Information based on query as of Saturday, May 18, 2024.
Permit Information
Permit NumberESC16-01654
StatusFinaled
Name MATT FORRESTER
Site Address 400 W FORT ST
Project NameBSD Fort St. F&O demo
Customer Number 
ePlanReviewNo
Description
Demolition of 21 buildings on the former Boise School District operations campus. Site will be cleared of asphalt, limited utilities and concrete. Demoltion dust and materials should be managed and contained. ESC/SWPPP site map and narrative developed. BMPs include phasing of the project to preserve existing surface and stormwater percolation, perimeter silt fence and construction entrance per ESC site map. CGP tracking # provided at time of plan review MS4 inlet protection on Fort Street. Site preparation inspection is required, call 608-7070
Contact Information
See Activities list for contact information
Show All Activities
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
General Inspection7/21/20178/1/20178/2/2017PPASS
DetailsAndy J. Long
Demo phase complete. Activity now for Braves Athletic Complex and covered under ESC17-00513. This permit finaled.
DOC - Permit Finaled8/2/20178/2/20178/2/2017PPASS
DetailsAndy J. Long
General Inspection7/21/20177/21/20177/21/2017APASS
DetailsAndy J. Long
WIP at Braves athletic complex. Entire area is graded and being prepped for topsoil. Some trench work occuring for utilities. Water tank and water truck on site for dust control and compaction. Using existing asphalt for stabilized construction entrance. Surround MS4 inlets have sediment bag protection. ESC permit posted at entrance. No corrections requested.
General Inspection5/17/20175/31/20175/31/2017PPASS
DetailsMelissa Jannusch
No WIP. BMPs are still installed. Will need dust control or stablization at site.
General Inspection5/17/20175/17/20175/17/2017PPASS
DetailsAndy J. Long
No trackout. Demolition of buildings now complete. Next inspection check for stabilization and temporary BMP removal (DI bags in surounding area)
General Inspection3/20/20173/20/20173/20/2017PPASS
DetailsMelissa Jannusch
Demolition in progress. No trackout. BMPs are maintained and ok. No corrections requested.
Site Preparation2/21/20172/21/20172/21/2017PPASS
DetailsMelissa Jannusch
Met with Ed on site. Silt fence, sign and DI bags are installed. Plans to use asphat driveway as construction entrance. Okay to start.