Wall: Shaft wall assemblies Level 2; Interior framing on L4; drywall hanging on L3. Phone #: ###-#### Inspection requested via web by Jamal Nelson
BLD-Framing/Rough-in11/6/201811/8/201811/9/2018PPASS
DetailsDave Hannah
interior framing level-3 ; 4; exterior framing and shaft walls level-4 Phone #: ###-#### Inspection requested via web by Jamal Nelson
BLD-Framing/Rough-in8/23/20188/24/20188/27/2018PPART
DetailsDave Hannah
Interior wall framing Level-2; Exterior wall framing Level-3 Phone #: ###-#### Inspection requested via web by Jamal Nelson
BLD-Framing/Rough-in8/15/20188/16/20188/17/2018PPASS
DetailsDave Hannah
Framing inspection Level 1 - pre drywall hanging
Jamal Nelson - Superintendent Phone #: ###-#### Inspection requested via web by Jamal Nelson
BLD-Framing/Rough-in6/13/20186/14/20186/14/2018PPEND
DetailsDave Hannah
Interior framing and spray applied fire proofing in progress on 1st-2nd floor; would like to walk building with Inspector and familiarize with project. Phone #: ###-#### Inspection requested via web by Jamal Nelson