BLD-Final | 11/26/2019 | 11/26/2019 | 11/26/2019 | P | PASS |
Mike Jordan
|
|
|
Please give me a call when you head this way. Phone #: ###-#### Inspection requested via web by Bob Thornton. Ok for perm occ.
|
FIRE-Final Inspection | 11/25/2019 | 11/26/2019 | 11/26/2019 | A | PASS |
Troy Cobbley
|
|
|
life safety passed.
Phone #: ###-#### Inspection requested via web by Bob Thornton
|
FIRE-Final Inspection | 11/18/2019 | 11/19/2019 | 11/19/2019 | P | FAIL |
Troy Cobbley
|
|
|
Provide annual inspection for the fire sprinkler system and fire extinguishers. Provide interconnect of the door mags and the fire alarm system as per the iFC. This work requires permit.
Call me when you’re headed this way. Phone #: ###-#### Inspection requested via web by Bob Thornton
|
BLD-Ceiling Grid Inspection | 10/23/2019 | 10/24/2019 | 10/24/2019 | A | PASS |
Mike Jordan
|
|
|
Call me when you’re headed this way please. Phone #: ###-#### Inspection requested via web by Bob Thornton
|
BLD-Framing/Rough-in | 8/28/2019 | 8/29/2019 | 8/29/2019 | A | PASS |
Mike Jordan
|
|
|
Inspect fat grid from grid line 4 east. Phone #: ###-#### Inspection requested via web by Bob Thornton
|
BLD-Ceiling Grid Inspection | 8/29/2019 | 8/29/2019 | 8/29/2019 | A | PASS |
Mike Jordan
|
|
|
Inspect fat grid from grid line 4 east. Phone #: ###-#### Inspection requested via web by Bob Thornton
|
BLD-Energy code compliance | 8/27/2019 | 8/27/2019 | 8/27/2019 | P | PASS |
Mike Jordan
|
|
|
Phone #: ###-#### Inspection requested via web by Bob Thornton
|
BLD-Framing/Rough-in | 8/21/2019 | 8/21/2019 | 8/21/2019 | P | PASS |
Mike Jordan
|
|
|
Please look at exterior walls for cover. Phone #: ###-#### Inspection requested via web by Bob Thornton. Ok to insulate exterior walls.
|
BLD-Wall cover | 8/12/2019 | 8/13/2019 | 8/13/2019 | A | PASS |
Mike Jordan
|
|
|
Look at vestibule walls. Phone #: ###-#### Inspection requested via web by Bob Thornton
|
BLD-Wall Bracing | 8/13/2019 | 8/13/2019 | 8/13/2019 | A | PASS |
Mike Jordan
|
|
|
Look at vestibule walls. Phone #: ###-#### Inspection requested via web by Bob Thornton. Parapet wall bracing is now ok.
|
BLD-Wall cover | 8/6/2019 | 8/7/2019 | 8/7/2019 | P | CANC |
Mike Jordan
|
|
|
Parapet wall bracing. Give me a call. Phone #: ###-#### Inspection requested via web by Bob Thornton
|
BLD-Framing/Rough-in | 8/7/2019 | 8/7/2019 | 8/7/2019 | P | PASS |
Mike Jordan
|
|
|
Parapet wall bracing. Give me a call. Phone #: ###-#### Inspection requested via web by Bob Thornton
|
BLD-Wall Bracing | 8/7/2019 | 8/7/2019 | 8/7/2019 | P | FAIL |
Mike Jordan
|
|
|
Parapet wall bracing. Give me a call. Phone #: ###-#### Inspection requested via web by Bob Thornton
|
BLD-Wall cover | 8/6/2019 | 8/6/2019 | 8/6/2019 | P | CANC |
Mike Jordan
|
|
|
Look at the roof wall bracing. Phone #: ###-#### >> Inspection requested via web by Bob Thornton Inspection cancelled from web by: Bob Thornton
|
BLD-Framing/Rough-in | 8/2/2019 | 8/2/2019 | 8/2/2019 | P | PASS |
Mike Jordan
|
|
|
Partial framing. Give me a call. Phone #: ###-#### Inspection requested via web by Bob Thornton. West side parapet wall ok per RFI from engineer.
|
BLD-Framing/Rough-in | 7/29/2019 | 7/29/2019 | 7/29/2019 | P | PASS |
Mike Jordan
|
|
|
Partial framing. Give me a call. Phone #: ###-#### Inspection requested via web by Bob Thornton. Stell stud framing for exterior canopies and store front.
|
FIRE-Conference | 7/12/2019 | 7/15/2019 | 7/15/2019 | A | DONE |
Troy Cobbley
|
|
|
Bob and I discussed a concealed space that will be built as "non-combustible" therefore not requireing fire sprinkler protection. Please call when you head this way. Phone #: ###-#### Inspection requested via web by Bob Thornton
|
BLD-Framing/Rough-in | 7/11/2019 | 7/12/2019 | 7/12/2019 | A | CANC |
Mike Jordan
|
|
|
Bob- please call before arriving Phone #: ###-####
|
BLD-Conference | 7/12/2019 | 7/12/2019 | 7/12/2019 | A | DONE |
Mike Jordan
|
|
|
Bob- please call before arriving Phone #: ###-####
|
BLD-Footing | 6/20/2019 | 6/20/2019 | 6/20/2019 | P | PART |
Mike Jordan
|
|
|
Bob-footing for building portion only-per Bob plan mod not for this portion Phone #: ###-####. Footings for new store front. WIP. Will be ok for concrete pending special inspection.
|
BLD-Footing | 6/6/2019 | 6/6/2019 | 6/6/2019 | P | DEFR |
Mike Jordan
|
|
|
Bob Phone #: ###-####. Concrete placed in the am. Special inspector on site.
|