Site Final | 10/7/2019 | 10/7/2019 | 10/7/2019 | P | PASS |
Andy J. Long
|
|
|
Home landscaped/stabilized. Subdivision RP to remove temporary BMPs
|
General Inspection | 4/9/2019 | 4/12/2019 | 4/15/2019 | A | FAIL |
Michael Zawacki
|
|
|
RP is aware and already ordered sweeper and new washout. Lot's of tracking on road, few trailers on site with muddy tires. Lot's of blown trash along northern perimeter and into open lands. Eaglewood homes on prosperity has mini excevator on site dumping straight onto sidewalk, other homes with stored backfill without builder sign out front. Large pile of landscape rock stored on Wagon Wheel.
|
General Inspection | 4/2/2019 | 4/3/2019 | 4/9/2019 | A | PEND |
Andy J. Long
|
|
|
|
Site Preparation | 3/29/2019 | 4/1/2019 | 4/2/2019 | A | PASS |
Andy J. Long
|
|
|
Review site to remove SWO. Permission granted for drywall work to occur this weekend.
SWO removed. Site cleaned up and fencing re-installed. Warning to not trespass into the open space easement.
|
Stop Work Order | 3/28/2019 | 3/28/2019 | 3/28/2019 | P | FAIL |
Andy J. Long
|
|
|
SWO posted on door.
-pick up all loose trash - sweep gutter - prohibit access to desert by closing open fence section. - pay re-inspection fee to PDS Permit Desk - schedule for inspection once all corrections complete.
|
BMP Violation | 3/28/2019 | 3/28/2019 | 3/28/2019 | P | FAIL |
Andy J. Long
|
|
|
- Loose trash and debris blowing around site. - fence to desert open space is open, evidence of damage to vegetation and dirt dumping. - Dirt in gutter.
Site under an NOV.
Stop Work Order issued.
|