Permit Information
Permit NumberESC17-00526
StatusFinaled
Name BRIAN ELLSWORTH
Site Address 625 N WHITEWATER PARK BLVD
Project NameEsther Simplot Restroom Constr
Customer Number 
ePlanReviewNo
Description
New restroom construction at Esther Simplot Park
Contact Information
See Activities list for contact information
Show All Activities
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
DOC - Permit Finaled5/22/20185/22/20185/22/2018PPASS
DetailsMichael Zawacki
General Inspection5/7/20185/7/20185/7/2018 PASS
DetailsMichael Zawacki
Building and landscaping complete. Will close permit adter all others closed.
General Inspection4/6/20184/6/20184/6/2018 PASS
DetailsMichael Zawacki
Building complete, fence and job trailer gone. Area surrounding building still exposed and needs landscaping. Talked with EKC on site, landscaping is scheduled for Monday.
General Inspection2/28/20182/28/20183/2/2018 PASS
DetailsAndy J. Long
WIP on new bathroom facility. No sediment runoff around perimeter, grassy strip preserved. no trackout . Trash is contained. Permits on site.
General Inspection1/23/20181/23/20181/23/2018PPASS
DetailsMichael Zawacki
Everything contained to work area. Greenbelt was cleaned where a delivery went through. Garbage taken care of, dumpster on site. No runoff towards ponds.
General Inspection12/18/201712/18/201712/18/2017PPASS
DetailsAndy J. Long
WIP on new restrooms. Site is fenced in and has wattles installed on south limit of disturbance. Staging area is clean and free of spills. No violations observed.
General Inspection11/29/201711/29/201711/29/2017PPASS
DetailsMichael Zawacki
Perimeter controls installed and working. Site is clean. Ecopan is full, project manager said he will call them to get maintenance.
General Inspection10/31/201710/31/201710/31/2017PPASS
DetailsAndy J. Long
WIP on new bathroom facility foundation. Permit sign posted, utilizing Ecopan concrete washout.

No trackout from site, perimeter controls install between project and Quinn's Pond. No corrections needed.
General Inspection9/7/20179/28/201710/5/2017ACANC
DetailsAndy J. Long
Site Preparation9/6/20179/6/20179/7/2017PPASS
DetailsAndy J. Long
Brad ###-####

ESC permit sign posted on SWPPP board. Existing parking lot to be used for stabilized access. Dumpster onsite for trash, will preserve existing turf around perimeter in addition to perimeter control wattles in between project and Quinn's Pond path.

As the project extends towards west of construction limits, crew will install additional wattle.

Approved for construction.