BLD-Final | 5/7/2020 | 5/8/2020 | 5/8/2020 | P | PASS |
Tony Young
|
|
|
ok pending others
|
BLD-Final | 5/6/2020 | 5/6/2020 | 5/6/2020 | P | PEND |
Tony Young
|
|
|
Please note we are waiting on the results for the Mechanical inspection. All T;B documents have been submitted and inspection called for By the mechanical contractor on 5/5, KMD. I do not get the results from that particular inspection results. Any questions please feel free to contact me at anytime. Thank You, Phone #: ###-#### Inspection requested via web by Ron Oswald// needs trades, // f/l/s
|
FIRE-Final Inspection | 5/4/2020 | 5/4/2020 | 5/4/2020 | P | PASS |
Jim Page
|
|
|
No fire sprinklers, no fire alarms, fire extinguishers are placed with current inspection tags in occupied section, none required in vanilla spaces, a knox box has been placed by the main entry. Final life fire safety inspection complete, signature provided on permit sign off card.
Ready for Fire Life safety Inspection- Any questions please feel free to contact me at anytime. Thank You, Phone #: ###-#### Inspection requested via web by Ron Oswald
|
BLD-Framing/Rough-in | 2/28/2020 | 3/2/2020 | 3/2/2020 | A | PASS |
Tony Young
|
|
|
Rough Framing for shell portion, Ready Now. Any questions please feel free to contact me at anytime.
Thank You, Phone #: ###-#### Inspection requested via web by Ron Oswald
|
BLD-Energy code compliance | 2/20/2020 | 2/20/2020 | 2/20/2020 | A | PART |
Tony Young
|
|
|
Partial Insulation inspection at Shear wall/Demising wall in interior Portion of building, For shear placement after passed inspection. Any questions please feel free to contact me at anytime.
Thank You. Phone #: ###-#### Inspection requested via web by Ron Oswald// south end ok
|
BLD-Framing/Rough-in | 2/20/2020 | 2/20/2020 | 2/20/2020 | A | PART |
Tony Young
|
|
|
Partial Exterior rough Framing for Buildouts at building perimeter. Any questions please feel free to contact me at anytime. Thank You, Phone #: ###-#### Inspection requested via web by Ron Oswald// work in progress,, ok to cover as needed pending trades
|
BLD-Energy code compliance | 2/19/2020 | 2/20/2020 | 2/20/2020 | P | CANC |
Tony Young
|
|
|
Partial at The shear wall demising Phone #: ###-#### >> Inspection requested via web by Ron Oswald Inspection cancelled from web by: Ron Oswald
|
BLD-Framing/Rough-in | 2/11/2020 | 2/12/2020 | 2/12/2020 | P | PART |
Tony Young
|
|
|
This inspection is for the Roof envelope, Sheeting Etc. Will be ready after 2:00 pm Any questions please feel free to contact me at anytime.
Thank You, Phone #: ###-#### Inspection requested via web by Ron Oswald// roof areas ok to cover
|
BLD-Concrete | 1/15/2020 | 1/16/2020 | 1/16/2020 | A | PEND |
Tony Young
|
|
|
This inspection is for the Top out lift at the Northeast, East and Southeast cmu wall areas. Mti on schedule for 10:30 am for rebar and grout placement. Any questions or concerns please feel free to contact me at anytime.
Thank You, Phone #: ###-#### Inspection requested via web by Ron Oswald
|
BLD-Concrete | 1/13/2020 | 1/14/2020 | 1/14/2020 | P | PEND |
Tony Young
|
|
|
This inspection is for 5th lift at 2:00 pm ready time. MTI on task for Rebar inspection and Grout observation. Any questions please feel free to contact me at anytime.
Thank You, Phone #: ###-#### Inspection requested via web by Ron Oswald
|
BLD-Concrete | 1/10/2020 | 1/13/2020 | 1/13/2020 | A | PART |
Tony Young
|
|
|
This inspection is for the Balance of the 4th lift at the North East, East and South East block line. Mti scheduled to Inspect and observe at 10:00 am. Any questions or concerns please feel free to contact me at anytime.
Thank You. Phone #: ###-#### Inspection requested via web by Ron Oswald/// met with Special inspector to go over rebar and cold weather issues,, ok pending report
|
BLD-Concrete | 1/9/2020 | 1/10/2020 | 1/10/2020 | P | PEND |
Tony Young
|
|
|
This inspection is for partial Forth lift grout at CMU. It was noted as per our conversation that MTI should and will be more thorough while providing special inspections on this project. Again they are scheduled to provide inspection and observation for this Grout process. This grout process is scheduled for 2:00 pm.
Thank You, Phone #: ###-#### Inspection requested via web by Ron Oswald// pending special inspection
|
BLD-Concrete | 1/7/2020 | 1/8/2020 | 1/8/2020 | A | PART |
Tony Young
|
|
|
This inspection is for the balance of the 3rd lift at 11:00am West and north Walls. MTI on task for inspection and observation at same. I have the MTI prior reports onsite for review. Prisms are made and will be in transit for tomorrow. Any questions please feel free to contact me at anytime.
Thank You, Phone #: ###-#### Inspection requested via web by Ron Oswald// work in progress,, talked with the special inspector about bar overlap etc, will fix various areas
|
BLD-Concrete | 1/6/2020 | 1/7/2020 | 1/7/2020 | A | PART |
Tony Young
|
|
|
We canceled the afternoon inspections and are rescheduling for same inspection at 3rd lift for CMU rebar- MTI is scheduled for rebar and Observation inspection at 8:00 am. This lift will also entail two sets of pyramids for breaks. any questions please feel free to contact me at anytime.
Thank You Phone #: ###-#### Inspection requested via web by Ron Oswald
|
BLD-Concrete | 1/6/2020 | 1/7/2020 | 1/6/2020 | P | CANC |
Tony Young
|
|
|
This inspection is for partial 3rd lift at CMU. Contractor notes they will be ready at 2:00 pm. MTI will be onsite for Rebar and observation this lift. Any questions please feel free to contact me at anytime.
Thank You, Phone #: ###-#### >> Inspection requested via web by Ron Oswald Inspection cancelled from web by: Ron Oswald
|
BLD-Concrete | 1/6/2020 | 1/8/2020 | 1/6/2020 | P | CANC |
Tony Young
|
|
|
This inspection is for partial 3rd lift at CMU. Contractor notes they will be ready at 2:00 pm. MTI will be onsite for Rebar and observation this lift. Any questions please feel free to contact me at anytime.
Thank You, Phone #: ###-#### >> Inspection requested via web by Ron Oswald Inspection cancelled from web by: Ron Oswald
|
BLD-Concrete | 1/2/2020 | 1/3/2020 | 1/3/2020 | P | PEND |
Tony Young
|
|
|
This inspection is for rebar at CMU second lift. MTI on task for observation and Rebar inspection. Foreman states he will be ready for Grout at 2:00 pm. Any questions please feel free to contact me at anytime. Thank You, Phone #: ###-#### Inspection requested via web by Ron Oswald// pending special inspection report
|
BLD-Concrete | 12/27/2019 | 12/30/2019 | 12/30/2019 | P | PEND |
Tell Riley
|
|
|
This is for CMU bar and Grout placement at first 4'' Lift. MTI on board for observation and inspection. Ready at 2:00 pm tentatively Any questions please feel free to call me at anytime. Thank You, Phone #: ###-#### Inspection requested via web by Ron Oswald//added bar in areas needed per plans//pend specials //
|
BLD-Concrete | 12/23/2019 | 12/23/2019 | 12/23/2019 | P | PEND |
Tony Young
|
|
|
This inspection is for Slab preparation to include welded wire and thickened opening pour throughs. Will be ready by 3:00 pm today. MTI will be inspecting and observing placement at 6:00 am Tomorrow.
Thank You, have a great day. Phone #: ###-#### Inspection requested via web by Ron Oswald// slab area ok when ready after raising rebar// pending special inspection
|
BLD-Footing | 12/10/2019 | 12/10/2019 | 12/10/2019 | P | PART |
Brandon Shaw
|
|
|
MTI will be on site for special inspections... Work in progress...
|
BLD-Foundation | 11/26/2019 | 11/27/2019 | 11/27/2019 | P | PART |
Tony Young
|
|
|
Sub contractor stated they would be ready at 1:00 pm, Placement scheduled for 3:00 pm. Any questions please feel free to contact me at anytime. Thank You, Phone #: ###-#### Inspection requested via web by Ron Oswald// poured,, MTI was on site for special inspections
|
BLD-Footing | 11/20/2019 | 11/21/2019 | 11/21/2019 | P | PART |
Tony Young
|
|
|
We will be ready for inspect near 1:00 pm. Any questions please feel free to contact me at anytime. Thank You, Phone #: ###-#### Inspection requested via web by Ron Oswald// special inspection also on site
|