Permit Information
Permit NumberBLD18-03990
StatusIssued
Name LAYTON CONSTRUCTION
Site Address 111 W STATE ST
Project NameSt. Luke's Downtown Parking Ga
Customer Number 
ePlanReviewYes
Description
(ST LUKES DOWNTOWN PARKING GARAGE) Permit for the construction of a new 383,808 sq. ft. parking garage with two levels of enclosed below grade (95,479 sq. ft.) and 5 levels of open above grade parking (288,329 sq. ft.). This building is fully fire sprinklered for fire flow. with the enclosed garage required to be sprinklered as an enclosed parking garage. This building is fully fire sprinklered for fire flow. CDM
Contact Information
See Activities list for contact information
Show All Activities
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
BLD-Concrete1/9/20201/10/20201/10/2020APEND
DetailsDave Hannah
Charlie Phone #: ###-#### ok with spec inspection
BLD-Foundation12/9/201912/9/201912/11/2019PPASS
DetailsDave Hannah
Charle Phone #: ###-#### ok after spec inspection sign offs
BLD-Concrete10/10/201910/11/201910/11/2019ACANC
DetailsJim Storey
Brian Phone #: ###-####
BLD-Other8/13/20198/13/20198/16/2019PPASS
DetailsDave Hannah
slab on deck level G //Brian Phone #: ###-####
BLD-Foundation7/17/20197/18/20197/18/2019PPASS
DetailsDave Hannah
Brian- foundation slab Phone #: ###-####
BLD-Concrete7/8/20197/8/20197/9/2019PPASS
DetailsDave Hannah
slab // brian Phone #: ###-####
BLD-Concrete7/1/20197/2/20197/2/2019APEND
DetailsDave Hannah
rebar in columns - gridline P15 // Brian Phone #: ###-####
BLD-Other6/27/20196/28/20196/28/2019ADEFR
DetailsMike Jordan
Brian- inspection for inwall rebar PCLINE Phone #: ###-####. Pending special inspection.
BLD-Concrete6/20/20196/21/20196/24/2019APASS
DetailsDave Hannah
rebar- Rid thin P15-Brian Phone #: ###-####
BLD-Foundation6/24/20196/25/20196/24/2019ACANC
DetailsDave Hannah
P D line- Brian Phone #: ###-####
BLD-Wall Bracing6/18/20196/19/20196/19/2019APART
DetailsBrandon Shaw
Pending Special Inspection...
rebar line PB
BLD-Foundation6/13/20196/14/20196/17/2019APASS
DetailsDave Hannah
PB line- Brian Phone #: ###-####
BLD-Foundation6/12/20196/13/20196/17/2019APASS
DetailsDave Hannah
rebar on gridline PA // Brian Phone #: ###-####
BLD-Other6/11/20196/12/20196/12/2019APEND
DetailsDave Hannah
Brian-shear wall rebar-grid line PB Phone #: ###-#### ok after spec final signoffs for placement of concrete
BLD-Wall Bracing6/5/20196/6/20196/6/2019APEND
DetailsDave Hannah
shear (pc grid line) // Brian Phone #: ###-#### ok after spec inspection sign off
BLD-Foundation6/3/20196/4/20196/4/2019APEND
DetailsDave Hannah
Brian- red line P15 going north to south Phone #: ###-#### ok after spec inspection sign off
BLD-Wall Bracing5/31/20196/3/20196/4/2019APEND
DetailsDave Hannah
Brian Phone #: ###-#### ok after spec inspection sign off
BLD-Other5/28/20195/29/20196/4/2019APEND
DetailsDave Hannah
concrete wall // Brian Phone #: ###-#### ok after spec inspection sign off
BLD-Footing5/30/20195/31/20196/4/2019APEND
DetailsDave Hannah
Brian-on grid line P15 ON THE EAST NE SIDE Phone #: ###-#### ok after spec inspection sign off
BLD-Foundation5/29/20195/30/20195/30/2019APEND
DetailsDave Hannah
Brian- inspection on grid line PD Phone #: ###-#### ok after spec insp sign offs
BLD-Other5/23/20195/24/20195/30/2019APEND
DetailsDave Hannah
Brian- column inspection- gridline PA North Wall Phone #: ###-#### ok after spec insp sign offs
BLD-Concrete5/22/20195/22/20195/30/2019APEND
DetailsDave Hannah
Brian-column line PA in the garage Phone #: ###-#### ok after spec insp sign offs
Extend Permit 90/180 days5/22/20195/22/20195/22/2019ACANC
DetailsDave Hannah
BLD-Footing5/20/20195/21/20195/22/2019APASS
DetailsDave Hannah
spread footer // Brian Phone #: ###-####
BLD-Other5/21/20195/22/20195/22/2019APART
DetailsDave Hannah
Brian-column line PA in the garage Phone #: ###-####
BLD-Wall Bracing5/16/20195/17/20195/20/2019PPEND
DetailsDave Hannah
wall cast in place, W side // Brian Phone #: ###-#### ok after spec inspection
BLD-Foundation5/15/20195/15/20195/16/2019PDONE
DetailsDave Hannah
rebar on N wall // Brian Phone #: ###-####
BLD-Foundation5/9/20195/10/20195/15/2019APART
DetailsDave Hannah
NW wall // Brian Phone #: ###-####
BLD-Foundation5/10/20195/13/20195/15/2019APART
DetailsDave Hannah
Ryan Phone #: ###-####
BLD-Foundation5/14/20195/15/20195/15/2019APART
DetailsDave Hannah
Brian Phone #: ###-####
BLD-Foundation5/2/20195/3/20195/6/2019ADONE
DetailsDave Hannah
west wall // Brian Phone #: ###-####
BLD-Framing/Rough-in5/3/20195/6/20195/6/2019ANR
DetailsDave Hannah
Brian Phone #: ###-####
BLD-Concrete10/3/201910/4/2019 A 
DetailsDave Hannah
Ryan Phone #: ###-####