BLD-Blower Door Test Results | 11/14/2019 | 11/14/2019 | 11/14/2019 | P | DONE |
Tell Riley
|
|
|
4.45 ACH 50
|
BLD-Final | 11/13/2019 | 11/14/2019 | 11/14/2019 | P | PASS |
Tell Riley
|
|
|
Alex Phone #: ###-####///corrections made//
|
DOC - Permit Finaled | 11/14/2019 | 11/14/2019 | 11/14/2019 | P | PASS |
Tell Riley
|
|
|
|
BLD-Final | 11/12/2019 | 11/13/2019 | 11/13/2019 | A | FAIL |
Tell Riley
|
|
|
Alex Phone #: ###-####//need blower door test//add step at door in garage//need fall prevention devices at windows with sill under 24" on 2nd floor//
|
BLD-Energy code compliance | 9/3/2019 | 9/4/2019 | 9/4/2019 | A | PASS |
Tell Riley
|
|
|
Alex Phone #: ###-####
|
BLD-Wall cover | 9/3/2019 | 9/4/2019 | 9/4/2019 | P | CANC |
Tell Riley
|
|
|
Alex Phone #: ###-####//only needs energy inspection//
|
BLD-Framing/Rough-in | 8/29/2019 | 8/30/2019 | 8/30/2019 | P | PASS |
Mike Jordan
|
|
|
aLEX Phone #: ###-####
|
BLD-Framing/Rough-in | 7/24/2019 | 7/25/2019 | 7/25/2019 | A | CANC |
Tell Riley
|
|
|
alex Phone #: ###-####
|
BLD-Wall Bracing | 7/24/2019 | 7/24/2019 | 7/24/2019 | P | PASS |
Tell Riley
|
|
|
ok//need to add holdowns a PFH//7/23/19 inspection completed//needed to change to wall bracing//canceled framing//
|
BLD-Framing/Rough-in | 7/22/2019 | 7/23/2019 | 7/24/2019 | A | CANC |
Tell Riley
|
|
|
Alex Phone #: ###-####//all panels blocked//nailing ok//add hold down at PFH per plans--will check at framing//
|
BLD-Conference | 7/18/2019 | 7/18/2019 | 7/18/2019 | P | DONE |
Tell Riley
|
|
|
caller thinks the side setbacks are not 5'' Phone #: ###-####//verified setbacks at footing and foundation with concrete contractor from survey points on the lot//all points measured at the inspections were completed with a string line running from survey pins//
|
BLD-Foundation | 7/11/2019 | 7/11/2019 | 7/11/2019 | P | CANC |
Tell Riley
|
|
|
Andras Phone #: ###-####//requested underfloor//no inspection required//
|
BLD-Foundation | 6/24/2019 | 6/24/2019 | 6/24/2019 | P | PASS |
Tell Riley
|
|
|
Phone #: 2086971241 >> Inspection requested via mobile web by Heron//rebar installed//vents ok//hold downs to be installed at framing//re-check setbacks--ok//
|
BLD-Footing | 6/21/2019 | 6/21/2019 | 6/21/2019 | A | PASS |
Tell Riley
|
|
|
Phone #: 2086971241 >> Inspection requested via mobile web by Heron//setbacks ok per approved plans//rebar installed per plans//footing depth and width ok per plans//
|