Permit Information
Permit NumberFIR18-00398
StatusFinaled
Name SHILO AUTOMATIC SPRINKLER CO
Site Address 2419 W FAIRVIEW AVE
Project NameADARE MANOR
Customer Number 
ePlanReviewYes
Description
(ADARE MANOR)(UNDERGROUND ONLY) QUICK PERMIT-SHILO WILL INSTALL APPROXIMATELY 321' OF 8" C900 AFTER A GATE VALVE, INSTALLED BY SUEZ. THE PIPE WILL LEAD TO A 8" STAINLESS STEEL IBR AND BRING WATER TO THE 4 WET SYSTEMS IN THE NEW BUILDING. SEE BLD17-02261 and BLD17-02262 This building is separated by a fire wall for allowable area. 4 stories, 148,045 total area, Type VB, 4 wet systems, Fire Pump
Contact Information
See Activities list for contact information
Show All Activities
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
INSP-Final Inspection9/5/20199/6/20199/6/2019PPASS
DetailsJim Page
Final inspection for underground supply complete.

Kenny Caldwell is the contact for this final inspection. Thanks for your help. Phone #: ###-#### Inspection requested via web by Stan Beus
INSP-Sprinkler Rough-in/Hydro4/22/20194/24/20194/24/2019ADONE
DetailsJim Page
Hydrostatic test for undergorund supply witnessed, no pressure loss observed.

Kenny Caldwell is the contact for this Hydro/Flush Inspection. We are hoping for an AM appointment and trying to coordinate with Stacey @ Suez. We appreciate your help. Have a great day. Phone #: ###-#### Inspection requested via web by Stan Beus
INSP-Supply line flush4/22/20194/24/20194/24/2019ADONE
DetailsJim Page
Underground main line flush complete.

Kenny Caldwell is the contact for this Hydro/Flush Inspection. We are hoping for an AM appointment and trying to coordinate with Stacey @ Suez. We appreciate your help. Have a great day. Phone #: ###-#### Inspection requested via web by Stan Beus
INSP-Sprinkler Rough-in4/19/20194/22/20194/22/2019ACANC
DetailsJim Page
No inspection performed, need an updated set of city approved draiwngs for future inspections, this request is cancelled per point of contact.

2nd, 3rd & 4th fl // Kenny Phone #: ###-####
INSP-Sprinkler Rough-in10/19/201810/22/201810/22/2018APASS
DetailsJim Page
Rough to cover inspection for remaining undergorund complete, approved for cover.

Bryan Collins is the contact for this underground rough to cover inspection. Thank you for your help. Phone #: ###-#### Inspection requested via web by Stan Beus
INSP-Sprinkler Rough-in5/30/20185/30/20185/30/2018PPART
DetailsJim Page
Underground inspection for IBR complete, IBR approved for cover, remaining underground to be installed at a later date.

Bryan Collins is the contact for this underground rough-in inspection. Thank you. Phone #: ###-#### Inspection requested via web by Stan Beus