Information based on query as of Wednesday, May 8, 2024.
Permit Information
Permit NumberBLD18-03768
StatusFinaled
Name ABBETH LLC
Site Address 1857 E RIDGECREST DR
Project NameAbbeth flip
Customer Number 
ePlanReviewNo
Description
HILLSIDE - WUI - 2/19/19 MODIFICATION CONVERTS THIS TO A FULL BUILDING PERMIT - PERMIT FOR A REMODEL AND CONSTRUCTION OF A NEW DECK. PROJECT INVOLVES THE FOUNDATION REPAIR NOTED IN THE EARLY START PERMIT, ADDING BASEMENT EGRESS WINDOWS, RELOCATING A STAIRWAY, RECONFIGURING THE MASTER BATH, RELOCATING THE POWDER BATH, RECONFIGURING THE KITCHEN, NEW SURFACES THROUGHOUT, NEW WINDOWS,SIDING & ROOFING. AND REPAIRNG TRUSS DAMAGE FROM PREVIOUS HOUSE SETTLING. ALL WORK PER PLANS, NOTATIONS, ATTACHMENTS, ENGINEERING, LOCAL CODES & ORDINANCES. SEPARATE ELECTRICAL, PLUMBING, AND MECHANICAL PERMITS REQUIRED. 2/19/19 **jab** This early start permit is being issued to allow applicant to begin prep and foundation work to address unsafe on-site conditions. Permit for the foundation work only. No framing allowed. Builder is beginning "At Own Risk". Any construction not in compliance with the code are the owner’s responsibility and shall be corrected at the owner's expense. Foundation work is based on the provided plans, engineering and geotechnical report. A letter from the applicant’s geotechnical engineer indicating that the footing subgrade is acceptable must be approved by Public Works prior to scheduling a footing inspection. Please e-mail the stamped inspection approval letter to mjannusch@cityofboise.org and allow 24 hours for subgrade approval processing. Call Melissa Jannusch at 208-608-7168 with questions. **JAB**The final inspection of the site grading and drainage work shall be done by the design engineer. Written approval shall be submitted to Boise Public Works prior to the issuance of the building final.
A letter from the applicant’s geotechnical engineer indicating that the footing/column subgrade is acceptable must be approved by Public Works prior to scheduling a footing inspection. Please e-mail the stamped inspection approval letter to mjannusch@cityofboise.org and allow 24 hours for subgrade approval processing. Call Melissa Jannusch at 208-608-7168 with questions.
The final inspection of the site grading and drainage work shall be done by the design engineer. Written approval shall be submitted to Boise Public Works prior to the issuance of the building final.
Contact Information
See Activities list for contact information
Show All Activities
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
BLD-Final9/16/20199/17/20199/17/2019APASS
DetailsBrandon Shaw
Melissa Janusch is meeting me at 10:00 to review the engineering, we should be ready for the building final anytime after 10:00. Phone #: ###-#### Inspection requested via web by Daniel Dow
DOC - Permit Finaled9/17/20199/17/20199/17/2019PPASS
DetailsBrandon Shaw
BLD-Final9/5/20199/6/20199/6/2019ANR
DetailsBrandon Shaw
Need PW approval...
BLD-Final9/3/20199/3/20199/4/2019AFAIL
DetailsBrandon Shaw
No access...
No city approved plans or permit on site...
No address posted...
BLD-Final8/31/20199/3/20199/3/2019AFAIL
DetailsBrandon Shaw
No access...
No city approved plans or permit on site...
No address posted...
BLD-Concrete4/12/20194/12/20194/12/2019PPASS
DetailsDave Hannah
rebar // Richard Phone #: ###-#### ftgs for deck
BLD-Foundation4/9/20194/10/20194/10/2019PNR
DetailsDave Hannah
Richard- Rebar inspection Phone #: ###-####
BLD-Framing/Rough-in4/1/20194/1/20194/1/2019PPASS
DetailsDave Hannah
Richard Phone #: ###-####
BLD-Framing/Rough-in3/28/20193/29/20193/29/2019APASS
DetailsDave Hannah
Richard Phone #: ###-#### ok to cover up stairs ok to insulate basement needs to fix floor joist cut by plumber
BLD-Footing1/14/20191/15/20191/16/2019APASS
DetailsDave Hannah
Chris Phone #: ###-#### this was a foundation inspection
BLD-Footing1/9/20191/10/20191/10/2019APASS
DetailsDave Hannah
Ross-Melissa J ok''d hold to be removed-please call her for questions Phone #: ###-####
BLD-Footing1/7/20191/8/20191/9/2019ANR
DetailsDave Hannah
pouring at 1pm- Rick Phone #: ###-#### needs geo tech
BLD-Foundation1/7/20191/8/20191/9/2019ANR
DetailsDave Hannah
Ross Phone #: ###-#### needs geo tech
BLD-Foundation12/20/201812/21/201812/21/2018APART
DetailsBrandon Shaw
South foundation wall...
Frost protection is required...
BLD-Footing12/17/201812/18/201812/18/2018APASS
DetailsDave Hannah
Rick Phone #: ###-#### ftgs for south wall
BLD-Footing12/14/201812/17/201812/17/2018ACANC
DetailsDave Hannah
Rick Phone #: ###-####