BLD-Final | 1/4/2019 | 1/4/2019 | 1/4/2019 | P | PASS |
Jim Sly
|
|
|
Request for Final Occupancy. The last piece of panic hardware is currently being installed and should be complete by 2pm. Please call Dan with any concerns. Phone #: ###-#### Inspection requested via web by Dan Koski OK for Perm. Occ.
|
FIRE-Final Inspection | 1/2/2019 | 1/2/2019 | 1/2/2019 | P | PASS |
Troy Cobbley
|
|
|
Life safety passed
Request for Life Safety Final inspection. Please contact Dan with any concerns. Phone #: ###-#### Inspection requested via web by Dan Koski
|
BLD-Other | 1/2/2019 | 1/2/2019 | 1/2/2019 | P | CANC |
Jim Sly
|
|
|
Life and Safety inspection request. Fire alarm final is this morning. I''m thinking that we could just do this when fire alarm is complete. Please call Dan with any concerns. Phone #: ###-#### Inspection requested via web by Dan Koski
|
BLD-Final | 1/2/2019 | 1/2/2019 | 1/2/2019 | P | PART |
Jim Sly
|
|
|
OK for Temp. Occ. OK for Perm. Occ. when Panic Hardware is installed on Select classroom Exterior Exit Door.
|
BLD-Conference | 12/19/2018 | 12/20/2018 | 12/20/2018 | P | PASS |
Jim Sly
|
|
|
Building walk through prior to final. Please call Dan with any issues. Phone #: ###-#### Inspection requested via web by Dan Koski
|
BLD-Conference | 11/28/2018 | 11/29/2018 | 11/29/2018 | P | DEFR |
Mike Jordan
|
|
|
Request for project walk through and occupancy requirements forthcoming. Please try to stop by after 1pm due to meetings. Call Dan with any concerns. Phone #: ###-#### Inspection requested via web by Dan Koski
|
BLD-Framing/Rough-in | 11/14/2018 | 11/14/2018 | 11/14/2018 | A | PASS |
Jim Sly
|
|
|
Fire walls and lid inspections for hallway, classrooms and bathrooms. Please contact Dan with any questions. Phone #: ###-#### Inspection requested via web by Dan Koski
|
BLD-Framing/Rough-in | 11/5/2018 | 11/5/2018 | 11/5/2018 | A | DONE |
Jim Sly
|
|
|
Final screw pattern inspection request on wood sheeting inside the gym. Please call Dan with any concerns. Phone #: ###-#### Inspection requested via web by Dan Koski
|
BLD-Framing/Rough-in | 11/2/2018 | 11/2/2018 | 11/2/2018 | P | PART |
Jim Sly
|
|
|
Screw pattern inspection request for the north wall of the gym. This is along grid line 5 between grids A and B. Please call Dan with any concerns. Phone #: ###-#### Inspection requested via web by Dan Koski OK
|
BLD-Framing/Rough-in | 10/30/2018 | 10/31/2018 | 10/31/2018 | A | PASS |
Jim Sly
|
|
|
Screw pattern inspection request along west wall of the gym. Please call Dan with any concerns. Phone #: ###-#### Inspection requested via web by Dan Koski
|
BLD-Energy code compliance | 10/30/2018 | 10/30/2018 | 10/30/2018 | P | PART |
Jim Sly
|
|
|
Fire lid inspection for the bathrooms, hallway, and classrooms. Please call Dan with any questions. Phone #: ###-#### Inspection requested via web by Dan Koski
|
BLD-Framing/Rough-in | 10/23/2018 | 10/23/2018 | 10/23/2018 | A | PART |
Jim Sly
|
|
|
Request for wall sheeting screw pattern inspection in the gym. Please call Dan with any questions. Phone #: ###-#### Inspection requested via web by Dan Koski 12 foot section in S. E. corner.......OK.
|
BLD-Conference | 10/18/2018 | 10/18/2018 | 10/18/2018 | P | DONE |
Jim Sly
|
|
|
Request for consult with Plumbing Contractor and Architect this afternoon. Please call Dan to confirm what time works best. Phone #: ###-#### Inspection requested via web by Dan Koski
|
BLD-Energy code compliance | 10/16/2018 | 10/17/2018 | 10/17/2018 | A | PART |
Jim Sly
|
|
|
Inspection of Fire Lid request for rooms and hallway south of grid 3. Please call Dan with any questions. Phone #: ###-#### Inspection requested via web by Dan Koski Fix ceiling penitrations built wit dissimilar materials.
|
BLD-Other | 10/4/2018 | 10/5/2018 | 10/5/2018 | P | PASS |
Jim Sly
|
|
|
Spray applied fire proofing on columns. (grid line C between 3-5) Phone #: ###-#### Inspection requested via web by Scott Hilbert 5 columns......MTI inspected.
|
BLD-Other | 10/4/2018 | 10/5/2018 | 10/5/2018 | A | PART |
Jim Sly
|
|
|
Above ceiling fire taping. Phone #: ###-#### Inspection requested via web by Scott Hilbert Select rooms........
|
BLD-Energy code compliance | 10/3/2018 | 10/4/2018 | 10/4/2018 | A | PART |
Jim Sly
|
|
|
Insulation and vapor barrier Phone #: ###-#### Inspection requested via web by Scott Hilbert Select area......
|
BLD-Other | 10/3/2018 | 10/4/2018 | 10/4/2018 | A | PASS |
Jim Sly
|
|
|
Shear wall screw inspection Phone #: ###-#### Inspection requested via web by Scott Hilbert
|
BLD-Framing/Rough-in | 9/21/2018 | 9/21/2018 | 9/21/2018 | A | PART |
Jim Sly
|
|
|
Request for fire lid inspection along grid 1 between classroom entry doors 110B and 103B. This alcove is exterior fire lid. Please call Dan with any questions. Phone #: ###-#### Inspection requested via web by Dan Koski OK
|
BLD-Framing/Rough-in | 9/20/2018 | 9/20/2018 | 9/20/2018 | P | PART |
Jim Sly
|
|
|
Inspection of encapsulated columns requested. Columns along grid 2 and the intersection of grids 5/B are ready. Please call Dan with any concerns. Phone #: ###-#### Inspection requested via web by Dan Koski Above items......OK.
|
BLD-Other | 9/17/2018 | 9/17/2018 | 9/17/2018 | P | DONE |
Jim Sly
|
|
|
Air Barrier inspection request. Please call Dan with any questions. Phone #: ###-#### Inspection requested via web by Dan Koski 90 percent complete. MTI providing special inspections.
|
BLD-Framing/Rough-in | 9/6/2018 | 9/6/2018 | 9/6/2018 | P | DONE |
Jim Sly
|
|
|
Consult request for fire ratings and column encapsulation. Please call Dan with any questions. Phone #: ###-#### Inspection requested via web by Dan Koski Defer to Architect of record.
|
BLD-Framing/Rough-in | 9/5/2018 | 9/5/2018 | 9/5/2018 | P | PART |
Jim Sly
|
|
|
Exterior DensGlas screw pattern inspection request. Please call Dan with questions. MTI was out yesterday looking at the same thing Phone #: ###-#### Inspection requested via web by Dan Koski Gym Ok pending MTI special insp.and approval.
|
BLD-Framing/Rough-in | 8/22/2018 | 8/23/2018 | 8/23/2018 | A | PART |
Jim Sly
|
|
|
Request for framing inspection on Gym and Classroom exterior walls. Please call Dan with any questions. Special inspection is scheduled as well. Phone #: ###-#### Inspection requested via web by Dan Koski Classroom and Gym Exterior walls and hold downs OK. MTI on site for welded connections.
|
BLD-Other | 7/31/2018 | 7/31/2018 | 7/31/2018 | P | DEFR |
Jim Sly
|
|
|
Request for inspection of Seepage bed before fabric and rock install. The Land Group is scheduled to come out as well. Please call Dan with any concerns. Phone #: ###-#### Inspection requested via web by Dan Koski Advised contr. to Call Public Works.
|
BLD-Framing/Rough-in | 7/30/2018 | 7/31/2018 | 7/31/2018 | A | PART |
Jim Sly
|
|
|
Request for install procedures, proper insulation, and overall framing request. Please call Dan with any concerns. Phone #: ###-#### Inspection requested via web by Dan Koski
|
BLD-Other | 7/26/2018 | 7/27/2018 | 7/26/2018 | P | PASS |
Jim Sly
|
|
|
Rebar and Vapor Barrier inspection request for the remainder of the building slab. This will complete our interior slab from grid lines A-D and 1-5. Please call Dan with any questions. Phone #: ###-#### Inspection requested via web by Dan Koski OK pending MTI special inspection, tests and approvals.
|
BLD-Other | 7/26/2018 | 7/26/2018 | 7/26/2018 | A | PART |
Jim Sly
|
|
|
Masonry rebar inspection request for the trash enclosure. Grouting this at 12pm. We will have MTI on site to take samples and check rebar as well. Please call Dan with any questions. Phone #: ###-#### Inspection requested via web by Dan Koski OK pending MTI special inspections, tests and approvals.
|
BLD-Concrete | 7/20/2018 | 7/20/2018 | 7/20/2018 | A | PART |
Jim Sly
|
|
|
Gym slab rebar and vapor barrier inspection request. The slab is scheduled to place next Monday. PM inspection is fine as well the area ready at any time. Please call Dan with any concerns. Phone #: ###-#### Inspection requested via web by Dan Koski Slab OK pending MTI special inspection, tests and approvals.
|
BLD-Footing | 7/17/2018 | 7/17/2018 | 7/17/2018 | P | PASS |
Brandon Shaw
|
|
|
Rebar inspection for spread footings along grid C and grids 4;5. Trash enclosure rebar in the footing requested as well. MTI is scheduled for special inspection as well.
|
BLD-Foundation | 7/13/2018 | 7/13/2018 | 7/13/2018 | A | PASS |
Jim Sly
|
|
|
Request for inspection on the rebar in the concrete stem walls. Perimeter stem walls and gym walls being placed this afternoon. Grids 1-5 and A-D. Please call Dan with any concerns. Phone #: ###-#### Inspection requested via web by Dan Koski OK .....Pending MTI special inspections, tests and approvals.
|
BLD-Footing | 7/9/2018 | 7/10/2018 | 7/10/2018 | A | PASS |
Jim Sly
|
|
|
Rebar inspection request for the footing placement scheduled this afternoon. Grids A-D, and 1-5. Please call Dan with any questions. Thanks Phone #: ###-#### Inspection requested via web by Dan Koski OK Pending MTI special inspections, Tests and Approvals.
|
BLD-Conference | 6/25/2018 | 6/26/2018 | 6/26/2018 | A | DONE |
Jim Sly
|
|
|
Pioneer Elementary overview and plans for the project. Please call Dan with any questions. Phone #: ###-#### Inspection requested via web by Dan Koski
|