INSP-Final Inspection | 7/14/2017 | 7/17/2017 | 7/17/2017 | P | PASS |
Jim Page
|
|
|
Final fire sprinkler inspection for this area of work passed/complete.
|
INSP-Final Inspection | 7/13/2017 | 7/14/2017 | 7/14/2017 | A | FAIL |
Troy Cobbley
|
|
|
The fire alarm system was not ready to verify the tamper/flow/pressure switches, need system zone map, signage on door, and plan modifications showing the dry pipe valves used. Also missing the spare sprinkler cabinet. The forward flush test passed.
|
INSP-Sprinkler Rough-in/Hydro | 7/7/2017 | 7/7/2017 | 7/7/2017 | P | PASS |
Troy Cobbley
|
|
|
24 hour air test for system 1 and 2 passed
|
INSP-Sprinkler Rough-in | 7/5/2017 | 7/6/2017 | 7/6/2017 | A | PART |
Troy Cobbley
|
|
|
24 Hour Air test started at 8:00am with 46psi on the left system and 45 1/2psi on the right system.
|
INSP-Sprinkler Rough-in/Hydro | 6/30/2017 | 7/5/2017 | 7/5/2017 | A | PASS |
Troy Cobbley
|
|
|
System #1 and #2 overhead hydro tests passed
|
INSP-Supply line flush | 6/20/2017 | 6/21/2017 | 6/21/2017 | P | DONE |
Jim Page
|
|
|
Underground main line flush complete
|
INSP-Sprinkler Rough-in | 6/6/2017 | 6/7/2017 | 6/7/2017 | A | PASS |
Troy Cobbley
|
|
|
The exterior canopy at the south building, east end is complete and sprinkler rough-in passed. Piping can be covered.
|
INSP-Sprinkler Rough-in/Hydro | 5/30/2017 | 5/31/2017 | 5/31/2017 | A | PASS |
Troy Cobbley
|
|
|
The underground and system #2 hydro tests passed
|
INSP-Sprinkler Rough-in | 5/12/2017 | 5/12/2017 | 5/12/2017 | P | PASS |
Troy Cobbley
|
|
|
Underground cover passed. Piping has been mechanicaly restrained. Brian is going to also add concrete thrust blocks. Piping can be covered.
|
INSP-Sprinkler Rough-in | 5/9/2017 | 5/9/2017 | 5/9/2017 | P | PASS |
Troy Cobbley
|
|
|
The remaining tenting is complete for the north half of the building and the piping can be covered. The new canopy at the south end of the building still needs inspected when built.
|
INSP-Sprinkler Rough-in | 5/5/2017 | 5/8/2017 | 5/8/2017 | A | PASS |
Troy Cobbley
|
|
|
The remaining piping rough-in passed. Piping can not be covered until a tenting inspection has been scheduled
|
INSP-Sprinkler Rough-in | 4/27/2017 | 4/28/2017 | 4/28/2017 | A | PASS |
Troy Cobbley
|
|
|
Rough-in inspection passed for piping from the south end to the CMU wall as marked on the plans. Piping can be covered except around the sky lights. Mark is going to follow up on the need for sidewalls in the two sky lights.
|
INSP-Sprinkler Rough-in | 4/25/2017 | 4/26/2017 | 4/26/2017 | A | FAIL |
Troy Cobbley
|
|
|
Todays inspection was for another area for cover. I stopped inspection when I found missing uprights in canopy and different heads installed in building. Plans need to be provided/submitted that show the actual heads installed. I gave the ok to cover in the previous area where upright have been removed and batt insulation provided.
|
INSP-Sprinkler Rough-in | 4/13/2017 | 4/14/2017 | 4/14/2017 | A | PASS |
Troy Cobbley
|
|
|
See the city approved plans for location where piping can be covered as marked with todays date. Still need to view piping when the south canopy is built and need to view insulation in the combustible space as discussed.
|
INSP-Sprinkler Rough-in | 4/11/2017 | 4/11/2017 | 4/11/2017 | P | PART |
Troy Cobbley
|
|
|
Resubmitted plans have been approved for the area inspected yesterday but insulation has been installed that blocks the CC2 heads on two branchlines.
|
INSP-Sprinkler Rough-in | 4/11/2017 | 4/11/2017 | 4/11/2017 | P | PART |
Troy Cobbley
|
|
|
This inspection was actually performed on 4/10/17 but was input under the wrong permit number.
Rough to cover inspection passed for area marked on the city approved plans. I noted one missing sprig up that was being installed as I waited. East canopy has not been built or piping installed yet. Plans need to be resubmitted for approval showing the changing of the standard heads to the CC2's prior to more cover inspections being approved.
|