General Inspection | 2/20/2019 | 2/20/2019 | 2/26/2019 | | CANC |
Michael Zawacki
|
|
|
|
DOC - Permit Finaled | 2/26/2019 | 2/26/2019 | 2/26/2019 | P | PASS |
Michael Zawacki
|
|
|
|
General Inspection | 2/1/2019 | 2/1/2019 | 2/1/2019 | | PART |
Michael Zawacki
|
|
|
Homeowner said they are working on backfill. Some light trackout.
|
General Inspection | 11/16/2018 | 11/16/2018 | 11/16/2018 | P | PASS |
Michael Zawacki
|
|
|
Waiting on final stabalization.
|
General Inspection | 10/15/2018 | 10/15/2018 | 10/15/2018 | P | PASS |
Michael Zawacki
|
|
|
Work complete, wattle on downhill perimeter, hillside hydroseeded. Will continue to monitor after rain events.
|
General Inspection | 8/23/2018 | 8/23/2018 | 8/23/2018 | A | PASS |
Michael Zawacki
|
|
|
Pool crew on site. Area is contained, BMPs still in place. No ESC issues.
|
General Inspection | 7/11/2018 | 7/11/2018 | 7/11/2018 | P | PASS |
Michael Zawacki
|
|
|
WIP. Pool is poured, pool building is all framed. washout has overflowed, I let worker at site know it needs to be cleaned and replaced before any new concrete work. All material is staying in work area.
|
General Inspection | 5/3/2018 | 5/17/2018 | 5/17/2018 | P | PASS |
Michael Zawacki
|
|
|
SWPPP sign and broom at entrance.Met with builder, no issues from rain event.
|
Site Preparation | 5/3/2018 | 5/3/2018 | 5/3/2018 | A | PASS |
Andy J. Long
|
|
|
Call prior to going Phone #: 2088598694 >> Inspection requested via mobile web by Brad
Will utilize existing access to building site behind home. Onsite broom staged next to exit for regular sweeping. Downstream storm drain already has an old sediment bag installed with capacity. RP will monitor. Permit sign posted.
Concrete washout provided on flat area at end of drive. Will install sediment control wattles around stockpiles and along the base of access drive where there is a potential for runoff to go over neighbors wall.
Approved for construction.
|