DOC - Permit Finaled | | | 1/28/2020 | | DONE |
|
|
|
|
BLD-Final | 1/27/2020 | 1/27/2020 | 1/27/2020 | P | PASS |
Tell Riley
|
|
|
need passing final inspection to close out permit please//final was complete pending other required inspections//
|
BLD-Final | 12/5/2019 | 12/6/2019 | 12/6/2019 | P | PEND |
Tell Riley
|
|
|
Paul Phone #: ###-####//special inspection report provided for structural bolting, compaction, and concrete//final on shell ok pending zoning final and ACHD signature//
|
BLD-Final | 11/25/2019 | 11/26/2019 | 11/26/2019 | P | NR |
Tell Riley
|
|
|
Michael Phone #: ###-####//need final special inspections report//
|
FIRE-Final Inspection | 11/25/2019 | 11/26/2019 | 11/26/2019 | A | PASS |
Troy Cobbley
|
|
|
Life safety passed.
Michael Phone #: ###-####
|
BLD-Foundation | 12/21/2018 | 12/26/2018 | 12/26/2018 | A | PART |
Tony Young
|
|
|
pour at 10 // zack Phone #: ###-####,, special inspector on site also,, work in progress
|
BLD-Footing | 12/7/2018 | 12/10/2018 | 12/10/2018 | A | PASS |
Jim Sly
|
|
|
Zack Phone #: ###-#### OK pending MTI special inspection, tests and approvals.
|