Information based on query as of Saturday, May 18, 2024.
Permit Information
Permit NumberBLD19-01952
StatusFinaled
Name WAYNCO CONSTRUCTION CO
Site Address 1185 S VISTA AVE
Project NameMcDonald's #4289
Customer Number 
ePlanReviewYes
Description
(MCDONALD’S #4289) ""PLAN MODIFICATION TO ADD A GREASE INTERCEPTOR"" Permit is to remodel the interior and exterior of an existing 4,471 sq. ft. assembly restaurant and new construction of exterior wall framing to create a total of 320 sq. ft. building addition (175 sq. ft. on the west end of the existing building between the existing drive-thru windows and 145 sq. ft. cooler building on the north end creating a building that is 4,791 sq. ft. (3,086 sq. ft. existing main floor + 175 sq. ft. new addition + 145 sq. ft. cooler addition + 1,385 sq. ft. basement). Approval is contingent upon adhering to the approved plans on file, plan review report and attached engineering. Work to include: removal of select site work, removal of drive-thru structural canopy, removal of select storefront windows, removal of select exterior finish, removal of select exterior walls, removal of select exterior storefront doors, removal of select mansard roof assembly, removal of select interior nonbearing walls, removal of interior menu boards and relocate, removal of dining area seating/tables/counters, select removal of select kitchen equipment and select replacement of kitchen equipment, select new site work, new exterior site concrete sidewalk, replace guardrail leading to basement, select new footing for addition, select new exterior wall infill, select new exterior wall assembly, select new exterior storefronts window and doors, select new interior nonbearing walls, relocate beverage bar counter, restroom remodel, new dining room fixture, millwork, select new kitchen equipment, select new exterior walk-in cooler, exterior roof access ladder to be in the interior of the building and adding a new roof hatch, new exterior TPO roof, select new gypsum and suspended acoustic ceiling, select new light fixtures, electrical work, plumbing work, mechanical work and interior finishes in compliance with Ch. 8 of the current IBC. Note: special inspection required, see attached form 310. Note 2: A separate sign permit is required. This building is Not Fire Sprinklered. **JG**
Contact Information
See Activities list for contact information
Show All Activities
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
BLD-Final3/27/20203/27/20203/27/2020PPASS
DetailsJim Storey
no card on site.
FIRE-Final Inspection3/26/20203/26/20203/26/2020PPASS
DetailsTroy Cobbley
Life safety passed.

Phone #: ###-#### Inspection requested via web by Dan Ryan
BLD-Aging Inspection3/25/20203/25/20203/25/2020 PASS
DetailsJim Storey
Life safety will be ok to final when the exit discharge lighting is installed and tested. fire permit open
BLD-Final11/7/201911/8/201911/12/2019PPASS
DetailsJim Storey
Justin Phone #: ###-####
BLD-Final11/7/201911/8/201911/12/2019PNR
DetailsJim Storey
Justin Phone #: ###-####
FIRE-Final Inspection11/7/201911/8/201911/8/2019AFAIL
DetailsTroy Cobbley
Life safety will be ok to final when the exit discharge lighting is installed and tested.

Justin Phone #: ###-####
BLD-Framing/Rough-in11/7/201911/7/201911/7/2019PPASS
DetailsJim Storey
Justin Phone #: ###-####
BLD-Ceiling Grid Inspection10/28/201910/28/201910/28/2019PPART
DetailsJim Storey
Justin Phone #: ###-#### grid ok pending trades.
BLD-Framing/Rough-in10/9/201910/9/201910/9/2019PPASS
DetailsJim Storey
Justin-partial Phone #: ###-#### restarooms ok to cover.
BLD-Framing/Rough-in8/28/20198/28/20198/28/2019PPASS
DetailsJim Storey
Justin Phone #: ###-####
BLD-Framing/Rough-in8/20/20198/20/20198/20/2019PPART
DetailsBrandon Shaw
Parapet walls and exterior sheeting...
BLD-Footing8/15/20198/16/20198/16/2019PPASS
DetailsJim Storey
foundation and rebar // Justin Phone #: ###-####
BLD-Foundation8/14/20198/15/20198/15/2019APART
DetailsJim Storey
Justin Phone #: ###-#### wip// si pending