Permit Information
Permit NumberFIR17-00771
StatusFinaled
Name JBL FIRE PROTECTION LLC
Site Address 10038 W OVERLAND RD
Project NamePad Thai Restaurant
Customer Number 
ePlanReviewYes
Description
[Pad Thai House Restaurant]
The fire sprinkler scope of work consists of an new 4” dry pipe system with 4” backflow preventer, supplied by 4”x85’± C-900 underground piping to protect a new restaurant with above and below protection.

[BLD17-03581]
Permit for the construction of a new 4,796 sq. ft. restaurant with work to include a concrete foundation, slab on grade floor, and wood framed type VB structure above along with related site improvements, per the approved plans. This building is fully fire sprinklered for A2 occupancy over 100. **JAR**

Alternative Materials and Methods:

• There are no AMM at this time.
Contact Information
See Activities list for contact information
Show All Activities
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
INSP-Final Inspection8/20/20188/21/20188/21/2018APASS
DetailsJim Page
Final fire sprinkler inspection complete.

John Phone #: ###-####
INSP-Final Inspection8/13/20188/15/20188/15/2018ACANC
DetailsTroy Cobbley
Johnathan Phone #: ###-####
INSP-Final Inspection8/13/20188/13/20188/13/2018PFAIL
DetailsTroy Cobbley
The project related fire alarm work does not have a permit. No testing performed.

Forward flush passed.


Johnathon Phone #: ###-####
INSP-Sprinkler Rough-in7/20/20187/23/20187/23/2018APASS
DetailsTroy Cobbley
Pendant head rough-in passed. Will need two pendants added for the space above the coolers or the area blocked off as discussed. Piping can be covered.


Jonathon Phone #: ###-####
INSP-Sprinkler Rough-in6/4/20186/5/20186/5/2018APASS
DetailsTroy Cobbley
24 hour air passed
INSP-Sprinkler Rough-in/Hydro6/4/20186/4/20186/4/2018PPART
DetailsTroy Cobbley
24 hour air test started at 3:40 with pressure as marked on guage.
INSP-Sprinkler Rough-in/Hydro4/24/20184/24/20184/24/2018PDONE
DetailsJim Page
Hydrostatic test for overhead fire sprinkler piping and FDC witnessed, no pressure loss observed at riser provided gauge.
INSP-Supply line flush4/17/20184/17/20184/17/2018PPASS
DetailsTroy Cobbley
The underground supply line flush passed.

Johnathon Phone #: ###-####
INSP-Sprinkler Rough-in4/11/20184/11/20184/11/2018PPASS
DetailsTroy Cobbley
Overhead rough-in passed. The piping above the hard lids can be covered. Another inspection will be required for the arm overs when the T-bar ceiling is installed.

Jonathan Phone #: ###-####
INSP-Sprinkler Rough-in/Hydro4/11/20184/11/20184/11/2018PPASS
DetailsTroy Cobbley
Supply line, underground hydro test passed
INSP-Sprinkler Rough-in1/23/20181/24/20181/24/2018PPASS
DetailsTroy Cobbley
Underground supply line is ok for cover.

Jonathan Phone #: ###-####