Permit Information
Permit NumberFIR18-00609
StatusFinaled
Name VIKING AUTOMATIC SPRINKLER CO
Site Address 11522 W FAIRVIEW AVE
Project NameDaVinci Stone
Customer Number 
ePlanReviewYes
Description
[DaVinci Stone Warehouse Addition]
***Plan Mod for backflow change to Ames C200 Approved 1/8/2019 MAS***The fire sprinkler scope of work consists of building a new warehouse on the back of an existing store and fabrication shop. The existing building was not sprinklered. Install a wet pipe fire sprinkler system throughout the new warehouse as well as the existing store and fabrication shop. The entire building will be protected per NFPA 13, 2016.

[BLD17-04590]
The fire sprinkler system is used for building area increase, for fire area, and for fire flow. To construct a 7,161 square foot warehouse addition on the North end of an existing 10,010 square foot building. After the addition, this building will have a total floor area of about 17,171 square feet (18,078 square feet including the existing 907 square foot mezzanine). For the addition, work is to include concrete footings, concrete stem walls, concrete slab on grade, steel moment frames (beams and columns), steel columns, lateral bracing cables, steel roof purlins, steel roof panels, steel wall purlins, steel wall panels, an overhead door, and side-hinged swinging doors. A liner system with R-38 insulation, a vapor retarder installed on the warm in winter side of the insulation, and thermal spacers will be used to insulate the roof. The walls will be insulated with R-25 insulation with thermal break tape at the horizontal purlins and will have a vapor retarder installed on the warm in winter side of the insulation. Work to be done to the adjacent existing roof to support the added snow drift load includes additional steel purlins, purlin blocking, reinforcing steel plates welded to the top and/or bottom flange of existing steel beams, and additional bolts at existing beam splices. Special Inspection is required for concrete, steel (including bolting and welding), and anchors post-installed in hardened concrete. A new 8-foot-tall masonry trash enclosure will be constructed. A separate permit is required for racks over 8 feet tall. The work is required to comply with the approved drawings, with the structural design, with the plan review report, and with all applicable codes and ordinances. A fire sprinkler system will be installed throughout this building (existing and new addition) in conjunction with this permit. This permit is intended to establish a Certificate of Occupancy for the entire building, the existing building and the building addition. The fire sprinkler system is required to comply with NFPA 13 and the fire alarm system is required to comply with NFPA 72 as regulated by the Fire Department. Separate fire sprinkler permits and fire alarm permits shall be obtained prior to beginning any modification or installation work on such systems. **CJW**

Alternative Materials and Methods:
This project includes approved code alternates to the following fire protection systems and/or building life safety systems. Please review the supplemental documents attached to this building permit case for details. Fire protection “shop drawings” shall include approved code alternate design.

• There are no AMM at this time.
Contact Information
See Activities list for contact information
Show All Activities
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
INSP-Final Inspection1/15/20191/16/20191/16/2019APASS
DetailsTroy Cobbley
Permit finaled

Roy Phone #: ###-####
INSP-Final Inspection1/2/20191/4/20191/4/2019AFAIL
DetailsTroy Cobbley
Permit can be finaled when the new backflow has been approved by plan review.


Jeff Phone #: ###-####
INSP-Final Inspection12/19/201812/21/201812/21/2018AFAIL
DetailsJim Page
Flow switch did not activate with water flow.

Rough in and Final inspection. POC is Jeff Jeager Phone #: ###-#### Inspection requested via web by Brett Lawatch
INSP-Sprinkler Rough-in12/19/201812/21/201812/21/2018APASS
DetailsJim Page
Rough in inspection for overhead fire sprinkler piping complete.

Rough in and Final inspection. POC is Jeff Jeager Phone #: ###-#### Inspection requested via web by Brett Lawatch
INSP-Final Inspection12/7/201812/10/201812/10/2018ACANC
DetailsTroy Cobbley
Not ready for final yet.

As-Builts have been approved by Tim Frost. Insulation has bee fixed. Robert Mullins is Foreman on job. Phone #: ###-#### Inspection requested via web by Brett Lawatch
INSP-Sprinkler Rough-in12/7/201812/10/201812/10/2018APART
DetailsTroy Cobbley
See the city approved plans for locations that need corrections that include insulation blocking heads in the attic, insulation needs to be provided in one location and removed in another at the east exterior exit, it appears per the data sheet that the COIN heads have been installed correctly. Areas in question have been marked on the plans.


As-Builts have been approved by Tim Frost. Insulation has bee fixed. Robert Mullins is Foreman on job. Phone #: ###-#### Inspection requested via web by Brett Lawatch
INSP-Sprinkler Rough-in11/19/201811/19/201811/19/2018APART
DetailsTroy Cobbley
Need data sheets for the sprinkler heads to veriy their listed spacing/obstruction Phone #: ###-#### Inspection requirements. Need insulation removed from the BB1 heads in the attic. Need city approved plans for the changes/additions.

requested via web by Brett Lawatch
INSP-Sprinkler Rough-in/Hydro11/9/201811/13/201811/13/2018APART
DetailsTroy Cobbley
Overhead Rough-In is partially passed. See the city approved plans for corrections needed with some earthquake bracing. Also need ceilings removed to inspect the new sprinkler piping. As-builts will be required prior to a final sign off showing the riser being relocated and some small pipe size changes and new area being sprinklered. The overhead hydro inspection passed with no visible loss on the guage.. Cesar Rodriguez is Foreman Phone #: ###-#### Inspection requested via web by Brett Lawatch
INSP-Sprinkler Rough-in/Hydro11/8/201811/9/201811/9/2018PCANC
DetailsTroy Cobbley
Overhead Rough-in and Hydro inspection. Cesar Rodriguez is the foreman. Phone #: ###-#### >> Inspection requested via web by Brett Lawatch Inspection cancelled from web by: Brett Lawatch
INSP-Supply line flush11/1/201811/2/201811/2/2018ADONE
DetailsJim Page
Main line flush complete.

This is to flush and final the underground fire main, Cesar Rodriguez is the project foreman on site. UG was already rough-in/hydro tested on 10/10/18. Phone #: ###-#### Inspection requested via web by Brett Lawatch
INSP-Sprinkler Rough-in/Hydro10/9/201810/10/201810/10/2018APASS
DetailsTroy Cobbley
underground hydro test passed - Robert Phone #: ###-####
INSP-Sprinkler Rough-in/Hydro10/8/201810/9/201810/9/2018PPART
DetailsTroy Cobbley
Bury depth has been corrected. Underground supply piping can be covered. Not ready for hydro test yet.

Underground, 2hr hydro - Robert Phone #: ###-####
INSP-Sprinkler Rough-in/Hydro10/4/201810/5/201810/5/2018PFAIL
DetailsTroy Cobbley
The underground supply line is not buried deep enough. It appears to need atleast 6" more just as it is getting to the corner of the building and may need more where the 90 is to turn into the building. No hydro test performed


underground // Robert Phone #: ###-####