Information based on query as of Monday, May 13, 2024.
Permit Information
Permit NumberFIR17-00317
StatusFinaled
Name SHILO AUTOMATIC SPRINKLER CO
Site Address 1825 W BEACON ST
Project NameIDENTITY STUDENT HOUSING
Customer Number 
ePlanReviewYes
Description
[Identity Student Housing Apartments]
The fire sprinkler scope of work consists of a 5 story student housing building. Level one has I-A construction. Level 2 - 5 uses V-A construction. The garage area is OG 2 the residential areas are light hazard. All systems are wet. There is a triple snoot FDC with 4" pipe on Oakland St. An 8" C-900 UDG feeds a 6" Ames C200BFG backflow. Each floor is roughly 30,000 ft², therefore each floor has its own floor control valve and drains into a 2" gang drain. The garage portion, level 1, has steel pipe. Levels 2 - 5 is CPVC. There are 2 standpipes - one which is a combination standpipe. There is a roof hydrant at the top of the roof access hatch. There is a small section of attic space on level 4 protected by concealed space sprinklers. All of level 5 has an attic space protected by concealed space Sprinklers. Per the concealed space listing the attic spaces will have draft curtains separating the area into no more than 1000 ft² areas.

• The underground piping is under permit FIR17-00206
• This project uses the special City of Boise ordinance for five story pedestal building.
• This building is NOT a high rise.
• This building does required standpipes.

[BLD17-00091]
The NFPA 13 fire sprinkler system is used for occupancy, story increase, and for building area increase. To construct a 4 story wood framed apartment building (Type V-A construction) having a total of 94 dwelling units (total of 295 bedrooms) over a one story podium (Type I-A construction) having parking, assembly, storage, and office use on the grade level. This building will be 5 stories tall and will have a total floor area of about 143,400 square feet (31,225 square feet 1st story, 28,833 square feet 2nd story, 28,859 square feet 3rd story, 28,856 square feet 4th story, and 25,626 square feet 5th story). All dwelling units are required to comply as Type B dwelling units. At least 2 dwelling units are required to comply as Type A dwelling units. Work is to include concrete footings, concrete foundations, concrete shear walls, horizontal 3-hr fire-resistance-rated podium between the 1st and 2nd stories, an insulated suspended gypsum board ceiling installed below much of the podium, exposed insulation installed to the underside of the rest of the podium where there is no conditioned space below, rigid insulation installed on top of the podium where there is no conditioned space above, slab edge insulation, horizontal 1-hr dwelling unit separations, 1-hr dwelling unit separation walls, enclosed 1-hr fire-resistance-rated corridors, enclosed 2-hr fire-resistance-rated stairway enclosures, enclosed 2-hr fire-resistance-rated mechanical shafts, an enclosed 2-hr fire-resistance-rated trash chute (3-hrs on the 1st story), unenclosed pedestrian bridges, 1-hr wood stud exterior walls, 1-hr wood stud interior bearing walls, 1-hr wood joists floors, 1-hr wood truss roofs, exterior wall finishes, exterior windows, interior and exterior doors, millwork, and interior finishes. Special Inspection is required for soils, concrete (including prestressing tendons), steel (including welding and bolting), and seismic resistance. Wood roof trusses and the structural design for the pre-engineered metal pergola at the 5th story roof deck are deferred submittal items. The work is required to comply with the approved drawings, with the structural design, with the plan review report, and with all applicable codes and ordinances. The fire sprinkler system is required to comply with NFPA 13 and the fire alarm system is required to comply with NFPA 72 as regulated by the Fire Department. Separate fire sprinkler permits and fire alarm permits shall be obtained prior to beginning any modification or installation work on such systems. **CJW**
Contact Information
See Activities list for contact information
Show All Activities
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
INSP-Final Inspection5/30/20185/30/20185/30/2018PPASS
DetailsJim Page
Final fire sprinkler inspection complete.

Jon Beazer is the contact for this final inspection. Thank you. Phone #: ###-#### Inspection requested via web by Stan Beus
INSP-Final Inspection5/9/20185/14/20185/14/2018PPART
DetailsJim Page
Final fire sprinkler inspection for levels 2 through 5 complete, level 1 to be completed at a later date. Fire sprinkler heads in bike storage area on level 1 will need to have the insulation raised so it's not resting on the uprights or pendant heads will need to be installed before level 1 final.

Jon Beazer is the contact for this inspection. Thank you. Phone #: ###-#### Inspection requested via web by Stan Beus
INSP-Sprinkler Rough-in4/16/20184/16/20184/16/2018APASS
DetailsJim Page
Rough to cover inspection for remaining overhead fire sprinkler piping in garage complete, approved for cover. Rough to cover inspection for overhead fire sprinkler piping in trash shoot room complete, approved for cover.
INSP-Sprinkler Rough-in/Hydro4/13/20184/16/20184/16/2018ADONE
DetailsJim Page
Hydrostatic test witnessed for level 1 wet system and wet standpipe (Combo floor supply/standpipe has been completed) complete, no pressure loss observed at riser provided gauge.
INSP-Sprinkler Rough-in3/29/20183/30/20183/30/2018PPART
DetailsJim Page
Rough to cover inspection for overhead fire sprinkler piping above hardlids in elevator lobby/common area level 1 complete, approved for cover.
INSP-Sprinkler Rough-in3/28/20183/28/20183/28/2018PPART
DetailsJim Page
Rough to cover inspection for overhead fire sprinkler piping abover remaining hardlids in parking area complete, parking area approved for cover. Hardlids in common area level 1 approved for cover with exception to elevator lobby, elevator lobby to be inspected at a later date.
INSP-Sprinkler Rough-in/Hydro3/20/20183/21/20183/21/2018PPART
DetailsJim Page
Hydrostatic test complete for levels 2, 3, 4 and 5 overhead fire sprinkler piping as well as wet standpipe/floor supply for sprinklers witnessed, no pressure loss observed at contractor provided gauge at main riser. Level 1 and 6 inch wet standpipe to have hydrostatic test dome at a later date.
INSP-Sprinkler Rough-in3/15/20183/16/20183/16/2018APART
DetailsJim Page
Rough to cover inspection for overhead fire sprinkler piping located above hardlids on the east and south side of parking area complete, north side common area hardlids are complete, areas mentioned/inspected approved for cover. RTS-O sensors will need to be installed in the area around space heaters above parking garage hardlid to monitor temperature in case of heater failure, area above parking garage hardlids needs to be maintained at 40 degrees or higher at all times.
INSP-Conference3/1/20183/1/20183/1/2018PDONE
DetailsJim Page
Combustible concealed space around rooftop heater/fire place on the northeast side patio will either need to be made into a non-combustible space with sheetrock, space needs to be filled with non-combustible insulation or a fire sprinkler head will need to be added for proper fire sprinkler coverage.
INSP-Sprinkler Rough-in1/11/20181/12/20181/12/2018APART
DetailsScott Arellano
Rough-in inspection of NW rooms and corridor. 2nd floor sprinkler plans. OK to cover.
INSP-Sprinkler Rough-in1/4/20181/5/20181/5/2018APART
DetailsJim Page
Rough to cover inspection for level 2 overhead fire sprinkler piping complete (3rd floor from ground level), level 2 approved for cover.
INSP-Sprinkler Rough-in/Hydro12/21/201712/22/201712/22/2017APART
DetailsJim Page
Rough to cover inspection for level 3 overhead fire sprinkler piping complete (4th floor from ground level), level 3 approved for cover.
INSP-Sprinkler Rough-in10/18/201710/19/201710/19/2017APART
DetailsJim Page
Partial rough to ocver inspection complete, notated the city approved drawings with yellow highlighter/red ink area's approved for cover.
INSP-Sprinkler Rough-in9/12/20179/13/20179/13/2017PPART
DetailsJim Page
Rough to cover inspection for overhead fire sprinkler piping/pendant heads Level 3 Area 3 complete, Level 3 Area 3 approved for cover, city approved planes are notated with yellow highlighter area's that were inspected.
INSP-Sprinkler Rough-in8/21/20178/22/20178/22/2017PPART
DetailsJim Page
Partial rough to cover inspection for overhead fire sprinkler piping on level 2 complete (first level of apartments above parking level) Notated the city approved drawings with green highlighter/red ink area's approved for cover. Concealed combustible spaces highlighted in rough to cover area cannot be completely covered until area's are verified to be sheetrocked and made into a non-combustile concealed space (area's also marked with green highlighter and red ink on city approved sprinkler drawings with associated notes written on drawings)