BLD-Final | 7/16/2019 | 7/17/2019 | 7/17/2019 | A | PASS |
Dave Hannah
|
|
|
Tom Phone #: ###-####
|
FIRE-Final Inspection | 7/17/2019 | 7/17/2019 | 7/17/2019 | P | PASS |
Jim Page
|
|
|
FIre sprinkler inspection has been completed (Fire sprinkler modifications was completed under permit for Knitting Factory), no fire alarm modifications in area of work, fire exitnguishers are placed in common areas with current ispection tags. Final life fire safety inspection for area of work complete.
Tom Phone #: ###-####
|
BLD-Final | 4/17/2019 | 4/17/2019 | 4/17/2019 | P | FAIL |
Jim Storey
|
|
|
Tom Phone #: ###-#### need fire final
|
BLD-Framing/Rough-in | 2/26/2019 | 2/27/2019 | 2/27/2019 | A | PASS |
Brandon Shaw
|
|
|
Seal penetrations in ceiling, at mech. room...
|
BLD-Framing/Rough-in | 2/26/2019 | 2/26/2019 | 2/26/2019 | P | CANC |
Jim Storey
|
|
|
Tom Phone #: ###-#### mec inspector and arch. plan states shaft
|
BLD-Framing/Rough-in | 1/31/2019 | 2/1/2019 | 2/1/2019 | A | PART |
Brandon Shaw
|
|
|
Framing around mech duct work, second floor...
|
BLD-Conference | 12/20/2018 | 12/20/2018 | 12/20/2018 | P | DONE |
Dave Hannah
|
|
|
Tom Phone #: ###-####
|