Information based on query as of Sunday, May 19, 2024.
Permit Information
Permit NumberFIR18-00511
StatusFinaled
Name THORPE FIRE SPRINKLER SYSTEMS
Site Address 7402 W FAIRVIEW AVE
Project NameCVS/PHARMACY OVERHEAD SYSTEM
Customer Number 
ePlanReviewYes
Description
[CVS Pharmacy]
The fire sprinkler scope of work consists of new pharmacy/mercantile building with a mezzanine. The 6” underground supplies a 6” backflow preventer and 6” riser. The system is design as a 4”x2”x2” grid.

• The underground piping is under permit FIR18-00286
• The fire alarm is under permit FIR18-00304

[BLD17-02704]
The fire sprinkler system is used for fire area. Three buildings and the East end of an existing retail sales building will be demolished to accommodate this new development. To construct a 12,648 square foot building (14,476 square feet including the 1,828 square foot enclosed mezzanine) to be used as a pharmacy and for retail sales. Work is to include concrete footings, concrete foundations, concrete slab on grade with slab edge insulation, masonry exterior walls, insulation installed on the inside of the masonry exterior walls, EIFS installed on the outside of masonry exterior walls, steel roof joists, steel roof deck, insulation installed on top of the roof deck, a roof membrane, exterior windows, exterior doors, an exterior roll-up door at the receiving area, suspended acoustical ceilings, gypsum board soffits, a VRC (Vertical Reciprocating Conveyor) with shallow pit and gates, a horizontal sliding security grill at the pharmacy, a hatch and ladder to the roof, interior nonbearing walls, two toilet rooms accessible to the disabled, display shelves, millwork, and finishes. Mezzanine work includes concrete footings, steel columns, steel girders, steel beams, concrete floor on a steel deck, and a steel stairway. Special Inspection is required for soils, concrete, masonry, anchors post-installed in hardened concrete or masonry, welding, and EIFS. All of the storage and display shelves will be less than 8 feet high. The work is required to comply with the approved drawings, with the structural design, with the plan review report, and with all applicable codes and ordinances. This permit is intended to establish a Certificate of Occupancy for this tenant and for the entire building. The fire sprinkler system is required to comply with NFPA 13 and the fire alarm system is required to comply with NFPA 72 as regulated by the Fire Department. Separate fire sprinkler permits and fire alarm permits shall be obtained prior to beginning any modification or installation work on such systems. **CJW**

Alternative Materials and Methods:
This project includes approved code alternates to the following fire protection systems and/or building life safety systems. Please review the supplemental documents attached to this building permit case for details. Fire protection “shop drawings” shall include approved code alternate design.

• There are AMM on this project but they do not pertain to the fire protection.

Contact Information
See Activities list for contact information
Show All Activities
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
INSP-Final Inspection10/22/201810/22/201810/22/2018PPASS
DetailsTroy Cobbley
Permit finaled

Phone #: ###-#### Inspection requested via web by Anthony Minichiello
INSP-Supply line flush9/20/20189/20/20189/20/2018APASS
DetailsTim Frost
Flush and forward flush. Call Anthony to coordinate Phone #: ###-#### >> Inspection requested via web by Anthony Minichiello

_________
Flush was ok.
Forward flow test failed. Could not achieve 12 Psi:
INSP-Sprinkler Rough-in8/29/20188/30/20188/30/2018APASS
DetailsTroy Cobbley
The piping above the lay-in ceiling is ok to cover. Soffits for the drive through have been filled with insulation.


Rough inspection for t-bar ceiling area. Phone #: ###-#### Inspection requested via web by Anthony Minichiello
INSP-Sprinkler Rough-in8/17/20188/17/20188/17/2018PPART
DetailsJim Page
Rough in inspection complete for overhead fire sprinkler piping, sway bracing will need to be adjusted so the 4 ways are not connected together as discussed. Piping for pendant heads to be inspected at a later date.
INSP-Sprinkler Rough-in/Hydro8/16/20188/17/20188/17/2018PDONE
DetailsJim Page
Hydrostatic test for overhead fire sprinkler piping witnessed, no pressure loss observed at riser provided gauge.

Call Anthony before heading out, thanks! Phone #: ###-#### Inspection requested via web by Anthony Minichiello
INSP-Sprinkler Rough-in/Hydro8/6/20188/6/20188/6/2018APART
DetailsTroy Cobbley
A partial hydro for the piping below the mezzanine passed. Piping above the hardlids below the mezzanine are ok to cover. I will need verification that the wood is rated or piping will need to be modified for upright coverage.


Call Anthony to schedule, thanks! Phone #: ###-#### Inspection requested via web by Anthony Minichiello