Permit Information
Permit NumberESC20-00004
StatusIssued
Name AMY FARRIS
Site Address 200 S LATAH ST
Project NameJEFFERSON ELEMENTARY CAFETERIA
Customer Number 
ePlanReviewNo
Description
Construction of a new free standing Cafeteria and Kitchen to serve the existing school.
Contact Information
See Activities list for contact information
Show All Activities
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
General Inspection8/11/20208/11/20208/12/2020PPASS
DetailsAndy J. Long
WIP. Minor trackout. Pouring concrete. Follow up scheduled to check on concrete washout BMP used at site.
Tracking Control7/2/20207/3/20207/2/2020PPASS
DetailsAndy J. Long
3 pm

Trackout has been cleaned up and street swept. Construciton entrance is angular rock, correct length, and has an under lining. Soure of mud is disturbed area adajecnt to exising asphalt entrance. RP lined area with cones. Next week construction/stabilization of this area will begin. Walked site to check for any trouble or ponding spots haul traffic should avoid.

ESC permit sign posted. Trackout fine issued paid. Parcel hold can be removed.
Tracking Control7/1/20207/1/20207/1/2020PFAIL
DetailsAndy J. Long
Trackout within paved site access and out to Latah. No ESC permit sign, no construction entrance. NO clean up after trackout.

ESC special site fee assessed and parcel hold placed on site for all BLD and trade inspections until construction entrance is installed.
Tracking Control6/11/20206/11/20206/16/2020PPEND
DetailsAndy J. Long
Site was cleaned up last week with sweepig and maintenace of entrace. It is getting muddy again. Will continue to monitor site.
Tracking Control6/9/20206/11/20206/11/2020ACANC
DetailsAndy J. Long
Tracking Control6/9/20206/9/20206/9/2020PFAIL
DetailsAndy J. Long
Trackout within site stabilzed area and onto Latah Street northbound.

Final trackout warning issued. Correction requests:

- sweep up Latah Street
- sweep/rinse (if water can be contained onsite) exisitng asphalt within site
- refresh rock construction entrance
- prohibit employee parking in the dirt or mud, set up parking area on stabilized area

Follow up scheduled for Thursday morning.
Tracking Control6/3/20206/5/20206/4/2020PPASS
DetailsAndy J. Long
No construction activity. Park areas have revegetated well. Still monitoring the area between veterans pond and green bike path.

Will check with Boise Parks project manager to see if all work is complete.
Tracking Control5/29/20206/1/20206/3/2020PPEND
DetailsAndy J. Long
NO trackout to Latah. Interior pavement is still very dirty.

Notified Carlo they can rinse the road as long as the rinse water stays on site.

Posted ESC permit sign. Will follow up
Tracking Control5/28/20205/28/20205/29/2020PFAIL
DetailsAndy J. Long
Correction request to sweep up existing asphalt leading to construction area and work on improving trackpad.

Notified RP Amy. Follow up inspection scheduled.
Site Preparation4/1/20204/1/20204/2/2020PPASS
DetailsAndy J. Long
Contractor/RP provided photos of initial BMPs installed at site.

Approved for construction
General Inspection8/12/20208/14/2020 A 
DetailsAndy J. Long