Permit Information
Permit NumberBLD17-03344
StatusFinaled
Name ANDERSEN CONSTRUCTION COMPANY IDAHO
Site Address 880 W RIVER ST
Project NameThe Afton Phase II - Podium
Customer NumberGRD17-00061
ePlanReviewYes
Description
(THE AFTON – CONCRETE PARKING GARAGE PODIUM OF PHASE II – WEST BUILDING) (DRH17-00213) The fire sprinkler system (NFPA 13 below and above the podium) is used for story, height, and building area increase. The apartment building will be constructed on top of the podium under permit BLD17-03345. To construct the concrete parking garage podium portion of Phase II (West building) of the Afton development. All other drawings are for reference only. When the entire building is completed, uses are expected to include parking, storage, and perhaps office, retail sales, or assembly on the 1st story; two story residential condominiums on the 2nd story; and 1 story residential condominiums on the 2nd, 3rd, 4th, and 5th stories. Work under this permit includes concrete continuous footings, concrete spread footings, concrete matt footings, concrete foundations, 3-hr concrete shear walls and bearing walls, 3-hr concrete columns, 3-hr two-way post tensioned concrete podium, and a concrete slab on grade. The podium (i.e. floor of 2nd story) will be a 12 inch thick post tensioned concrete slab having a 3-hr fire-resistance-rating. Penetrations for plumbing pipes, roof drains, hold downs for shear walls, etc. are required to be made without cutting any reinforcement, including post tensioned tendons. Special Inspection is required for soils, concrete including post tensioning, masonry, steel including welding, anchors post-installed in hardened concrete, fire-resistance-rated through penetration fire stops, etc. The work is required to comply with the approved drawings, with the structural design, with the plan review report, and with all applicable codes and ordinances. The permit for the entire building shall not be finaled and a Certificate of Occupancy shall not be issued until the condo plat that removes the interior property line is completed. This permit does not establish a Certificate of Occupancy for any portion of this building. Fire sprinkler permits and fire alarm permits are required in conjunction with future building permits. **CJW**
Contact Information
See Activities list for contact information
Show All Activities
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
DOC - Permit Finaled  12/12/2019 DONE
Doc final per inspection conducted on 12/09/2019 by David Hannah and confirm with him
BLD-Final12/6/201912/9/201912/9/2019APASS
DetailsDave Hannah
Jason Phone #: ###-####
BLD-Framing/Rough-in12/6/201912/9/201912/9/2019ADONE
DetailsDave Hannah
Jason Phone #: ###-####
BLD-Final12/6/201912/9/201912/9/2019APASS
DetailsDave Hannah
BLD-Framing/Rough-in12/6/201912/6/201912/6/2019PCANC
DetailsJim Storey
Jason Phone #: ###-#### no access or call back.
BLD-Framing/Rough-in12/5/201912/6/201912/6/2019ADEFR
DetailsBrandon Shaw
Jason Phone #: ###-####
FIRE-Final Inspection12/5/201912/6/201912/6/2019APASS
DetailsJim Page
Final life fire safety inspection is complete.

Jason Phone #: ###-####
FIRE-Final Inspection9/24/20199/24/20199/24/2019APART
DetailsJim Page
Partial final inspwection for life fire safety is complete, item left for life fire safety is signage placed in north stairwell, install signage for fire sprinkler floor control access at discussed doors. Fire sprinkler inspection is complete, fire alarm inspection is complete. 45 day TCO authorized per conversation with Ron Johnson for life fire safety.
BLD-Framing/Rough-in5/16/20195/16/20195/16/2019APART
DetailsDave Hannah
5th floor drop soffit framing Phone #: ###-#### Inspection requested via web by Jason Reisinger first four rooms ok
BLD-Framing/Rough-in5/13/20195/14/20195/14/2019APART
DetailsDave Hannah
Jason Phone #: ###-#### 2nd floor corradors drop ceilings ok to cover
BLD-Framing/Rough-in9/27/20189/27/20189/27/2018PPEND
DetailsDave Hannah
Jason Phone #: ###-####
BLD-Framing/Rough-in8/24/20188/24/20188/27/2018PNR
DetailsDave Hannah
Jason Phone #: ###-####
BLD-Foundation7/18/20187/18/20187/18/2018PPASS
DetailsDave Hannah
post tension // Jason Phone #: ###-####
BLD-Footing4/24/20184/24/20184/25/2018PPEND
DetailsDave Hannah
Jason Phone #: ###-#### crews still working on forms and rebar also spec inspection will do final rebar and test concrete