(IN THE BAG PROMOTIONS) 09/11/2019 PLAN MODIFICATION #2 TO ADD AN EXTERIOR DOOR LANDING, STAIRS AND HANDRAIL. JG // 07/8/19 PLAN MODIFICATION TO TRUSS FRAMING AT THE UL U309 1-HOUR RATED EXTERIOR WALL CONSTRUCTION SEE DETAIL IN SMALL DOCUMENTS FILE. JG // Permit for a 3,942 sq. ft. addition to an existing 4,894 sq. ft. building and create an 8,836 sq. ft. building. Approval is contingent upon adhering to the approved plans on file and attached engineering. Work to include: removal of select exterior walls, removal of select removal of select door/door frame, removal of select exterior windows, removal of select exterior walls, construction of a new footings, concrete floor slab, 2x exterior walls, wood and stucco exterior siding, pre-engineered roof trusses, asphalt shingle and TPO roof covering, an accessible restroom, suspended acoustic and gypsum ceilings, some minor site work, electrical work, plumbing work, mechanical work and interior finishes in compliance with Ch. 8 of the 2015 IBC. Note: special inspection is required, see form #310 attached. This building is Not Fire Sprinklered. **JG**
Contact Information
See Activities list for contact information
Show All Activities
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
BLD-Final11/25/201911/25/201911/25/2019PPASS
DetailsTell Riley
Bob Phone #: ###-####//plan mod for steps at service door and railing complete//final is complete//no signature card to sign//
BLD-Final11/19/201911/19/201911/19/2019PNR
DetailsTell Riley
Bob Phone #: ###-####//need to modify hand rail to meet plan mod//discussed onsite//
BLD-Final8/12/20198/12/20198/13/2019PPEND
DetailsTell Riley
joe Phone #: ###-####//discussed ramp at exit door--too steep--plans show 1:12//
BLD-Final7/18/20197/19/20197/19/2019PPASS
DetailsTell Riley
Joe Phone #: ###-####//building complete per plans//temp occupancy ok//final occupancy once parking lot is finished and signage is installed//
FIRE-Final Inspection7/19/20197/19/20197/19/2019PPASS
DetailsTroy Cobbley
life safety passed.

Joe Phone #: ###-####
BLD-Final7/18/20197/18/20197/18/2019PNR
DetailsTell Riley
Joe Phone #: ###-####//need electrical final//need fire final//new sidewalks and ADA ramp to be poured 7/19/19//
FIRE-Final Inspection7/17/20197/18/20197/18/2019APART
DetailsTroy Cobbley
Hvac unit won't go into heat mode for duct detector testing. Owner agreed to lock out the unit until it is repaired and shut down could be tested. All other life safety items appear ok. Joe Phone #: ###-####
BLD-Framing/Rough-in7/9/20197/10/20197/10/2019APASS
DetailsTell Riley
Joe Phone #: ###-####//truss framing and beams installed per plans for modification//engineering was reveiwed//two electrical wires were fire caulked at the penetrations//
BLD-Ceiling Grid Inspection7/1/20197/1/20197/2/2019PPASS
DetailsDave Hannah
Joe- modification reveiw has nothing to do with this inspection Phone #: ###-####
BLD-Framing/Rough-in6/25/20196/26/20196/26/2019AFAIL
DetailsJim Storey
Joe Phone #: ###-#### stop work/ submitals to get aproved by planreview not done/ need ul listings for wall assemley trusses bearing in wall . prevously noted with c/n an not responded to.
BLD-Ceiling Grid Inspection6/25/20196/25/20196/26/2019PNR
DetailsDave Hannah
joe Phone #: ###-####
BLD-Framing/Rough-in6/21/20196/24/20196/24/2019APART
DetailsDave Hannah
Joe Phone #: ###-#### blocking in wall at trusses ok to cover with sheet rock
BLD-Energy code compliance6/19/20196/19/20196/19/2019PPASS
DetailsBrandon Shaw
Ceiling insulation...
BLD-Other6/13/20196/14/20196/14/2019APASS
DetailsDave Hannah
Joe- drywall nai off inspection Phone #: ###-####
BLD-Wall cover6/10/20196/10/20196/11/2019PPART
DetailsDave Hannah
Joe Phone #: ###-#### picl up butt seams 8 oc/ plm pipe repairs to gyp and fire stop / and truss removal or fire rating pending. ok to cover int walls
BLD-Wall cover6/7/20196/10/20196/10/2019AFAIL
DetailsJim Storey
Joe Phone #: ###-#### defered to pm
BLD-Wall cover6/6/20196/6/20196/6/2019PPASS
DetailsJim Storey
vapor barrier exterior // Joe Phone #: ###-####/ pending architect submittal for wall protection
BLD-Energy code compliance6/4/20196/5/20196/5/2019APART
DetailsJim Storey
Joe- Phone #: ###-#### wall insulation ok/ need vappor barrior/ pending p/l fire wall aplacation at trusses.
BLD-Other5/16/20195/17/20195/20/2019APART
DetailsDave Hannah
fire wall // Joe Phone #: ###-#### sheet rock behind ledger ok
BLD-Wall Bracing4/30/20195/1/20195/1/2019AFAIL
DetailsJim Storey
Joe Phone #: ###-#### over driven renail
BLD-Framing/Rough-in4/30/20195/1/20195/1/2019AFAIL
DetailsJim Storey
Joe Phone #: ###-#### c/n 602 1 hr from bothsides provide engineering to resolve to planreview.
BLD-Other4/2/20194/3/20194/3/2019PPASS
DetailsDave Hannah
pre slab // Joe Phone #: ###-####
BLD-Footing3/18/20193/19/20193/19/2019PPASS
DetailsDave Hannah
pour time 3pm-Joe Phone #: ###-####