INSP-Final Inspection | 6/7/2018 | 6/8/2018 | 6/7/2018 | A | PASS |
Troy Cobbley
|
|
|
Permit finaled
|
INSP-Sprinkler Rough-in/Hydro | 6/4/2018 | 6/6/2018 | 6/6/2018 | A | PASS |
Troy Cobbley
|
|
|
Permit finaled
Contact Andrew Larson ###-#### 30 min. prior to 24 hr hydro test start please.
Thank YOU Phone #: ###-#### Inspection requested via web by Teri Cruickshank
|
INSP-Sprinkler Rough-in/Hydro | 6/1/2018 | 6/5/2018 | 6/5/2018 | A | PART |
Troy Cobbley
|
|
|
The 200lb overhead hydro for the pre-action system passed. The 24 hour air test was started at 9:30 with 45psi on the guage.
Contact Andrew Larson ###-#### 30 min prior to Hydro 24 hr Test start please.
Thank YOU Phone #: ###-#### Inspection requested via web by Teri Cruickshank
|
INSP-Sprinkler Rough-in/Hydro | 6/1/2018 | 6/4/2018 | 6/4/2018 | A | CANC |
Troy Cobbley
|
|
|
Rescheduled for tomorrow morning.
Contact Andrew Larson ###-#### 30 min prior to Hydro Test start please.
Thank YOU Phone #: ###-#### Inspection requested via web by Teri Cruickshank
|
INSP-Final Inspection | 5/29/2018 | 6/1/2018 | 6/1/2018 | P | FAIL |
Troy Cobbley
|
|
|
Need 200lb test and 24 hour air test and the interconnects with the fire alarm panel tested.
Contact Anrew Larson - ###-#### 30 Min prior to Fire Final Insp Start please.
Thank YOU Phone #: ###-#### Inspection requested via web by Teri Cruickshank
|
INSP-Sprinkler Rough-in | 5/23/2018 | 5/24/2018 | 5/24/2018 | P | PASS |
Troy Cobbley
|
|
|
The previous corrections have been made. Piping can be covered. There are no fire review comments on site. I will need these prior to a final sign off and all conditions, if any, will need to be met.
ontact Andrew Larson ###-#### 30 min prior to RTC Insp Start please
Thank YOU Phone #: ###-#### Inspection requested via web by Teri Cruickshank
|
INSP-Sprinkler Rough-in | 5/22/2018 | 5/23/2018 | 5/23/2018 | P | PART |
Troy Cobbley
|
|
|
Piping is ok to cover. I noted one pendant needs to be relocated near the front of the building and heads need to be added/relocated in two storage areas. I will check these heads at next inspection but piping can be covered.
Contact Andrew Larson - ###-#### 30 min prior to RTC Insp Start please.
Thank YOU Phone #: ###-#### Inspection requested via web by Teri Cruickshank
|
INSP-Sprinkler Rough-in | 5/1/2018 | 5/4/2018 | 5/4/2018 | A | PASS |
Troy Cobbley
|
|
|
Todays inspection was to verify hanger and earth quake bracing attachments so that the insulation backing can be installed. Not all areas had been completed so another inspection will be needed.
|
INSP-Sprinkler Rough-in | 4/2/2018 | 4/2/2018 | 4/2/2018 | P | CANC |
Troy Cobbley
|
|
|
Contact Hunter Anderson ###-#### 30 min prior to Partial RTC Insp start please Phone #: ###-#### >> Inspection requested via web by Teri Cruickshank Inspection cancelled from web by: Teri Cruickshank
|
INSP-Conference | 3/19/2018 | 3/19/2018 | 3/19/2018 | P | DONE |
Troy Cobbley
|
|
|
Leroy and I discussed the hangers. Per Scott Arellano the hangers need to meet code, whether it be current or the code under which they were originally installed.
|
INSP-Conference | 3/16/2018 | 3/16/2018 | 3/16/2018 | P | CANC |
Troy Cobbley
|
|
|
Contact Leroy Anderson ###-#### 30 Min prior to Consult start please.
Thank YOU Phone #: ###-#### Inspection requested via web by Teri Cruickshank
|