BLD-Final | 7/20/2020 | 7/20/2020 | 7/20/2020 | P | PASS |
Mike Jordan
|
|
|
Looking for our final on the second and last phase.
Phone #: ###-#### Inspection requested via web by Drew Moorhouse
|
DOC - Permit Finaled | 7/20/2020 | 7/20/2020 | 7/20/2020 | P | PASS |
Mike Jordan
|
|
|
|
BLD-Final | 7/9/2020 | 7/10/2020 | 7/10/2020 | A | NR |
Mike Jordan
|
|
|
Looking for our final inspection in the 2nd (last phase). I would like to meet you onsite if possible.
Thanks, Dana Phone #: ###-#### Inspection requested via web by Drew Moorhouse. Needs to complete flooring. Everything else ok.
|
FIRE-Final Inspection | 7/8/2020 | 7/9/2020 | 7/9/2020 | A | PASS |
Troy Cobbley
|
|
|
Life safety passed.
We are Looking for the fire/life safety final on the second and final phase of the project. I would like to meet you onsite if available.
Thanks Dana McCarter ###-#### Phone #: ###-#### Inspection requested via web by Drew Moorhouse
|
BLD-Framing/Rough-in | 6/3/2020 | 6/4/2020 | 6/4/2020 | A | PART |
Mike Jordan
|
|
|
I would like to meet you onsite to review.
Thanks,
Dana McCarter ###-#### Phone #: ###-#### Inspection requested via web by Drew Moorhouse. Framing for phase 2 is ok. Architect will need to upload a plan mod for suite 120 and an additional permit for suite 200.
|
BLD-Final | 5/27/2020 | 5/27/2020 | 5/27/2020 | P | PART |
Mike Jordan
|
|
|
We are looking for a final for phase one. I would like to meet you there. Phone #: ###-#### Inspection requested via web by Drew Moorhouse. Ok to occupy the two new exam rooms only.
|
FIRE-Final Inspection | 5/26/2020 | 5/27/2020 | 5/27/2020 | A | PART |
Troy Cobbley
|
|
|
Life safety passed for Exam Rooms 1 and 2 which are phase 1.
We are trying to final out the first phase (two rooms) it order for the client to move to that side to be able to begin the second phase.
Thanks, Dana Phone #: ###-#### Inspection requested via web by Drew Moorhouse
|
BLD-Final | 5/26/2020 | 5/26/2020 | 5/26/2020 | P | NR |
Mike Jordan
|
|
|
We are Looking to final out two rooms as we are doing this TI in phases and the clients need to move over to this side to begin the next phase. I would like to meet you onsite to review.
Thanks, Dana McCarter ###-#### Phone #: ###-#### Inspection requested via web by Drew Moorhouse. Needs fire/life/safety first.
|
BLD-Framing/Rough-in | 4/1/2020 | 4/2/2020 | 4/2/2020 | A | PASS |
Mike Jordan
|
|
|
We are looking for a framing inspection on the first phase of the Ti. I am happy to meet onsite to review. Thanks, Drew Moorhouse McCarter-Moothouse ###-#### Phone #: ###-#### Inspection requested via web by Drew Moorhouse. Interior steel stud framed walls only for exam rooms 101 and 102.
|