Site Final | 4/4/2019 | 4/5/2019 | 4/5/2019 | P | PASS |
Andy J. Long
|
|
|
Work complete, area stabilized. Approved.
|
General Inspection | 1/22/2019 | 1/22/2019 | 1/23/2019 | P | PASS |
Michael Zawacki
|
|
|
Rockwork and channel armoring completed. Willows have been planted. Fill being placed and compacted on slopes, will all be landscaped. Backfill materials stored in park.
|
General Inspection | 1/7/2019 | 1/7/2019 | 1/11/2019 | P | PASS |
Andy J. Long
|
|
|
no construction activity yet. Equipment staged in parking lot.
|
Site Preparation | 12/24/2018 | 12/26/2018 | 12/27/2018 | A | DEFR |
Michael Zawacki
|
|
|
Left message with contractor. Stopped by location and didn't see any equipment or work.
|
Site Preparation | 12/24/2018 | 12/24/2018 | 12/24/2018 | P | CANC |
Andy J. Long
|
|
|
RP called to notify construction is to begin on Wednesday
|
Site Preparation | 12/18/2018 | 12/18/2018 | 12/18/2018 | P | PEND |
Andy J. Long
|
|
|
Pre-construciton site meeting conducted last week. Work has not yet started. RP Rusty to notify when BMPs are installed.
|