BLD-Framing/Rough-in | 8/7/2020 | 8/7/2020 | 8/7/2020 | P | CANC |
Mike Jordan
|
|
|
progress shear inspection due to hidden OSB when wall is stood. Phone #: ###-#### Inspection requested via web by Dan Murrer
|
BLD-Wall Bracing | 8/7/2020 | 8/7/2020 | 8/7/2020 | P | PASS |
Mike Jordan
|
|
|
progress shear inspection due to hidden OSB when wall is stood. Phone #: ###-#### Inspection requested via web by Dan Murrer
|
BLD-Concrete | 8/5/2020 | 8/5/2020 | 8/5/2020 | P | PASS |
Mike Jordan
|
|
|
Non-Structural building interior slab on grade ready for placement Phone #: ###-#### Inspection requested via web by Dan Murrer
|
BLD-Energy code compliance | 8/5/2020 | 8/5/2020 | 8/5/2020 | P | PASS |
Mike Jordan
|
|
|
Metal Building Simple Saver Insulation System Complete Phone #: ###-#### Inspection requested via web by Dan Murrer
|
BLD-Framing/Rough-in | 7/17/2020 | 7/20/2020 | 7/20/2020 | A | PASS |
Mike Jordan
|
|
|
Pre-engineered building erected, ready for insulation covering of purlins and girts. Phone #: ###-#### Inspection requested via web by Dan Murrer
|
BLD-Energy code compliance | 6/23/2020 | 6/24/2020 | 6/24/2020 | A | PASS |
Jim Storey
|
|
|
Rigid Insulation Inspection on stem walls, ready for backfill. Phone #: ###-#### Inspection requested via web by Dan Murrer
|
BLD-Foundation | 6/18/2020 | 6/19/2020 | 6/19/2020 | A | PASS |
Mike Jordan
|
|
|
north stem wall rebar inspection (other half) Phone #: ###-#### Inspection requested via web by Dan Murrer. north perimeter stemwalls.
|
BLD-Foundation | 6/17/2020 | 6/18/2020 | 6/18/2020 | A | PASS |
Mike Jordan
|
|
|
rebar inspection for 1/2 of the stem walls. Phone #: ###-#### Inspection requested via web by Dan Murrer. South and west exterior stemwalls.
|
BLD-Foundation | 6/16/2020 | 6/17/2020 | 6/17/2020 | P | CANC |
Mike Jordan
|
|
|
Building Stem Wall Concrete. If possible, request inspection as soon as possible after lunch hour. Concrete scheduled for mid-afternoon. MTI scheduled for special inspections. Phone #: ###-#### >> Inspection requested via web by Dan Murrer Inspection cancelled from web by: Dan Murrer
|
BLD-Footing | 6/15/2020 | 6/16/2020 | 6/16/2020 | A | PART |
Mike Jordan
|
|
|
Rebar Inspection for Afternoon pour Phone #: ###-#### Inspection requested via web by Dan Murrer. Perimeter footings and column psd footings. Work in progress. Ok to place concrete pending special inspection.
|
BLD-Footing | 6/12/2020 | 6/15/2020 | 6/15/2020 | P | CANC |
Mike Jordan
|
|
|
If possible request inspection at 3PM. MTI will be there at 3PM as well for rebar, and concrete cylinders for pour at 4PM Phone #: ###-#### >> Inspection requested via web by Dan Murrer Inspection cancelled from web by: Dan Murrer
|
BLD-Other | 5/20/2020 | 5/20/2020 | 5/20/2020 | P | CANC |
Mike Jordan
|
|
|
Erosion and Sediment Control Program Site Preparation Inspection Phone #: ###-#### Inspection requested via web by Dan Murrer
|