INSP-Final Inspection | 12/2/2019 | 12/3/2019 | 12/3/2019 | P | PASS |
Jim Page
|
|
|
Final fire sprinkler inspection complete.
Call James before heading out so he (or Anthony) can meet you there. Thank you! Phone #: ###-#### Inspection requested via web by Anthony Minichiello
|
INSP-Sprinkler Rough-in/Hydro | 9/17/2019 | 9/18/2019 | 9/18/2019 | A | DONE |
Jim Page
|
|
|
Re-hydro witnessed after pipe relocation, no pressure loss observed.
Re-Hydro. We had to cut out a line of pipe due to conflict with another trade, and reinstalled it under the stairs. Call Anthony before heading out. Phone #: ###-#### Inspection requested via web by Anthony Minichiello
|
INSP-Sprinkler Rough-in | 9/12/2019 | 9/12/2019 | 9/12/2019 | A | PASS |
Jim Page
|
|
|
Previously noted items have been corrected, all tenting in place at time of inspection, rough to cover inspection complete, cover is approved, approval sticker placed by sprinkler riser.
|
INSP-Sprinkler Rough-in/Hydro | 9/11/2019 | 9/12/2019 | 9/12/2019 | A | DONE |
Jim Page
|
|
|
Hydrostatic test for overhead fire sprinkler piping witnessed at city pressure, no pressure l;oss observed.
Call Anthony before heading out, thanks! Also Tenting inspection Phone #: ###-#### Inspection requested via web by Anthony Minichiello
|
INSP-Sprinkler Rough-in/Hydro | 9/9/2019 | 9/10/2019 | 9/10/2019 | P | FAIL |
Jim Page
|
|
|
Tenting not installed correclty in numerous areas, cover is not approved, hydro to be completed after vertical section of pipe in attic space is moved closer to sheetrock for freeze prevention.
Call James before heading out, thanks! Phone #: ###-#### Inspection requested via web by Anthony Minichiello
|