General Inspection | 7/21/2020 | 7/21/2020 | 7/22/2020 | | PASS |
Michael Zawacki
|
|
|
Footings have been poured, worker was placing backfill in. Crew on site setting forms, did not see a washout or any dumped washout on site. Site has no issues.
|
General Inspection | 6/3/2020 | 6/3/2020 | 6/3/2020 | | PASS |
Michael Zawacki
|
|
|
No workers on site, gates locked, inspection was from perimeter looking in. A few footings poured, lots of rebar on site. Lot is all contained, inlets along Front are protected.
|
General Inspection | 3/2/2020 | 3/19/2020 | 3/24/2020 | P | PASS |
Andy J. Long
|
|
|
WIP on foundation. Concrete washout pan onsite. No trackout from site, receiving storm drains have sediment protection.
|
Site Preparation | 2/28/2020 | 3/2/2020 | 3/2/2020 | A | PASS |
Andy J. Long
|
|
|
11 AM
Onsite meeting with site stormwater team. ESC permit posted, RP designated. Review ESC site plan. Site is approved for construction.
Correction request/action items to check for next inspection: - install sediment protection on storm drain inlet west of site on Front Street - keep 6th street staging area and pavement clean, add additional surface level storm drain protection to reduce maintenance of DI bag and add additional protection. Sugged bloksom fiber mat or sandbag/weighted wattle - have spill kit on site ASAP - designate location of ecopans for washout away from storm drain on level area - post additional ESC sign next to SWPPP box - relocate portapots > 50 ft from storm drain. - prevent wind blown trash from site
|
Site Preparation | 2/24/2020 | 2/24/2020 | 2/28/2020 | P | CANC |
Andy J. Long
|
|
|
rescheduled
|