Final | 9/3/2019 | 9/4/2019 | 9/4/2019 | A | PASS |
Tom Saunders
|
|
|
please cal 20 mins ahead- John Phone #: ###-####...job complete..ok to final...card signed
|
Final | 8/13/2019 | 8/13/2019 | 8/13/2019 | P | PART |
Tom Saunders
|
|
|
John Phone #: ###-####... remaining for complete final ...laundry room, breakroom D/W, and xray machine wiring
|
Final | 6/11/2019 | 6/12/2019 | 6/12/2019 | A | PART |
Tom Saunders
|
|
|
Phone #: ###-####... partial final for hospital area only allowing furniture to be moved in only
|
Conference | 6/11/2019 | 6/11/2019 | 6/11/2019 | P | PASS |
Tom Saunders
|
|
|
John Phone #: ###-####... discussed requirement for partial final so furniture can be moved in ....certain areas be inspected and listed off
|
Electrical Rough-In | 5/14/2019 | 5/14/2019 | 5/14/2019 | P | PASS |
Rock A. Hudson
|
|
|
ceiling // JOhn Phone #: ###-#### Level 2 grid rough in ok cover
|
Electrical Rough-In | 5/13/2019 | 5/13/2019 | 5/13/2019 | P | NH |
Rock A. Hudson
|
|
|
John-ceiling Phone #: ###-#### Called, no answer, left message, recall when accessible.
|
Electrical Rough-In | 5/3/2019 | 5/3/2019 | 5/3/2019 | P | PASS |
Rock A. Hudson
|
|
|
John- ceiling electrical inspection Phone #: ###-#### Hospital side grid, all except storage room. Exam or surgical lights have support system in but not luminaires. Rest of grid in this area rough in ok cover
|
Electrical Rough-In | 4/29/2019 | 4/29/2019 | 4/29/2019 | P | PASS |
Tom Saunders
|
|
|
ceiling // John Phone #: ###-####... shelter area grid...ok to cover
|
Permanent Service | 4/25/2019 | 4/25/2019 | 4/25/2019 | P | PASS |
Tom Saunders
|
|
|
John Phone #: ###-####... p/s u/g ok to switch feeds at transformer
|
Electrical Rough-In | 4/2/2019 | 4/2/2019 | 4/2/2019 | P | PASS |
Tom Saunders
|
|
|
John Phone #: ###-####... ok to cover garage walls and hospital reception
|
Electrical Rough-In | 2/19/2019 | 2/19/2019 | 2/19/2019 | P | PASS |
Tom Saunders
|
|
|
John Phone #: ###-####... ceiling in training area and exterior soffits ok to cover
|
Conference | 2/7/2019 | 2/7/2019 | 2/7/2019 | P | PASS |
Tom Saunders
|
|
|
John Phone #: ###-####... discussed panel room and location of underground feeds vs panel
|
Electrical Rough-In | 1/15/2019 | 1/15/2019 | 1/15/2019 | P | PASS |
Tom Saunders
|
|
|
Ceiling- John Phone #: ###-####.... ceiling areas and wall areas as marked on electrical plans
|
Electrical Rough-In | 8/23/2018 | 8/23/2018 | 8/23/2018 | P | PASS |
Tom Saunders
|
|
|
underground for pole lights....remaining underground for perrimeter pole lights-20
|
Electrical Rough-In | 8/20/2018 | 8/20/2018 | 8/20/2018 | P | PASS |
Eric Story
|
|
|
underground // John Phone #: ###-#### u/g west end of builfding for parking lot light ok to cover
|
Electrical Rough-In | 8/6/2018 | 8/7/2018 | 8/7/2018 | A | PASS |
Eric Story
|
|
|
Partial // John Phone #: ###-#### Hospital area and upstairs ok to cover
|
Electrical Rough-In | 6/6/2018 | 6/6/2018 | 6/6/2018 | P | CANC |
Tom Saunders
|
|
|
underground- John Phone #: ###-####
|
Conference | 4/23/2018 | 4/24/2018 | 4/24/2018 | A | PASS |
Tom Saunders
|
|
|
John Phone #: ###-####...discussed feeding main lug panel. wire sizing, and lug rating..questioning circuit sizing for lighting loads, requesting verification of amp draw per fixture on each circuit
|
Electrical Rough-In | 2/21/2018 | 2/21/2018 | 2/21/2018 | P | PASS |
Tom Saunders
|
|
|
Underground - John Phone #: ###-####...underground for south slab and service feeds from transformer
|
Temporary Service | 2/14/2018 | 2/15/2018 | 2/15/2018 | A | PASS |
Tom Saunders
|
|
|
John Phone #: ###-####...t/s u/g new ok
This inspection moved to ELE17-04094, scheduled Temp Service on wrong permit. Added ufir underground to permit and re-open per Tom S 2/21/18 C_P
|