Permit Information
Permit NumberBLD18-03023
StatusFinaled
Name ENVIROSPARK ENERGY SOLUTIONS INC
Site Address 8300 W OVERLAND RD
Project NameWalmart elec vehicle charging
Customer Number 
ePlanReviewYes
Description
(WALMART - ELECTRIC VEHICLE CHARGING STATIONS) Permit for the installation of (4) electric vehicle charging stations, equipment yard with (6) power units and switchboard assembly, fencing with (2) gates, parking signage and landscaping. Approval is contingent upon adhering to the approved plans and engineering. This project is classified as a U occupancy. There are no accessibility requirements for U occupancies. Accessible parking is provided elsewhere in the same parking lot. MDH
Contact Information
See Activities list for contact information
Show All Activities
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
BLD-Final3/22/20193/25/20193/25/2019PPASS
DetailsMike Jordan
Call prior to going Phone #: 6027037603 >> Inspection requested via mobile web by Matthew Jimenez
DOC - Permit Finaled3/25/20193/25/20193/25/2019PPASS
DetailsMike Jordan
BLD-Final3/20/20193/21/20193/21/2019PNR
DetailsMike Jordan
Call prior to going Phone #: 6027037603 >> Inspection requested via mobile web by Matthew Jimenez. Needs electrical final.
FIRE-Final Inspection3/20/20193/21/20193/21/2019ACANC
DetailsTroy Cobbley
No life safety, fire alarm or fire sprinkler sign off required per the permit details.

Call prior to going Phone #: 6027037603 >> Inspection requested via mobile web by Matthew Jimenez
BLD-Concrete1/26/20191/28/20191/28/2019PPART
DetailsMike Jordan
Call prior to going Phone #: 6027037603 >> Inspection requested via mobile web by Matthew Jimenez. rebar for slab.
BLD-Concrete1/24/20191/25/20191/25/2019APART
DetailsMike Jordan
As early as possible Phone #: 6027037603 >> Inspection requested via mobile web by Matthew Jimenez