BLD-Final | 7/8/2019 | 7/8/2019 | 7/11/2019 | P | PASS |
Dave Hannah
|
|
|
BLD final for Occ EO wilson Phone #: ###-#### Inspection requested via web by Brandon Reynolds
|
BLD-Conference | 6/25/2019 | 6/26/2019 | 6/26/2019 | A | CANC |
Mike Jordan
|
|
|
Safari Camp Tents Phone #: ###-#### Inspection requested via web by Brandon Reynolds
|
BLD-Final | 6/20/2019 | 6/21/2019 | 6/20/2019 | P | CANC |
Dave Hannah
|
|
|
Final inspection for Occ. Phone #: ###-#### >> Inspection requested via web by Brandon Reynolds Inspection cancelled from web by: Brandon Reynolds
|
BLD-Final | 6/20/2019 | 6/20/2019 | 6/20/2019 | P | CANC |
Brandon Shaw
|
|
|
Final Occ for EO Wilson bulding Phone #: ###-#### >> Inspection requested via web by Brandon Reynolds Inspection cancelled from web by: Brandon Reynolds
|
FIRE-Final Inspection | 6/20/2019 | 6/20/2019 | 6/20/2019 | P | PASS |
Jim Page
|
|
|
Previously noted items in the 15MAY2019 inspection have been completed, final life fire safety inspection for area of work is complete.
Life safety for Occ. Reviewed today while on site for other buildings Phone #: ###-#### Inspection requested via web by Brandon Reynolds
|
BLD-Final | 5/13/2019 | 5/14/2019 | 5/15/2019 | P | PART |
Dave Hannah
|
|
|
Temp Occupency for D7 prior to animals moving in. Not open to public yet. Phone #: ###-#### Inspection requested via web by Brandon Reynolds ok to load anaimal
|
FIRE-Final Inspection | 5/14/2019 | 5/14/2019 | 5/14/2019 | A | PART |
Jim Page
|
|
|
Fire sprinkler inspection complete, fire alarm inspection complete, fire extinguishers are placed with current inspection tags. Permanant manhole cover will be placed over sewer clean-out pit located by FDC, platform to enter fire sprinkler riser room will be extended out to meet the height requirements for the wall mount post indicator valve. 45 day TCO for life fire safety is authorized per conversation with Ron Johnson with Boise Fire. Life fire safety can be finaled after permanent manhole cover is placed and platform is extended, all other life safety items are complete.
|
FIRE-Conference | 5/13/2019 | 5/13/2019 | 5/13/2019 | P | DONE |
Jim Page
|
|
|
Wall mounted post indicator is to high above finish grade, maximum allowable elevation above finish floor needs to be 48 inches or less per conversation with Ron Johnson with Boise Fire. Manhole cover will be placed over sewer clean-out pit prior to final occupancy.
|
FIRE-Final Inspection | 5/13/2019 | 5/13/2019 | 5/13/2019 | P | CANC |
Jim Page
|
|
|
Request was for a conference, this request is cancelled.
Please coordinate with fire suppression and alarm. building D7 Phone #: ###-#### Inspection requested via web by Brandon Reynolds
|
FIRE-Final Inspection | 5/6/2019 | 5/7/2019 | 5/7/2019 | P | CANC |
Troy Cobbley
|
|
|
Since the project related fire alarm and fire sprinkler permits could not be finaled I did a conference on general life safety requirements. Life safety inspection will need to be rescheduled. This is for fire life safety in building D7 EO wilson Phone #: ###-#### Inspection requested via web by Brandon Reynolds
|
BLD-Framing/Rough-in | 4/29/2019 | 4/29/2019 | 4/29/2019 | P | PASS |
Dave Hannah
|
|
|
Inspection for framing sometime between 12pm and 4pm please. Phone #: ###-#### Inspection requested via web by Savannah Sanderson
|
BLD-Wall cover | 3/13/2019 | 3/18/2019 | 3/18/2019 | P | PASS |
Dave Hannah
|
|
|
Approval to cover ceiling prior to spray foam, had a partial already this is for the remainder Phone #: ###-#### Inspection requested via web by Brandon Reynolds
|
BLD-Wall cover | 2/28/2019 | 2/28/2019 | 3/1/2019 | P | PART |
Jim Sly
|
|
|
This is a partial approval for cover in the bathrooms and common area of D7. Please check in with Brandon ###-#### Phone #: ###-#### Inspection requested via web by Brandon Reynolds
|
BLD-Framing/Rough-in | 2/20/2019 | 2/21/2019 | 2/21/2019 | A | PASS |
Dave Hannah
|
|
|
Building D7 Partial approval to cover with spray foam. Electrical is approved and Plumbing should be first thing in a.m. Phone #: ###-#### Inspection requested via web by Brandon Reynolds
|
BLD-Framing/Rough-in | 2/19/2019 | 2/19/2019 | 2/19/2019 | P | PEND |
Dave Hannah
|
|
|
Roddy Phone #: ###-#### needs flood plan certs
|
BLD-Framing/Rough-in | 1/22/2019 | 1/22/2019 | 1/22/2019 | P | PASS |
Dave Hannah
|
|
|
Rody Phone #: ###-#### roof framing ok to cover ext side
|
BLD-Concrete | 9/5/2018 | 9/6/2018 | 9/6/2018 | P | PEND |
Dave Hannah
|
|
|
Requesting a rebar inspection for Thursday afternoon between 3pm-4pm. There will be a concrete pour on Friday morning. Phone #: ###-#### Inspection requested via web by Justin Palm ok after specal inspection sign off
|
BLD-Foundation | 8/31/2018 | 9/5/2018 | 9/6/2018 | P | PEND |
Dave Hannah
|
|
|
Rebar inspection at remaining stem walls D7 EO Wilson building. Phone #: ###-#### Inspection requested via web by Brandon Reynolds ok after spec inspection sign off
|
BLD-Foundation | 8/31/2018 | 9/4/2018 | 8/31/2018 | P | CANC |
Dave Hannah
|
|
|
Rebar inspection in remaining walls D7 EO Wilson Building. Phone #: ###-#### >> Inspection requested via web by Brandon Reynolds Inspection cancelled from web by: Brandon Reynolds
|
BLD-Concrete | 8/27/2018 | 8/28/2018 | 8/29/2018 | P | PASS |
Dave Hannah
|
|
|
We need a rebar inspection in the afternoon on Tuesday, 8/28. Anytime in the afternoon before 4pm. Phone #: ###-#### Inspection requested via web by Justin Palm
|
BLD-Foundation | 8/16/2018 | 8/17/2018 | 8/17/2018 | A | PASS |
Dave Hannah
|
|
|
rebar inspection for NW half of EO Wilson building Phone #: ###-#### Inspection requested via web by Brandon Reynolds
|
BLD-Footing | 8/7/2018 | 8/8/2018 | 8/9/2018 | P | PASS |
Dave Hannah
|
|
|
There will be a footing pour the following day, Thursday, at 5am. Inspection can be as late as 3:30pm on Wednesday the 8th. Inspection requested via web by Justin Palm
|
BLD-Concrete | 8/7/2018 | 8/9/2018 | 8/7/2018 | A | CANC |
Dave Hannah
|
|
|
Column footing to be poured early morning. Expecting mud at 5am. There is an additional footing pour happening on site, same day/same time, different building and permit number. I will put in for an individual inspection, just know its all on the same job site. Number listed is for Savannah, she will be on site. Phone #: ###-#### >> Inspection requested via web by Justin Palm Inspection cancelled from web by: Justin Palm
|