INSP-Final Inspection | 1/16/2015 | 1/16/2015 | 1/16/2015 | P | PASS |
Forrest France
|
|
|
Correction items finished. Final walkthrough passed.
|
INSP-Final Inspection | 1/8/2015 | 1/8/2015 | 1/8/2015 | P | NR |
Forrest France
|
|
|
Items noted include; missing sprinkler at the north stairway top level, replace painted sprinkler, certify DCVA, missing caps at the FDC, secure control valve to rooftop hose connection, replace missing flow switch covers, install missing escutcheon at electrical room.
|
INSP-Final Inspection | 12/30/2014 | 1/6/2015 | 1/6/2015 | P | PART |
Forrest France
|
|
|
|
INSP-Sprinkler Rough-in | 12/19/2014 | 12/22/2014 | 12/22/2014 | P | PART |
Forrest France
|
|
|
OH work at the 1st, 2nd, 3rd and 4th floor corridors approved for cover. Need to provide vertical restraint at one armover and pendent 4th floor north end.
|
INSP-Conference | 12/12/2014 | 12/15/2014 | 12/15/2014 | A | PART |
Forrest France
|
|
|
Okay to cover fire sprinkler work at the 1st floor center corridor sheetrock lid ceiling. Discussed coverage at the 2nd, 3rd, and 4th floor mechanical rooms adjacent to the elevator equipment rooms.
|
INSP-Conference | 12/12/2014 | 12/15/2014 | 12/12/2014 | A | CANC |
Forrest France
|
|
|
Ken is your contact. Please call 1/2 hour before inspection. Phone #: ###-#### >> Inspection requested via web by Stan Beus Inspection cancelled from web by: Stan Beus
|
INSP-Conference | 11/18/2014 | 11/19/2014 | 11/19/2014 | A | DONE |
Forrest France
|
|
|
On site conference with general contractor regarding NFPA 13R 6.4.6.3.2.1, (2.2),(2.3) and table 6.4.6.3.4.2
|
INSP-Conference | 11/18/2014 | 11/18/2014 | 11/18/2014 | P | DONE |
Forrest France
|
|
|
Regarding obstructions to sprinkler coverage.
|
INSP-Sprinkler Rough-in | 11/12/2014 | 11/13/2014 | 11/13/2014 | A | PART |
Forrest France
|
|
|
Coverage at units where sprinklers are adjacent to surface mounted light fixtures to meet NFPA 13D 6.4.6.3.2.1, 6.4.6.3.2.2, 6.4.6.3.2.3.
|
INSP-Sprinkler Rough-in | 11/12/2014 | 11/12/2014 | 11/13/2014 | P | PART |
Forrest France
|
|
|
OH fire sprinkler work at three restrooms 1st floor south okay for cover. Coverage at soffit SE corner also approved for cover.
|
INSP-Sprinkler Rough-in | 9/25/2014 | 9/26/2014 | 9/26/2014 | A | PART |
Forrest France
|
|
|
Verified drops to pendent heads at 1st floor east side unit restrooms for sheetrock ceilings, eight locations. Need to fire stop at upper lid as discussed.
|
INSP-Sprinkler Rough-in | 9/9/2014 | 9/9/2014 | 9/9/2014 | A | PART |
Forrest France
|
|
|
Need to provide a plan modification for resubmittal due to field changes in pipe routing, coverage at the stairways and landings prior to permit final.
|
INSP-Sprinkler Rough-in/Hydro | 9/2/2014 | 9/3/2014 | 9/3/2014 | A | PART |
Forrest France
|
|
|
OH hydrostatic testing for the 1st thru 4th floors including the standpipe completed acceptable.
|
INSP-Sprinkler Rough-in | 8/28/2014 | 8/29/2014 | 8/29/2014 | A | PART |
Forrest France
|
|
|
|
INSP-Sprinkler Rough-in | 8/27/2014 | 8/28/2014 | 8/28/2014 | P | PART |
Forrest France
|
|
|
OH rough-in at 4th floor units. Noted exposed CPVC at the electrical/mechanical closet.
|
INSP-Sprinkler Rough-in | 8/22/2014 | 8/25/2014 | 8/25/2014 | A | PART |
Forrest France
|
|
|
Completed rough-in inspection for the third floor level apartment units. One missing head added while on site, upright at the mech/electrical closet okayed, need to relocate branchline at the SE unit away from metal edge at beam. Expansion joint needs finished. Plan mod required for changes to sprinkler coverage at the stairways all levels.
|
INSP-Sprinkler Rough-in/Hydro | 8/19/2014 | 8/19/2014 | 8/19/2014 | A | PART |
Forrest France
|
|
|
Inspection for standpipe completed. Need to provide seismic clearance at floor landings, install guage at the top level.
|
INSP-Sprinkler Rough-in | 8/11/2014 | 8/12/2014 | 8/19/2014 | P | PART |
Forrest France
|
|
|
OH rough-in at the second floor completed. Need to provide flushing cap at the south end main per plan note. Locations of sprinklers to meet obstruction criteria per NFPA 13 with regard to light fixtures and ceiling fans as discussed.
|
INSP-Sprinkler Rough-in | 8/8/2014 | 8/8/2014 | 8/8/2014 | A | PART |
Forrest France
|
|
|
Rough-in at 1st floor as noted
|
INSP-Sprinkler Rough-in | 8/6/2014 | 8/7/2014 | 8/7/2014 | A | PART |
Forrest France
|
|
|
Rough-in inspection for the 1st floor retail and live work units completed. Combustible concealed spaces to be sprinklered or meet NFPA 13 exceptions.
|