BLD-Final | 5/3/2018 | 5/4/2018 | 5/4/2018 | A | PASS |
Mike Jordan
|
|
|
Jade Phone #: ###-####. All issues have been resolved. ok for perm occ.
|
BLD-Aging Inspection | 4/2/2018 | 4/2/2018 | 4/2/2018 | | PEND |
Mike Jordan
|
|
|
Spoke with Jade from Wright Brothers, Informed him that temp occ. expires at the end of this month (April). Jade noted that architect is waiting to get compensated prior to completing the plan mod.
|
BLD-Final | 1/29/2018 | 1/30/2018 | 1/30/2018 | P | PART |
Mike Jordan
|
|
|
Jade Phone #: ###-####. Ok for temp occ. Waiting for approval of resubmittal for front entry and letter from engineer for new MAU.
|
FIRE-Final Inspection | 1/29/2018 | 1/30/2018 | 1/30/2018 | A | PASS |
Troy Cobbley
|
|
|
life safety passed
Jade Phone #: ###-####
|
BLD-Final | 1/26/2018 | 1/29/2018 | 1/29/2018 | P | CANC |
Mike Jordan
|
|
|
Jade Phone #: ###-####. Cancelled by contractor via phone call.
|
FIRE-Final Inspection | 1/26/2018 | 1/29/2018 | 1/29/2018 | A | FAIL |
Troy Cobbley
|
|
|
Repair the emergency lights as discussed, provide corrected hardware at the west/front exterior exit door or get plan review approval for the two doors with keyed lock/deadbolts
Jade Phone #: ###-####
|
BLD-Final | 1/25/2018 | 1/26/2018 | 1/26/2018 | P | NR |
Mike Jordan
|
|
|
Jade Phone #: ###-####. Needs electrical, mech and fire finals first. Also noted that an RTU was not added that may be needed for make up air, two vent fans in bathroom also were deleted. Store front work also not done. Archtiect to submit plan mod for work not completed.
|
BLD-Framing/Rough-in | 1/26/2018 | 1/26/2018 | 1/26/2018 | P | PASS |
Mike Jordan
|
|
|
Jade Phone #: ###-####. Framing already covered. HAd contractor remove ceiling tile to inspect above grid. All walls were supported to structure as shown on plans walls were steel stud as per plans. All trades were inspected prior to cover.
|
FIRE-Final Inspection | 1/25/2018 | 1/26/2018 | 1/26/2018 | A | CANC |
Troy Cobbley
|
|
|
Need the project related hood suppression permit and fire alarm permit finaled prior to a life safety inspection. I was willing to perform a conference for the life safety but due to time constraints and prior obligations was unable to.
Jade Phone #: ###-####
|
BLD-Final | 1/25/2018 | 1/25/2018 | 1/25/2018 | P | CANC |
Mike Jordan
|
|
|
Jade Phone #: ###-####. Final scheduled for wrong day. Aslo noted that no framing framing or grid inspections have been scheduled or done. No insspections were ever conducted on this permit.
|
FIRE-Final Inspection | 1/25/2018 | 1/25/2018 | 1/25/2018 | P | CANC |
Jim Page
|
|
|
Inspection request scheduled for the wrong date, request date is for 26JAN2018 to cooincide with fire sprinkler inspections. Per conversation with Jade Phone #: ###-####, this request is cancelled.
|