BLD-Concrete | 1/9/2020 | 1/10/2020 | 1/10/2020 | A | PEND |
Dave Hannah
|
|
|
Charlie Phone #: ###-#### ok with spec inspection
|
BLD-Foundation | 12/9/2019 | 12/9/2019 | 12/11/2019 | P | PASS |
Dave Hannah
|
|
|
Charle Phone #: ###-#### ok after spec inspection sign offs
|
BLD-Concrete | 10/10/2019 | 10/11/2019 | 10/11/2019 | A | CANC |
Jim Storey
|
|
|
Brian Phone #: ###-####
|
BLD-Other | 8/13/2019 | 8/13/2019 | 8/16/2019 | P | PASS |
Dave Hannah
|
|
|
slab on deck level G //Brian Phone #: ###-####
|
BLD-Foundation | 7/17/2019 | 7/18/2019 | 7/18/2019 | P | PASS |
Dave Hannah
|
|
|
Brian- foundation slab Phone #: ###-####
|
BLD-Concrete | 7/8/2019 | 7/8/2019 | 7/9/2019 | P | PASS |
Dave Hannah
|
|
|
slab // brian Phone #: ###-####
|
BLD-Concrete | 7/1/2019 | 7/2/2019 | 7/2/2019 | A | PEND |
Dave Hannah
|
|
|
rebar in columns - gridline P15 // Brian Phone #: ###-####
|
BLD-Other | 6/27/2019 | 6/28/2019 | 6/28/2019 | A | DEFR |
Mike Jordan
|
|
|
Brian- inspection for inwall rebar PCLINE Phone #: ###-####. Pending special inspection.
|
BLD-Concrete | 6/20/2019 | 6/21/2019 | 6/24/2019 | A | PASS |
Dave Hannah
|
|
|
rebar- Rid thin P15-Brian Phone #: ###-####
|
BLD-Foundation | 6/24/2019 | 6/25/2019 | 6/24/2019 | A | CANC |
Dave Hannah
|
|
|
P D line- Brian Phone #: ###-####
|
BLD-Wall Bracing | 6/18/2019 | 6/19/2019 | 6/19/2019 | A | PART |
Brandon Shaw
|
|
|
Pending Special Inspection... rebar line PB
|
BLD-Foundation | 6/13/2019 | 6/14/2019 | 6/17/2019 | A | PASS |
Dave Hannah
|
|
|
PB line- Brian Phone #: ###-####
|
BLD-Foundation | 6/12/2019 | 6/13/2019 | 6/17/2019 | A | PASS |
Dave Hannah
|
|
|
rebar on gridline PA // Brian Phone #: ###-####
|
BLD-Other | 6/11/2019 | 6/12/2019 | 6/12/2019 | A | PEND |
Dave Hannah
|
|
|
Brian-shear wall rebar-grid line PB Phone #: ###-#### ok after spec final signoffs for placement of concrete
|
BLD-Wall Bracing | 6/5/2019 | 6/6/2019 | 6/6/2019 | A | PEND |
Dave Hannah
|
|
|
shear (pc grid line) // Brian Phone #: ###-#### ok after spec inspection sign off
|
BLD-Foundation | 6/3/2019 | 6/4/2019 | 6/4/2019 | A | PEND |
Dave Hannah
|
|
|
Brian- red line P15 going north to south Phone #: ###-#### ok after spec inspection sign off
|
BLD-Wall Bracing | 5/31/2019 | 6/3/2019 | 6/4/2019 | A | PEND |
Dave Hannah
|
|
|
Brian Phone #: ###-#### ok after spec inspection sign off
|
BLD-Other | 5/28/2019 | 5/29/2019 | 6/4/2019 | A | PEND |
Dave Hannah
|
|
|
concrete wall // Brian Phone #: ###-#### ok after spec inspection sign off
|
BLD-Footing | 5/30/2019 | 5/31/2019 | 6/4/2019 | A | PEND |
Dave Hannah
|
|
|
Brian-on grid line P15 ON THE EAST NE SIDE Phone #: ###-#### ok after spec inspection sign off
|
BLD-Foundation | 5/29/2019 | 5/30/2019 | 5/30/2019 | A | PEND |
Dave Hannah
|
|
|
Brian- inspection on grid line PD Phone #: ###-#### ok after spec insp sign offs
|
BLD-Other | 5/23/2019 | 5/24/2019 | 5/30/2019 | A | PEND |
Dave Hannah
|
|
|
Brian- column inspection- gridline PA North Wall Phone #: ###-#### ok after spec insp sign offs
|
BLD-Concrete | 5/22/2019 | 5/22/2019 | 5/30/2019 | A | PEND |
Dave Hannah
|
|
|
Brian-column line PA in the garage Phone #: ###-#### ok after spec insp sign offs
|
Extend Permit 90/180 days | 5/22/2019 | 5/22/2019 | 5/22/2019 | A | CANC |
Dave Hannah
|
|
|
|
BLD-Footing | 5/20/2019 | 5/21/2019 | 5/22/2019 | A | PASS |
Dave Hannah
|
|
|
spread footer // Brian Phone #: ###-####
|
BLD-Other | 5/21/2019 | 5/22/2019 | 5/22/2019 | A | PART |
Dave Hannah
|
|
|
Brian-column line PA in the garage Phone #: ###-####
|
BLD-Wall Bracing | 5/16/2019 | 5/17/2019 | 5/20/2019 | P | PEND |
Dave Hannah
|
|
|
wall cast in place, W side // Brian Phone #: ###-#### ok after spec inspection
|
BLD-Foundation | 5/15/2019 | 5/15/2019 | 5/16/2019 | P | DONE |
Dave Hannah
|
|
|
rebar on N wall // Brian Phone #: ###-####
|
BLD-Foundation | 5/9/2019 | 5/10/2019 | 5/15/2019 | A | PART |
Dave Hannah
|
|
|
NW wall // Brian Phone #: ###-####
|
BLD-Foundation | 5/10/2019 | 5/13/2019 | 5/15/2019 | A | PART |
Dave Hannah
|
|
|
Ryan Phone #: ###-####
|
BLD-Foundation | 5/14/2019 | 5/15/2019 | 5/15/2019 | A | PART |
Dave Hannah
|
|
|
Brian Phone #: ###-####
|
BLD-Foundation | 5/2/2019 | 5/3/2019 | 5/6/2019 | A | DONE |
Dave Hannah
|
|
|
west wall // Brian Phone #: ###-####
|
BLD-Framing/Rough-in | 5/3/2019 | 5/6/2019 | 5/6/2019 | A | NR |
Dave Hannah
|
|
|
Brian Phone #: ###-####
|
BLD-Concrete | 10/3/2019 | 10/4/2019 | | A | |
Dave Hannah
|
|
|
Ryan Phone #: ###-####
|