INSP-Final Inspection | 2/7/2019 | 2/8/2019 | 2/8/2019 | P | PASS |
Troy Cobbley
|
|
|
Permit finaled.
Phone #: ###-#### Inspection requested via web by Kyle Burgess
|
INSP-Final Inspection | 1/28/2019 | 1/29/2019 | 1/29/2019 | P | FAIL |
Troy Cobbley
|
|
|
Need as-builts/plan mods approved as previously requested. I did a walk through to verify the changes have been implemented. No other testing performed.
Please call 30 min prior so that I can meet onsite Phone #: ###-#### Inspection requested via web by Kyle Burgess
|
INSP-Final Inspection | 12/14/2018 | 12/17/2018 | 12/17/2018 | P | FAIL |
Troy Cobbley
|
|
|
Project is not ready for a final yet. During the initial walk through I found over spaced stobes and one area where new costruction, not shown on the plans, has caused spacing issues with the strobes. Contractor is going to provide as-builts with the modified candellas and addtional strobes required for the new construction. Also I noted to small rooms being used as open office areas that will require notificaiton. No other testing was performed.
Please call before arrival so I can plan to meet at site. Phone #: ###-#### Inspection requested via web by Kyle Burgess
|