Information based on query as of Thursday, May 16, 2024.
Permit Information
Permit NumberBLD18-02304
StatusIssued
Name GAFFORD CONSTRUCTION INC
Site Address 11350 W FRANKLIN RD
Project NameIdaho power Substation Control
Customer Number 
ePlanReviewYes
Description
(IDAHO POWER) ***Special inspections required see attached #310 form*** Permit to construct a new 960 sq. ft. one story CMU block building with work to include: construction of footing foundation, slab on grade concrete floor, pre-engineered roof trusses, one exterior door, one accessible bathroom, and (1) 2x6 interior wall. Seperate mechanical, electrical, and plumbing permits required. All work shall be per approved plans. This building is not fire sprinkled. MDH
Contact Information
See Activities list for contact information
Show All Activities
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
FIRE-Conference5/15/20205/15/20205/15/2020PDONE
DetailsTroy Cobbley
Fire dept access has been approved by Ron with Boise Fire, The fire alarm system has been resolved. Need battery storage data to final life safety.
BLD-Final4/26/20194/26/20194/26/2019PNR
DetailsMike Jordan
Jason Phone #: ###-####. Fire/life/safety failed. Also need public works final inspection.
FIRE-Final Inspection4/25/20194/26/20194/26/2019AFAIL
DetailsTroy Cobbley
I need verification of all requirements listed under "Battery Storage" section of the fire code reveiw comments. Project superintendant stated these items were provided by Idaho Power.

Call half hour before // Jason Phone #: ###-####
FIRE-Final Inspection2/6/20192/7/20192/7/2019AFAIL
DetailsTroy Cobbley
Need small documents, need fire dept access approved (pending), need a permit for the already installed fire alarm system.

Jason-please call 30 minutes prior Phone #: ###-####
BLD-Framing/Rough-in10/18/201810/18/201810/18/2018PPASS
DetailsMike Jordan
BLD-Other10/17/201810/18/201810/18/2018ACANC
DetailsMike Jordan
roof inspection // Jason Phone #: ###-####. Moved to pm per contracotr.
BLD-Concrete9/25/20189/26/20189/26/2018PPASS
DetailsMike Jordan
rebar-Jason Phone #: ###-####. Interior thickend footing and reinforcement for slab on grade.
BLD-Footing9/10/20189/11/20189/11/2018PCANC
DetailsMike Jordan
Stem wall, early PM, pouring at 2 - Jason Phone #: ###-####
BLD-Foundation9/11/20189/11/20189/11/2018PPASS
DetailsMike Jordan
Stem wall, early PM, pouring at 2 - Jason Phone #: ###-####
BLD-Footing9/6/20189/7/20189/7/2018APART
DetailsMike Jordan
jason Phone #: ###-####. Perimeter footings. Work in progress on installing vertical reinforcement. Ok to place concrete after special inspection has approved footings.
BLD-Footing9/5/20189/6/20189/6/2018PCANC
DetailsMike Jordan
Pouring at 3, special inspections prior - Jason Phone #: ###-####. Cancelled per contractor via phone call.