Information based on query as of Monday, May 13, 2024.
Permit Information
Permit NumberBLD19-01777
StatusFinaled
Name TRAIL FAMILY TRUST DATED 8/20/93
Site Address 4935 N QUAIL SUMMIT PL
Project Name 
Customer Number 
ePlanReviewNo
Description
***06/27 PLAN MOD TO CHANGE PATIO FROM CONCRETE TO PAVERS*** ***W.U.I. ZONE A FOOTHILLS CLASS "A" ROOF AND NON-COMBUSTIBLE CONSTRUCTION REQUIRED*** Permit for the construction of a new 3170 sq. ft., one story single family dwelling with 3 bedrooms, 2.5 bathrooms, approximately 126 sq. ft. of covered patio/porch and a 1941 sq. ft. attached garage per the approved plans and any notations. Prescriptive Energy Compliance. R-1C zoning and setbacks per planning. ***RDP*** ***SPRINKLERS ARE NOT REQUIRED*** LGM
A letter from the applicant’s geotechnical engineer indicating that the footing/column subgrade is acceptable must be approved by Public Works prior to scheduling a footing inspection. Please e-mail the stamped inspection approval letter to mjannusch@cityofboise.org and allow 24 hours for subgrade approval processing. Call Melissa Jannusch at 208-608-7168 with questions.

Prior to obtaining a final for the permit, the roof storm drainage system must be inspected by Public Works. Call Melissa Jannusch at 208-608-7168.

The final inspection of the site grading and drainage work shall be done by the design engineer. Written approval shall be submitted to Boise Public Works prior to the issuance of the building final.

An erosion and sediment control site preparation inspection is required for this site. The site preparation inspection takes place after all required erosion and sediment control best management practices have been installed and BEFORE any earthwork takes place. Call 208-608-7070 to schedule an inspection.
Contact Information
See Activities list for contact information
Show All Activities
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
BLD-Final7/30/20207/31/20207/31/2020APASS
DetailsTony Young
Tom; Phone #: ###-####
DOC - Permit Finaled7/31/20207/31/20207/31/2020PPASS
DetailsTony Young
BLD-Final7/13/20207/13/20207/13/2020PPART
DetailsTony Young
Tom *screened* Phone #: ###-####// needs hill side public works approval,, needs minor fire caulking// then ok
BLD-Aging Inspection4/17/20204/17/20204/22/2020 PASS
DetailsTony Young
BLD-Energy code compliance12/5/201912/5/201912/5/2019PPASS
DetailsTony Young
Tom Phone #: ###-####
BLD-Wall cover12/4/201912/5/201912/5/2019APASS
DetailsTony Young
Tom Phone #: ###-####,, ok to cover
BLD-Framing/Rough-in11/27/201911/29/201911/29/2019APASS
DetailsTony Young
Tom Phone #: ###-####,, ok to insulate
BLD-Other11/4/201911/4/201911/4/2019PPASS
DetailsTony Young
Tom-- inspection for soffit and facia Phone #: ###-####/// 2 layers 5/8 " sheet rock on the facia and soffits ok
BLD-Wall Bracing10/10/201910/10/201910/13/2019PPASS
DetailsDave Hannah
tOM Phone #: ###-#### ok to cover ext needs to install three hd hold downs
BLD-Other8/12/20198/12/20198/14/2019ADEFR
DetailsTony Young
there''s black pvc type pipe open-they''ve stubbed off the sewer pipe. It''s in the back yard at the back of lot. neighbor is very concerned that if more rains come it could flood the people out below,, see ESC permit notes
BLD-Foundation8/9/20198/12/20198/12/2019PPART
DetailsTony Young
pour time 1 ..wall // mark Phone #: ###-####
work in progress
BLD-Footing8/8/20198/9/20198/9/2019PPART
DetailsTony Young
Mark- pouring schedule is at 3pm Phone #: ###-####,, garages footings ok,, set backs appear ok
BLD-Foundation7/24/20197/25/20197/25/2019PPASS
DetailsDave Hannah
Mark-pour 2:30 Phone #: ###-####
BLD-Footing7/22/20197/22/20197/22/2019PPART
DetailsTell Riley
pouring at 8am tomorrow morning // Dusty Phone #: ###-####//hillside ok per Melissa//rebar ok//side and back setbacks of main house ok//will need to chech setbacks at wall inspection and garage section//
BLD-Footing7/17/20197/18/20197/18/2019ACANC
DetailsDave Hannah
Pour at 1045 // Mark Phone #: ###-####