Information based on query as of Saturday, May 18, 2024.
Permit Information
Permit NumberFIR18-00410
StatusFinaled
Name M2 AUTOMATION
Site Address 2601 N BOGUS BASIN RD
Project NameHealthwise FACP Replacement
Customer Number 
ePlanReviewYes
Description
Replace Existing 20 Year Old FACP & Detectors. Preemptive replacement prior to failure, Due to several recent CPU failures. This work does not appear to ba associated with a building permit.
Contact Information
See Activities list for contact information
Show All Activities
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
INSP-Final Inspection2/7/20192/8/20192/8/2019PPASS
DetailsJim Page
As builts are complete and approved, final fire alarm inspection complete.

We are good to go! -Neal Timmerman Phone #: ###-#### Inspection requested via web by Neal Timmerman
INSP-Final Inspection2/4/20192/6/20192/6/2019AFAIL
DetailsJim Page
Final inspection for fire alarm upgrade is complete. Noted on my 08NOV2018 inspection: Submit as-builts and have them ready for next inspection, as-buits have not been submitted to Lee as of this inspection, as builts need to be submitted. When as-builts are approved then permit can be finaled.

Would it be possible to do a 7:00 am inspection on Wednesday the 6th? -Jason ###-#### Phone #: ###-#### Inspection requested via web by Neal Timmerman
INSP-Final Inspection11/6/201811/8/201811/8/2018AFAIL
DetailsJim Page
Provide audio/visual devices on level 2 corridor that is missing, verify devices are in place on level 3 in same area. Provide notification in "Quite Room" on level 1. Integrate access control to fire panel for door release on general alarm. Stobe in level 3 conference room did not operate. Add notification to cover office area that is part of the common hallway area on levels 2 and 3. All devices in level 1 restrooms that have showers need to be weatherproof type devices, no seperation between showers and restroom area. Submit as-builts and have them ready for next inspection.

Hi Jim, I hope your feeling better. Just in case your not, Troy or Lee said they could do a 7:00 am start inspection Thursday if you cannot. I have made arrangements with Troy ; Lee just in case your still out or cannot do the early start. Let me know Thanks Mike Phone #: ###-#### Inspection requested via web by Neal Timmerman
INSP-Final Inspection10/30/201811/6/201811/6/2018ACANC
DetailsTroy Cobbley
Hi Jim If possible we would like to start the inspection at 7:00 am. Would you please call and let me know if that is doable? Thanks Mike Timmerman Phone #: ###-#### >> Inspection requested via web by Neal Timmerman

Mike will schedule a new date with the owner, as they need an early start and time to plan. Expecting Wednesday or Thursday morning at 7:00 am.