Information based on query as of Friday, April 26, 2024.
Permit Information
Permit NumberBLD18-03870
StatusIssued
Name WATER DAMAGE PRO OF IDAHO LLC
Site Address 611 S 8TH ST
Project NameThe Afton - Repair Permit
Customer Number 
ePlanReviewYes
Description
(THE AFTON CONDOMINIUM REPAIR) A PRE-CONSTRUCTION CONFERENCE WITH THE BUILDING INSPECTOR IS REQUIRED PRIOR TO ANY RECONSTRUCTION. Permit for repairs as a result of water damage to units 101, 302, and 402. Work to include reparing: interior walls, rated wall/floor/ceiling assemblies, and interior finishes. Unit 101 does not contain any rated assemblies in need of repair. This is a scope of work permit only with a certificate of completion to be issued upon completion and approval of the project. This building is fully Fire Sprinklered with an approved Fire Alarm system. Any alterations or modifications to the buildings Fire Sprinkler or Fire Alarm system WILL REQUIRE A SEPARATE PERMIT and shall be installed per NFPA 13 & NFPA 72 as regulated by the Boise Fire Department. **JHB**
Contact Information
See Activities list for contact information
Show All Activities
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
BLD-Final2/11/20192/12/20192/12/2019ANR
DetailsDave Hannah
John Phone #: ###-#### needs fire finals
FIRE-Final Inspection2/11/20192/12/20192/12/2019AFAIL
DetailsJim Page
Need to have the fire sprinker issue resolved with fire department and plan review. Also need to test the fire alarm system in effected rooms due to possible issues with devices getting saturated.

Dave Phone #: ###-####
FIRE-Final Inspection1/4/20191/4/20191/4/2019PPART
DetailsJim Page
Final life fire safety inspection for units 101 and 402 complete, level 3 unit to be completed at a later date. Will need to test fire alarms in effected units before permit can be finaled.

John- Phone #: ###-####
BLD-Final1/4/20191/4/20191/4/2019PPART
DetailsDave Hannah
John Phone #: ###-#### ok to occ unit 101 after fire finals
BLD-Final1/4/20191/4/20191/4/2019PPART
DetailsDave Hannah
John Phone #: ###-#### ok to occ unit 402 after fire finals
BLD-Final1/3/20191/4/20191/4/2019ACANC
DetailsDave Hannah
John Phone #: ###-####
BLD-Energy code compliance11/6/201811/7/201811/7/2018APASS
DetailsDave Hannah
John Phone #: ###-#### ok to start sheet rocking
BLD-Conference11/2/201811/5/201811/5/2018APART
DetailsDave Hannah
John Phone #: ###-#### ok to insulate