Information based on query as of Saturday, May 4, 2024.
Permit Information
Permit NumberBLD19-02122
StatusIssued
Name ESI
Site Address 1100 W IDAHO ST
Project Name11th & Idaho Foundation/Supers
Customer NumberESC19-00779
ePlanReviewYes
Description
(11TH AND IDAHO) (FOUNDATION AND SUPERSTRUCTURE ONLY) **Project Management- Ron Hill** (DRH18-00260) (DRH19-00228) This building is fully fire sprinklered because it is a high-rise. To construct the concrete and structural steel phase (Package I) for a new 10 story office building having a total floor area of about 180,900 square feet. The shell and core improvement phase (Package II) will be under a separate permit (BLD19-02339). Work is to include concrete spread footings, concrete continuous footings, concrete mat footings, concrete piers, concrete foundation walls including mechanical pits and elevator pits, concrete slabs on grade including mechanical pits and elevator pits, steel columns, steel base plates, steel girders, steel beams, concrete filled steel floor decks, steel roof decks, steel braced frames, steel moment frames, and steel stairways with steel pan concrete filled treads. Other drawings that show work beyond this phase are not approved and are for reference only. Special Inspection is required for soils, concrete, steel including welding and bolting, wind resistance, seismic resistance, fire-resistance coatings, fire-resistant joints, and smoke control. This permit is not intended to establish a Certificate of Occupancy for any portion of this building. The work is required to comply with the approved drawings, with the structural design, with the plan review report, and with all applicable codes and ordinances. The fire sprinkler system and the fire alarm system will be installed in conjunction with a future phase permit. **JHB**
Contact Information
See Activities list for contact information
Show All Activities
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
BLD-Wall cover5/18/20205/18/20205/18/2020PDEFR
DetailsJim Storey
please come inspect the daft stop on the roof for the parapet. Roof line. Phone #: ###-#### Inspection requested via web by Andy Pense

bld19-02339
BLD-Framing/Rough-in5/7/20205/7/20205/7/2020PPASS
DetailsDave Hannah
Framing inspection on the SE corner soffit on the first floor. Phone #: ###-#### Inspection requested via web by Andy Pense
BLD-Framing/Rough-in5/4/20205/5/20205/6/2020PPASS
DetailsBrandon Shaw
North East corner framing inspection to cover. 6th floor to 8th. Also the soffit on the first floor North elevation. Phone #: ###-#### Inspection requested via web by Andy Pense
BLD-Framing/Rough-in4/30/20204/30/20204/30/2020PPART
DetailsDave Hannah
please get with Jake ISI when on site. Phone #: ###-#### Inspection requested via web by Andy Pense
BLD-Framing/Rough-in4/28/20204/29/20204/30/2020APASS
DetailsDave Hannah
Please come inspect the North East exterior framing from GL, 8-11 levels 6-10. Phone #: ###-#### Inspection requested via web by Andy Pense
BLD-Framing/Rough-in4/21/20204/22/20204/30/2020PPASS
DetailsDave Hannah
Inspection on the Framing to cover. West elevations to the roof. South West corner to the roof. Phone #: ###-#### Inspection requested via web by Andy Pense
BLD-Framing/Rough-in4/23/20204/23/20204/30/2020APASS
DetailsDave Hannah
Inspection on the Framing to cover. West elevations to the roof. South West corner to the roof. Phone #: ###-#### Inspection requested via web by Andy Pense
BLD-Framing/Rough-in4/16/20204/20/20204/20/2020APASS
DetailsDave Hannah
First floor North Exterior soffit. Phone #: ###-#### Inspection requested via web by Andy Pense
BLD-Framing/Rough-in4/13/20204/14/20204/14/2020APASS
DetailsDave Hannah
Inspection for exterior soffit North-West elevation floors 6, 7, 8. Call Mike when your on site. Phone #: ###-#### Inspection requested via web by Andy Pense
BLD-Framing/Rough-in4/6/20204/6/20204/8/2020PPART
DetailsDave Hannah
Framing inspection for the 2nd 3rd 4th floor interior. south side soffit first floor south side ; first floor east side. Phone #: ###-#### Inspection requested via web by Andy Pense
BLD-Framing/Rough-in3/31/20204/1/20204/1/2020PPART
DetailsDave Hannah
Framing inspections on the first floor South and West elevations for the ribbon framing to get sheeted. Phone #: ###-#### Inspection requested via web by Andy Pense sw corner of 2,3 &4 ok
BLD-Framing/Rough-in3/27/20203/30/20203/30/2020APART
DetailsDave Hannah
Please inspected the West side of the building framing. Call Andy when on site. Phone #: ###-#### Inspection requested via web by Andy Pense nw corner levels 2,3and 4 ok
BLD-Framing/Rough-in3/25/20203/26/20203/26/2020APART
DetailsDave Hannah
Framing inspection please get with Andy Pense/ Mike Koci Phone #: ###-#### Inspection requested via web by Andy Pense first floor ok to start one siding top of walls
BLD-Framing/Rough-in3/25/20203/25/20203/25/2020APART
DetailsDave Hannah
Framing inspection on the north elevations. Phone #: ###-#### Inspection requested via web by Andy Pense
BLD-Framing/Rough-in3/16/20203/16/20203/16/2020PPART
DetailsDave Hannah
PM inspection for the East end framing. Please get with Mike Koci or Andy Pense. Phone #: ###-#### Inspection requested via web by Andy Pense ok to cover
BLD-Framing/Rough-in3/9/20203/10/20203/10/2020APART
DetailsDave Hannah
Please come visit to view the framing on the South East elevation. Phone #: ###-#### Inspection requested via web by Andy Pense FLOORS 2,3 & 4 EAST end south wall ok to cover
BLD-Framing/Rough-in3/6/20203/9/20203/9/2020ACANC
DetailsDave Hannah
Framing clip inspection. Please get with Mike Koci and or Andy Pense Phone #: ###-#### >> Inspection requested via web by Andy Pense Inspection cancelled from web by: Andy Pense
BLD-Framing/Rough-in3/2/20203/3/20203/3/2020PPASS
DetailsDave Hannah
Please come out and inspect the screw and attachment of clips prior to sheeting. Please see Mike Koci or Andy Pense for comments. Thank you. Phone #: ###-#### Inspection requested via web by Andy Pense
BLD-Framing/Rough-in2/19/20202/21/20202/21/2020APART
DetailsDave Hannah
please stop by and check out installation of the clips on 3rd-5th. Get with Mike Koci while on site. Phone #: ###-#### Inspection requested via web by Andy Pense
BLD-Wall Bracing2/5/20202/6/20202/6/2020APASS
DetailsDave Hannah
Can we get an inspector to check out our clips attached to the bent plate levels 2 and 3. Please reach out to Mike Koci or Andy Pense Superintendents on site. Phone #: ###-#### Inspection requested via web by Andy Pense
BLD-Other1/28/20201/29/20201/29/2020PPEND
DetailsDave Hannah
Need to have the framing clips to the steel inspected please. Phone #: ###-#### Inspection requested via web by Andy Pense work in progresss
BLD-Other1/28/20201/29/20201/29/2020ADONE
DetailsDave Hannah
Need to have the Fire proofing inspected on the 2nd floor. Please get a hold of Mr. Mike Koci or my self when on site.
Thank you. Phone #: ###-#### Inspection requested via web by Andy Pense
BLD-Concrete1/17/20201/21/20201/23/2020APASS
DetailsDave Hannah
SOG Bar inspection pre pour. Phone #: ###-#### Inspection requested via web by Andy Pense
BLD-Concrete12/16/201912/19/201912/19/2019APEND
DetailsDave Hannah
concrete placement 2nd level east. Phone #: ###-#### Inspection requested via web by Andy Pense
BLD-Concrete12/12/201912/13/201912/13/2019APEND
DetailsDave Hannah
please come out and do a pre pour inspection. Phone #: ###-#### Inspection requested via web by Andy Pense east half second fl ok after spec inspection sign off
BLD-Footing10/21/201910/25/201910/25/2019APEND
DetailsMike Jordan
GL-A continuous footings need to be inspected. Phone #: ###-#### Inspection requested via web by Andy Pense. Ok pending special inspection.
BLD-Foundation10/21/201910/23/201910/23/2019APASS
DetailsDave Hannah
GL-1 walls need to be inspected. Phone #: ###-#### Inspection requested via web by Andy Pense
BLD-Footing10/17/201910/18/201910/18/2019PPASS
DetailsJim Storey
GL-A spread footings. Please see on site superintendent to confirm. Phone #: ###-#### Inspection requested via web by Andy Pense
BLD-Foundation10/14/201910/17/201910/17/2019APART
DetailsJim Storey
Continuous Perimeter footings. Phone #: ###-#### Inspection requested via web by Andy Pense 1 grid line wall ok parallel to idaho road/ no one in office no log seen.
BLD-Foundation10/8/201910/9/201910/9/2019PPEND
DetailsDave Hannah
Please call Andy Pense ###-#### if there are and comments or concerns.

Shear Walls and Piers. Phone #: ###-#### Inspection requested via web by Andy Pense ok to place concrete after spec inpc sign offs
BLD-Footing10/8/201910/8/201910/9/2019PPASS
DetailsDave Hannah
Please call Andy Pense ###-#### if there are and comments or concerns.

Continuous Footings. Phone #: ###-#### Inspection requested via web by Andy Pense ok to place concrete after spec inpc sign offs
BLD-Footing10/4/201910/7/201910/7/2019APEND
DetailsDave Hannah
Please get with Andy Pense with any concerns or comments thank you.
We need to have a footing inspection on the material man hoist footing as well as the elevator footing.

Thank you. Phone #: ###-#### Inspection requested via web by Andy Pense ok to place concrete after spec insp final sign off is oked
BLD-Footing9/30/201910/2/201910/3/2019APASS
DetailsDave Hannah
Brace frame footing inspection at Grid 5.2. Large mat footing in middle of project. Please call Mike when in route. Thanks! Phone #: ###-#### Inspection requested via web by Mike Koci ok to place concrete after spec inspection sign offs
BLD-Footing9/30/201910/1/201910/1/2019APASS
DetailsDave Hannah
Footing inspection at Gridline 1 and 3 along gridline H. The southeast section of the building. Please call Mike when in route. Thanks! Phone #: ###-#### Inspection requested via web by Mike Koci
BLD-Footing9/27/20199/30/201910/1/2019PPASS
DetailsDave Hannah
Inspection for Tower crane mat footing - please call Mike when headed to the site. Thanks! Phone #: ###-#### Inspection requested via web by Mike Koci
BLD-Footing9/20/20199/25/20199/25/2019APEND
DetailsDave Hannah
For the core footing Phone #: ###-#### Inspection requested via web by Andy Pense
BLD-Footing9/19/20199/23/20199/24/2019APART
DetailsDave Hannah
Inspection of crane footing. Phone #: ###-#### Inspection requested via web by Andy Pense
BLD-Footing9/20/20199/24/20199/24/2019APART
DetailsDave Hannah
spread footings on grids 9, 10 ; 11, from A to H Phone #: ###-#### Inspection requested via web by Andy Pense