Permit Information
Permit NumberESC19-00148
StatusFinaled
Name CITY OF BOISE (BOISE PARKS & RECREA
Site Address 3206 W PLEASANTON AVE
Project NameQuinnsPond freshwater intake
Customer Number 
ePlanReviewNo
Description
Project to install new freshwater intake for Quinn's Pond. Include post installation bank stabilization per project sheets. ESC site preparation inspection and final are required. ESC plan approved. Operator is Falvey's LLC. Site access via 3150 W Main Street. Staging area in paved asphalt area.
Contact Information
See Activities list for contact information
Show All Activities
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
Site Final4/9/20194/9/20194/9/2019PPASS
DetailsAndy J. Long
ECB has been properly reinstalled. Site cleaned up, equipment or disturbed area. Permit paid for, ESC permit conditions satisfied.
Site Final4/4/20194/5/20194/8/2019ANR
DetailsAndy J. Long
Erosion control blanket has now been installed with an anchor trench at top of slope per installation instructions. No new corrections. Permit not ready for final until paid for by PW, invoice sent.
General Inspection3/11/20193/11/20193/12/2019PPASS
DetailsMichael Zawacki
Work complete and stabalization in progress. People are using area to access river and walking on exposed soils.