General Inspection | 7/21/2017 | 8/1/2017 | 8/2/2017 | P | PASS |
Andy J. Long
|
|
|
Demo phase complete. Activity now for Braves Athletic Complex and covered under ESC17-00513. This permit finaled.
|
DOC - Permit Finaled | 8/2/2017 | 8/2/2017 | 8/2/2017 | P | PASS |
Andy J. Long
|
|
|
|
General Inspection | 7/21/2017 | 7/21/2017 | 7/21/2017 | A | PASS |
Andy J. Long
|
|
|
WIP at Braves athletic complex. Entire area is graded and being prepped for topsoil. Some trench work occuring for utilities. Water tank and water truck on site for dust control and compaction. Using existing asphalt for stabilized construction entrance. Surround MS4 inlets have sediment bag protection. ESC permit posted at entrance. No corrections requested.
|
General Inspection | 5/17/2017 | 5/31/2017 | 5/31/2017 | P | PASS |
Melissa Jannusch
|
|
|
No WIP. BMPs are still installed. Will need dust control or stablization at site.
|
General Inspection | 5/17/2017 | 5/17/2017 | 5/17/2017 | P | PASS |
Andy J. Long
|
|
|
No trackout. Demolition of buildings now complete. Next inspection check for stabilization and temporary BMP removal (DI bags in surounding area)
|
General Inspection | 3/20/2017 | 3/20/2017 | 3/20/2017 | P | PASS |
Melissa Jannusch
|
|
|
Demolition in progress. No trackout. BMPs are maintained and ok. No corrections requested.
|
Site Preparation | 2/21/2017 | 2/21/2017 | 2/21/2017 | P | PASS |
Melissa Jannusch
|
|
|
Met with Ed on site. Silt fence, sign and DI bags are installed. Plans to use asphat driveway as construction entrance. Okay to start.
|