General Inspection | 7/10/2018 | 7/10/2018 | 7/10/2018 | | CANC |
Michael Zawacki
|
|
|
|
DOC - Permit Finaled | 7/10/2018 | 7/10/2018 | 7/10/2018 | P | PASS |
Michael Zawacki
|
|
|
|
General Inspection | 6/21/2018 | 6/21/2018 | 6/21/2018 | | PASS |
Michael Zawacki
|
|
|
Yard is landscaped and stable. South east hill is exposed, may be on neighboring parcel. Will monitor for runoff from home.
|
General Inspection | 6/4/2018 | 6/4/2018 | 6/4/2018 | | PASS |
Michael Zawacki
|
|
|
Site not yet landscaped. No ESC issues.
|
General Inspection | 5/3/2018 | 5/17/2018 | 5/18/2018 | A | PASS |
Michael Zawacki
|
|
|
Exterior work complete. Topsoil has been spread on lot. No one parking on lot, all workers using street parking.
|
General Inspection | 5/3/2018 | 5/3/2018 | 5/3/2018 | | PASS |
Andy J. Long
|
|
|
WIP on interior, perimeter wattles installed. Site using adjacent lot for parking, construction entrance rock installed. No violations observed.
|
General Inspection | 9/22/2017 | 9/22/2017 | 9/22/2017 | P | PASS |
Andy J. Long
|
|
|
BMPs installled. No trackout or sediment runoff from site.
|
Site Preparation | 8/3/2017 | 8/3/2017 | 8/3/2017 | P | PASS |
Andy J. Long
|
|
|
Aitor Phone #: ###-####
BMPs installed - silt fence on downhill side of lot, perimeter sediment control. DI bag installed previously by subdivision developer on Clubview. Homeowner, builder, and RP familiar with ESC permit condtions and will maintain as necessary. Concrete washout provided on bottom right lot in Somerset # 6
Approved for construction, permit sign posted.
|