INSP-Final Inspection | 7/20/2016 | 7/20/2016 | 7/20/2016 | P | PASS |
Troy Cobbley
|
|
|
Permit finaled
|
INSP-Final Inspection | 7/5/2016 | 7/7/2016 | 7/7/2016 | P | PART |
Troy Cobbley
|
|
|
Todays inspection was just for the jet-X 2% Foam Test. The system was activated by the smoke detectors and from time of smoke detector activation to discharge of foam was 5 seconds. The entire floor area to the walls and to a minimum depth of 2'-6" was achieved with-in 60 seconds. TVFP will provide documentation for the concentration, water flow and quantity of foam used. Also they need to provide the fire pump certification documents prior to a final sign off.
|
INSP-Final Inspection | 7/5/2016 | 7/8/2016 | 7/5/2016 | A | CANC |
Troy Cobbley
|
|
|
Jet-X 2% Foam Test 9:00am TVFP Foreman Kerry Turner Phone #: ###-#### >> Inspection requested via web by Christophe Wilson Inspection cancelled from web by: Christophe Wilson
|
INSP-Sprinkler Rough-in/Hydro | 6/27/2016 | 6/28/2016 | 6/28/2016 | A | PASS |
Troy Cobbley
|
|
|
Remaining hydro tests passed. Pendants installed in Pump Room.
|
INSP-Sprinkler Rough-in | 6/27/2016 | 6/27/2016 | 6/27/2016 | P | PASS |
Troy Cobbley
|
|
|
Office area piping and pendants are complete. I noted one pendant head has been painted in the restroom accessible from the hanger. Heads in pump room not complete yet.
|
INSP-Supply line flush | 6/6/2016 | 6/10/2016 | 6/10/2016 | A | CANC |
Troy Cobbley
|
|
|
Rick Phone #: ###-####
|
INSP-Supply line flush | 6/6/2016 | 6/9/2016 | 6/9/2016 | P | PASS |
Troy Cobbley
|
|
|
Certification fo the two fire pumps passed today. Papaer work to be provided when finalized.
|
INSP-Sprinkler Rough-in/Hydro | 6/7/2016 | 6/8/2016 | 6/8/2016 | A | PASS |
Troy Cobbley
|
|
|
The overhead hydros for Foam Gen. System, Wet Hanger, Hose System and the Test Header side of the Pump Room piping passed inspection.
|
INSP-Sprinkler Rough-in | 5/26/2016 | 5/26/2016 | 5/26/2016 | P | PASS |
Troy Cobbley
|
|
|
See the city approved plans for two pendant heads on the upper level that are ok for cover.
|
INSP-Conference | 5/17/2016 | 5/17/2016 | 5/17/2016 | P | DONE |
Troy Cobbley
|
|
|
After dicussing lack of slope in the FIre Pump Room with Scott Arellano I spoke to the project superintendant about the floor slope issue and that there would be no final sign off on the life safety until the floor had been sloped as per previous discussions.
|
INSP-Sprinkler Rough-in | 5/16/2016 | 5/17/2016 | 5/17/2016 | A | PASS |
Troy Cobbley
|
|
|
Four pendant heads as marked on the drawings are ok for cover. I noted that the Fire Pump Room floor has not been sloped except for maybe a 1'-0" circle around the floor drain which is positioned next to the north wall. I spoke to the job superintendant again and deferred him to Scott Arellano.
|
INSP-Sprinkler Rough-in | 5/3/2016 | 5/3/2016 | 5/3/2016 | P | PASS |
Troy Cobbley
|
|
|
Pendant added in restroom. Piping is ok to cover
|
INSP-Sprinkler Rough-in | 4/28/2016 | 4/28/2016 | 4/28/2016 | P | PART |
Troy Cobbley
|
|
|
Rough-in for the Hanger area passed, just need bracing for the northwest foam diffusser finished up. General rough-in for the office area overhead piping is complete. Will need another rough-in inspection when all of the drops are cut/installed. Riser room/fire pump room is not complete. Need low point drain on the north main.
|