FIRE-Final Inspection | 8/13/2020 | 8/13/2020 | 8/13/2020 | P | PART |
Jim Page
|
|
|
Life fire safety inspection for phase 3A complete.
Requesting a fire life inspection in Phase 3A. please give me a call 30 minutes in advice if possible to allow tie for my electrician to be onsite for assistance. Please contact Markus Schlegel if you have questions. Phone #: ###-#### Inspection requested via web by Markus Schlegel
|
BLD-Ceiling Grid Inspection | 8/4/2020 | 8/4/2020 | 8/4/2020 | P | PASS |
Mike Jordan
|
|
|
Requesting a ceiling grid inspection in the vestibule, lobby and room 106. Please contact Markus Schlegel if you have any questions. Thank you. Phone #: ###-#### Inspection requested via web by Markus Schlegel
|
BLD-Ceiling Grid Inspection | 7/30/2020 | 7/31/2020 | 7/31/2020 | A | PASS |
Mike Jordan
|
|
|
Requesting an inspection for Phase 3A. Please contact Markus Schlegel if you have questions. Thank you. Phone #: ###-#### Inspection requested via web by Markus Schlegel
|
BLD-Framing/Rough-in | 7/7/2020 | 7/7/2020 | 7/7/2020 | A | PASS |
Mike Jordan
|
|
|
Requesting an inspection on Exam room ; office door and wall infills. Restroom wall framing, lobby wall and soffit framing. Thank you. Phone #: ###-#### Inspection requested via web by Markus Schlegel
|
BLD-Final | 6/15/2020 | 6/16/2020 | 6/16/2020 | P | PART |
Tony Young
|
|
|
Requesting a partial building final after the fire life safety inspection phase 2 for requested for 7:30am. Please call me for confirmation. Phone #: ###-#### Inspection requested via web by Markus Schlegel// phase 2 ok
|
FIRE-Final Inspection | 6/15/2020 | 6/16/2020 | 6/16/2020 | A | PART |
Troy Cobbley
|
|
|
Phase two life safety passed.
|
BLD-Ceiling Grid Inspection | 5/28/2020 | 5/28/2020 | 5/28/2020 | P | PASS |
Mike Jordan
|
|
|
Phone #: ###-#### Inspection requested via web by Markus Schlegel
|
BLD-Framing/Rough-in | 5/8/2020 | 5/11/2020 | 5/11/2020 | A | PASS |
Mike Jordan
|
|
|
Phase II wall ; hard lid inspection framing inspection. Phone #: ###-#### Inspection requested via web by Markus Schlegel. Interior steel stud framed walls and hardlids for phase 2 ok.
|
BLD-Final | 4/21/2020 | 4/22/2020 | 4/22/2020 | A | PART |
Mike Jordan
|
|
|
Requesting an inspection after the Fire Alarm ; Fire Life Safety inspection is complete tomorrow morning. Thank you, Phone #: ###-#### Inspection requested via web by Markus Schlegel. Temp occ. ok for phase 1 only ok to occupy.
|
FIRE-Final Inspection | 4/21/2020 | 4/22/2020 | 4/22/2020 | A | PART |
Troy Cobbley
|
|
|
Life safety for phase 1 passed. Fire sprinkler and fire alarm complete.
Requesting an inspection after the Fire Alarm inspection is complete tomorrow morning. Thank you, Phone #: ###-#### Inspection requested via web by Markus Schlegel
|
BLD-Final | 4/20/2020 | 4/21/2020 | 4/21/2020 | A | CANC |
Mike Jordan
|
|
|
Requesting a late morning Building Final for Temp CofO Phase 1 Fire Alarm Inspection is at 7am Fire Life Safety is scheduled for after. Phone #: ###-#### >> Inspection requested via web by Markus Schlegel Inspection cancelled from web by: Markus Schlegel
|
FIRE-Final Inspection | 4/20/2020 | 4/21/2020 | 4/21/2020 | A | CANC |
Troy Cobbley
|
|
|
Final Fire Life Safety Phase 1 after Fire Alarm Inspection at 7am Phone #: ###-#### >> Inspection requested via web by Markus Schlegel Inspection cancelled from web by: Markus Schlegel
|
BLD-Ceiling Grid Inspection | 4/1/2020 | 4/2/2020 | 4/2/2020 | P | PASS |
Mike Jordan
|
|
|
Phase 1 only. Phone #: ###-#### Inspection requested via web by Markus Schlegel. Phase 1 grid ok.
|
BLD-Ceiling Grid Inspection | 3/23/2020 | 3/24/2020 | 3/24/2020 | A | CANC |
Mike Jordan
|
|
|
Requesting a late morning inspection on exam rooms and offices on the north ; east side of phase 1. Thank you Phone #: ###-#### Inspection requested via web by Markus Schlegel
|
BLD-Framing/Rough-in | 3/18/2020 | 3/18/2020 | 3/18/2020 | P | PASS |
Mike Jordan
|
|
|
Interior wall and soffit framing in Hall H11 ; Room 105. Phone #: ###-#### Inspection requested via web by Markus Schlegel
|
BLD-Framing/Rough-in | 3/17/2020 | 3/19/2020 | 3/18/2020 | P | CANC |
Mike Jordan
|
|
|
Interior soffit & wall framing in team center room 105 & Hall H11. Phone #: ###-#### >> Inspection requested via web by Markus Schlegel Inspection cancelled from web by: Markus Schlegel
|
BLD-Framing/Rough-in | 3/9/2020 | 3/10/2020 | 3/10/2020 | A | PART |
Mike Jordan
|
|
|
Interior framing w/ structural steel elements and 3 exterior window framing additions. Phone #: ###-#### Inspection requested via web by Markus Schlegel. Phase 1 interior steel stud framed walls and hardlid ok pending electrical and plumbing rough in inspections. Also structural steel columns and beams in phase 1 require special inspection. Noted bolt holes are over sized and will require plate washers.
|
BLD-Footing | 2/10/2020 | 2/11/2020 | 2/11/2020 | A | PASS |
Mike Jordan
|
|
|
Footing in crawl space. Can be viewed from floor above. Phone #: ###-#### Inspection requested via web by Markus Schlegel. Interior column pad footing in crawl space ok.
|
BLD-Final | 8/13/2020 | 8/14/2020 | | A | |
Mike Jordan
|
|
|
Requesting a building final in Phase 3A. Please contact Markus Schlegel if you have questions. Phone #: ###-#### >> Inspection requested via web by Markus Schlegel
|